Bracy Bros. Hardware Co. v. Herman-McCain Construction Co.

259 S.W. 384, 163 Ark. 133, 1924 Ark. LEXIS 257
CourtSupreme Court of Arkansas
DecidedMarch 10, 1924
StatusPublished
Cited by7 cases

This text of 259 S.W. 384 (Bracy Bros. Hardware Co. v. Herman-McCain Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bracy Bros. Hardware Co. v. Herman-McCain Construction Co., 259 S.W. 384, 163 Ark. 133, 1924 Ark. LEXIS 257 (Ark. 1924).

Opinion

Wood, J.

This is an action by the appellant against the appellee. The appellant alleged that on December 3, 1921, it entered into a contract with the appellee under which appellant was to furnish certain equipment for the kitchen and mess-liall at Port Logan H. Boots for the United States Public Health Service Hospital; that the appellant was to receive as compensation for such equipment the sum of $8,250; that the appellant furnished the equipment and performed all its incidental duties under the contract, and there is now due the appellant from the appellee the sum of $737, which appellee, on demand, refused to pay, and for which sum it prayed judgment.. Appellant exhibits with its complaint, as the foundation of its action, the following:

“Little Bock, Arkansas, December 3,1921. Herman-McCain Construction Co., Beigler Building, Little Bock, Arkansas. G-entlemen: We take pleasure in making you quotation on kitchen and mess-hall equipment for the United States Public Health Service Hospital at Port Logan H. Boots, North Little Bock, Ark., as per specifications supplemented by Jas. A. Wetmore, acting supervising architect, as listed under items 780 to 821, inclusive, for the sum of eight thousand two hundred and fifty dollars ($8,250), 50 per cent, of which is to be paid on delivery of said goods to kitchen and mess-hall at Port Logan H. Boots, 40 per cent, when goods are set in place, and the balance as soon as inspected and accepted by government.

“Our quotation does not include plumbing, gas-fitting or electric work, other than that which is a part of the specified equipment. This equipment to be manufactured as per said specification and delivered by us to said kitchen and mess-hall, and each piece of equipment set in place and position, as designated by blue-print submitted by above-mentioned architect with these specifications:

“We to furnish you with blue-print showing the proper location of necessary waste and supply water, gas and steam pipe.

“Assuring you of our desire to give you good service and equipment second to none, and hoping that we will be favored with your order, we are. Above goods to be shipped March 15, 1922. Yours very truly, Bracy Bros, Hardware Co. by E. H. Krebs. Accepted. By Herman-McCain Cons. Co., by H. C. McCain, Pres., Secy, and Treas.”

Appellee, in its answer, denied that appellant performed the duties which it agreed to perform under the contract set up in its complaint. Appellee alleged that it was required and caused to expend the sum of $737 to have the balance of the work done which appellant had agreed to do under its contract and had failed to do; that appellee offered appellant the opportunity to do the work and receive the pay therefor, and appellant refused. Appellee alleged that the sum of $737 was a reasonable amount for the work it had to do because of appellant’s failure to perform its contract. Appellee therefore prayed- that appellant’s -complaint be dismissed. The cause was, by consent, tried by the court sitting as a jury.

E. jEL Krebs testified that he had been in charge of the builders-’ hardware department of appellant for nineteen years. He identified the letter which is attached to and made a part of the complaint upon which the action was founded, and which constituted the contract between the parties. This contract refers to items 780 to 821 of specifications for kitchen and mess-hall equipment for the H. S. Public Health Service Hospital at Port Logan H. Boots'. Section 780 of the specifications is as follows: “Kitchen Equipment. 780. Scope of the work — The following equipment is to be furnished complete in every detail and installed in the kitchen and mess-hall building.” The equipment called for was furnished by the appellant and accepted by the government. It was delivered by the appellant to the hospital building, and by the appellant uncrated and assembled. The range was a very large one, and came in more than fifty pieces. It was set up and bolted together — that is, assembled by the appellant. Appellant also assembled the electric dish-washer, several large boilers, and other equipment. After assembling the equipment, appellant placed it in position, as called for in the contract. Some days later appellant was notified by the appellee to get a plumber out there and connect up the equipment. Appellant replied' that it was not required to do so under the contract, and it therefore refused to do it. Appellant had stated in the contract that it was to do no plumbing, gas-fitting, or electrical work except that which was a part of the specified equipment. Appellant was not a plumber, and that is the reason it put in the offer the provision that it was not to do the plumbing, gas-fitting, or electrical work, other than what was a part of the specified equipment. Witness understood the meaning of the word “install,” and that is what witness, acting for the appellant, did not offer to do, but offered only to assemble and set in place.

Appellee claimed that it had the plumbing done, after the appellant refused to do it, and the controversy is over $737, which amount the appellee holds out of the contract price. Witness wrote the contract, and included in it §■§ 780 to 821, inclusive. He had these specifications before him when he wrote the contract. Appellant does not dispute the amount in controversy. The appellee has the right to retain it if it is a proper charge. Appellant’s factory submitted blue-prints showing where it would be necessary for the plumbers to bring up pipes for the openings. Witness saw a good many pipes there, but didn’t put them there. The object of the blue-prints was to show the height the plumbing should be so as to correspond with the height of the connection of the equipment.

Henry C. McCain testified that he was the secretary and treasurer of the appellee. When appellee received specifications for the hospital equipment it asked for bids from the subcontractors. Appellee is not a builder, plumber, or furnisher of kitchen material, and it does not do electrical work. Bach item of the specifications appellee submitted to appellant was just as appellee received it from the government. After appellant had assembled the equipment, the appellee demanded that it connect it, which appellant refused to do. Appellee then had the work done, and retained the amount out of the contract price. In the contract of the appellee with the government there was a whole section devoted to plumbing, and it is appellee’s understanding of that contract that the' one who furnished the equipment was to connect it. The appellant was required to furnish a blue-print showing where the plumbing should be brought up, so that it would connect with the equipment. The plumbers did the roughing-in and brought the connections up to where the equipment' could be connected with it. Witness had had four years’ experience in building, and it was his understanding that, if appellant had agreed to install this kitchen equipment, without reference to plumbing, it would be appellant’s duty to do what the plumber did— that is, run all pipes up to make connections, unless that part had been provided for under the specification of plumbing. It was necessary to have the blue-prints to' show how high the connections would be to correspond with the equipment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meers v. Tommy's Men's Store, Inc.
320 S.W.2d 770 (Supreme Court of Arkansas, 1959)
Massy v. United States
214 F.2d 935 (Eighth Circuit, 1954)
United States ex rel. Commercial Equipment Co. v. Wooten
121 F. Supp. 130 (W.D. Arkansas, 1954)
Central States Life Insurance v. Morris
155 S.W.2d 333 (Supreme Court of Arkansas, 1941)
Dewey Portland Cement Co. v. Benton County Lumber Co.
63 S.W.2d 649 (Supreme Court of Arkansas, 1933)
Whittaker v. Holmes
263 S.W. 788 (Supreme Court of Arkansas, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
259 S.W. 384, 163 Ark. 133, 1924 Ark. LEXIS 257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bracy-bros-hardware-co-v-herman-mccain-construction-co-ark-1924.