Bradley Corporate Park v. Crotty

39 A.D.3d 632, 835 N.Y.S.2d 254
CourtAppellate Division of the Supreme Court of the State of New York
DecidedApril 10, 2007
StatusPublished
Cited by11 cases

This text of 39 A.D.3d 632 (Bradley Corporate Park v. Crotty) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bradley Corporate Park v. Crotty, 39 A.D.3d 632, 835 N.Y.S.2d 254 (N.Y. Ct. App. 2007).

Opinion

[633]*633In a proceeding pursuant to CPLR article 78 to review a determination of Erin M. Grotty, Commissioner of the New York State Department of Environmental Conservation, dated June 18, 2001, which adopted the findings and conclusions of two Administrative Law Judges, made after a hearing, that the petitioners violated ECL article 24 and 6 NYCRR 663.4, and a related proceeding to review a determination of Erin M. Crotty, Commissioner of the New York State Department of Environmental Conservation, dated January 21, 2004, which adopted, in part, the findings and conclusions of an Administrative Law Judge, made after a separate hearing, and, among other things, imposed a penalty upon the petitioners in the sum of $120,000 and directed them to submit a remediation and restoration plan to the New York State Department of Environmental Conservation, the petitioners appeal, as limited by their brief, from stated portions of an order of the Supreme Court, Rockland County (Smith, J.), dated July 18, 2005, which, inter alia, transferred a portion of the proceedings to this Court to decide whether the determinations were supported by substantial evidence.

Ordered that the appeal is dismissed and the order is vacated; and it is further,

Adjudged that the determinations are confirmed, the petitions are denied, and the proceedings are dismissed on the merits; and it is farther,

Ordered that the petitioners’ time to pay the penalty is extended until 120 days after service upon them of a copy of this decision, order, and judgment; and it is further,

Ordered that the petitioners’ time to submit a remediation and restoration plan to the New York State Department of Environmental Conservation is extended until 90 days after service upon them of a copy of this decision, order, and judgment; and it is further,

Ordered that one bill of costs is awarded to the respondents.

Since the petitions raise a substantial evidence question, and the remaining points raised by the petitioners and disposed of by the Supreme Court were not objections that could have terminated the proceedings within the meaning of CPLR 7804 (g), the Supreme Court should have transferred the proceedings in their entirety to the Appellate Division (see Matter of Al Turi Landfill v New York State Dept. of Envtl. Conservation, 289 [634]*634AD2d 231 [2001], affd 98 NY2d 758 [2002]; Matter of Steck v Jorling, 219 AD2d 727, 727-728 [1995]). Nonetheless, since the record is before us, this Court will treat the proceedings as if they had been properly transferred here in their entirety (see Matter of Al Turi Landfill v New York State Dept. of Envtl. Conservation, supra at 231; Matter of Steck v Jorling, supra at 727-728).

The respondent Erin M. Crotty (hereinafter the Commissioner), who is the commissioner of the respondent New York State Department of Environmental Conservation (hereinafter the DEC), adopted the findings and conclusions of two Administrative Law Judges, made after a hearing, that the petitioners violated the Freshwater Wetlands Act (ECL art 24) by performing certain construction activities in a freshwater wetland, as well as on its “adjacent area” (6 NYCRR 663.2 [b]), without a DEC permit. The initial issue to be resolved is whether the record contains substantial evidence to support this determination. Determining whether substantial evidence exists requires a reviewing court to look at the entire record before the administrative agency and ascertain “whether sufficient proof exists from which ‘an inference ... of the [facts] found may be drawn reasonably’ and once it makes a determination as to this quantum of evidence—roughly that needed for a court to submit a question of fact to a jury—its task is complete” (Matter of Furey v County of Suffolk, 105 AD2d 41, 43 [1984], quoting Matter of Stork Rest, v Boland, 282 NY 256, 273 [1940] ; see also 300 Gramatan Ave. Assoc. v State Div. of Human Rights, 45 NY2d 176, 180-181 [1978]). “In the final analysis, it is not the function of the reviewing court to weigh the evidence or substitute its own judgment for that of an administrative body to whose expertise a subject matter has been entrusted, but rather to determine whether there is a ‘reasonable fulcrum of support in the record’ to sustain the body’s findings” (Matter of Furey v County of Suffolk, supra at 43-44, quoting Matter of Paulsen [Catherwood], 27 AD2d 493, 495 [1967]).

With these guidelines in mind, the testimony and exhibits from the administrative hearing must be reviewed to decide whether it was “so substantial” that the Commissioner could “reasonably” find that the petitioner’s construction site was within the wetland or its adjacent area (300 Gramatan Ave. Assoc. v State Div. of Human Rights, supra at 179-180). As correctly pointed out in the hearing report by the Administrative Law Judges, resolution of this issue largely turns on which of two lines depicting wetlands boundaries placed on the official map by the petitioners’ landscape architect represented the [635]*635actual boundary of the state-regulated wetland. The ambiguity on the official map arose as follows: On February 27, 1996 Roger Torgersen, who was a “landscape architect” hired by the petitioner Bradley Corporate Park to perform work in connection with certain expansion at its corporate park in Rockland County, flagged what he believed to be the freshwater wetland’s boundary. According to his boundary lines, there were 5.075 acres of wetlands. On May 31, 1996 the United States Army Corps of Engineers (hereinafter the ACOE), which regulates “federal” freshwater wetlands, sent representatives to the corporate park to verify the freshwater wetland’s boundary. The ACOE’s representatives determined that there were actually 5.535 acres of wetlands and expanded certain portions of Torgersen’s boundary. Torgersen then had an engineer prepare a “site plan for [the] Park,” which depicted the project. The site plan also depicted Torgersen’s boundary lines of the freshwater wetland (which was represented by a thin line that was drawn through all of the flags that Torgersen had placed), the ACOE’s boundary lines of the freshwater wetland (which was represented by a thick line that generally followed the line representing Torgersen’s boundary, except for three areas where it jutted out), and the boundary of the adjacent area (which was represented by a “dash-dot-dot-dash” line). It was undisputed that the line representing the adjacent area’s boundary was based on the line representing the ACOE’s boundary lines of the freshwater wetland. In 1999 Torgersen asked the DEC to re-certify the freshwater wetland’s boundary. He provided the DEC with a copy of the 1996 site plan for the corporate park which contained only one change. He wrote the word “wetlands” within two of the areas where the thick line representing the ACOE’s boundary lines of the freshwater wetland jutted away from the thinner line representing his boundary lines of the freshwater wetland. This map was then certified by the DEC in a signature block stating, “the freshwater wetland boundary as represented on these plans accurately depicts the limits of freshwater wetlands NA-4 as delineated by Robert Torgersen on 2/27/96.”

Despite the admitted ambiguity as to which line on the map depicted the correct boundary of the wetland, there was sufficient proof to reasonably conclude, as the Commissioner did, that both DEC staff and the petitioners’ representatives considered the thicker ACOE line as the relevant wetland boundary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reeves v. Associated Newspapers, Ltd.
2024 NY Slip Op 04286 (Appellate Division of the Supreme Court of New York, 2024)
Karl Reeves, C.E.I.N.Y. Corp. v. Associated Newspapers, Ltd.
2024 NY Slip Op 01898 (Appellate Division of the Supreme Court of New York, 2024)
Matter of Nahum v. New York State Dept. of Motor Vehs.
2020 NY Slip Op 3916 (Appellate Division of the Supreme Court of New York, 2020)
Matter of Garvey v. Sullivan
129 A.D.3d 1078 (Appellate Division of the Supreme Court of New York, 2015)
Efstathios Valiotis v. State
95 A.D.3d 1026 (Appellate Division of the Supreme Court of New York, 2012)
R.I., Inc. v. New York State Department of Labor
72 A.D.3d 1098 (Appellate Division of the Supreme Court of New York, 2010)
DeCillis v. Grannis
69 A.D.3d 851 (Appellate Division of the Supreme Court of New York, 2010)
Mill River Club, Inc. v. New York State Division of Human Rights
59 A.D.3d 549 (Appellate Division of the Supreme Court of New York, 2009)
Venditti v. New York State Department of Environmental Conservation
57 A.D.3d 685 (Appellate Division of the Supreme Court of New York, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
39 A.D.3d 632, 835 N.Y.S.2d 254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bradley-corporate-park-v-crotty-nyappdiv-2007.