BP America Production Company v. Red Deer Resources, LLC

466 S.W.3d 335, 2015 Tex. App. LEXIS 5052, 2015 WL 2400252
CourtCourt of Appeals of Texas
DecidedMay 18, 2015
Docket07-14-00032-CV
StatusPublished
Cited by3 cases

This text of 466 S.W.3d 335 (BP America Production Company v. Red Deer Resources, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BP America Production Company v. Red Deer Resources, LLC, 466 S.W.3d 335, 2015 Tex. App. LEXIS 5052, 2015 WL 2400252 (Tex. Ct. App. 2015).

Opinion

OPINION

James T. Campbell, Justice

After a jury trial in a suit brought by appellee Red Deer Resources, LLC, the court signed a judgment terminating an oil, gas and mineral lease held by appellant BP America Production Company. BP appeals. We will affirm the judgment.

Factual and Procedural Background

Some 2113 acres in Lipscomb and Hemphill Counties, Texas, are subject to BP’s Vera Murray lease. The lease, signed in 1962, began with a primary term of five years, and continued “as long thereafter as oil, gas or other mineral is produced from said land.” BP has owned and operated the lease since 2000.

Between 1967 and 1983, seven oil wells were drilled on the lease and produced from the Tonkawa formation. All were plugged by 2002. In 1986, the lessee drilled three wells completed in the Upper Morrow formation, the Vera Murray # 9, # 10 and # 11. They began production as oil wells but in 1989 were reclassified as gas wells.

Of the three Upper Morrow wells, the # 9 produced the greatest volume of gas, but its casing parted and it was plugged on April 27, 2009. By 2001, production from the # 10 well had declined to about 100 Mcf per day. During that year, it experienced a sudden drop-off in production. BP treated the well for salt build-up and performed other work, but production never exceeded 20 Mcf per day after 2001. The # 10 well was plugged in 2012. The parties stipulated at trial that the # 10 well was not capable of producing in paying quantities on or after June 12, 2012, without additional equipment or repairs.

By 1994, production from the Vera Murray #11 was averaging about 200 Mcf per day. Production declined to something under 100 Mcf per day by 2000, and by 2009 had declined to less than 10 Mcf per day. An internal BP document, 1 prepared by its reservoir engineering department in 2012, forecast a 19.3% annual decline in production from the #11 during the period beginning January 1, 2012.

The #11 well is equipped with a “plunger lift” system, which allows gas production to be interrupted to permit the well to build reservoir pressure. When pressure builds to a preset level, the gas pushes the plunger up through the tubing, clearing liquids that hinder production and allowing a free flow of gas when the plunger reaches the wellhead. When the pressure declines as the gas is produced, the plunger falls back to the bottom of the tubing, and the cycle is repeated.

The evidence includes BP’s monthly gas volume statements for the #11 well for the months of January 2009 through January 2013, admitted as Red Deer’s exhibit 85. Each monthly statement has several columns, each column containing entries for each day of the month. One column depicts the number of hours the well *340 flowed during each day; another depicts the volume of gas produced. Generally speaking, the statements show the #11 most often followed a pattern of producing gas every other day during the months before it was shut in. As examples of the entries seen on the statements, the January 2009 statement shows the well did not flow on January 1; flowed .70 hours on January 2, producing - 10 Mcf of gas; flowed .47 hours on January 3, producing 10 Mcf, and did not flow on January 4. On six occasions during that month, the well flowed on two days in a row before a day of no flow; on six other occasions, the well flowed one day and did not flow on the next day. It produced on eighteen days, did not'flow on thirteen. On one day, it produced 14 Mcf, the highest during that month. On the days the well produced that month, its production ranged from 10 to 14 Mcf.

The low production from the Vera Murray lease came to Red Deer’s attention, and it obtained top leases from the mineral owners, signed from March through June 2011. 2 In July 2011, Red Deer notified BP of its top leases and asserted its belief BP’s wells were “non-commercial.” The parties exchanged correspondence over the next several months.

In May 2012, the # 11 experienced a period of seven consecutive days with no flow of gas. In the days that followed, the well resumed a general pattern of flowing gas for a period of time every other day. 3 The well produced gas on June 4, 2012, but then began an eight-day period of no flow. On June 12, BP shut the well in, and, on June 13, sent notice to the lessors that it was invoking the shut-in royalty clause of its lease, and enclosed checks for the shut-in royalty. 4 The lessors did not negotiate the checks. The #11 well has remained shut-in since.

Red Deer brought suit against BP in Lipscomb County in August 2012. Its amended pleadings asked the court to declare whether BP’s lease had terminated. The case was tried in July and August 2013. Red Deer asserted two theories. It first contended BP’s lease had terminated because it had not produced in paying quantities, measured over a period of time ending on June 12, 2012. Secondly, it contended BP’s invocation of the shut-in royalty clause was ineffective because the *341 # 11 well was not capable of producing in paying quantities when it was shut in on June 12.

The court’s charge submitted these four questions to the jury:

Question 1: From April 27, 2009 to June 12, 2012, did the Vera Murray lease fail to produce oil or gas in paying quantities?
Question 2: Do you find that, under all the relevant circumstances, a reasonably prudent operator would not continue, for the purpose of making a profit and not merely for speculation, to operate the Vera Murray [ljease in the manner in which the lease was operated between April 27, 2009 to June 12, 2012?
Question 3: Was the Vera Murray # 11 well incapable of producing in paying quantities when it was shut-in on June 13, 2012?
Question 4: Do you find that, under all the relevant circumstances, if the Vera Murray # 11 [wjell were turned on, without additional equipment or repairs, a reasonably prudent operator would not, for the purpose of making a profit and not merely for speculation, operate the Vera Murray #11 well in the manner in which the well had been operated up to June 13, 2012?

To question 1, the jury answered, “No, the Vera Murray lease did not fail to produce in paying quantities.” The jury did not answer question 2 because it was conditioned on an affirmative answer to question 1.

To question 3, the jury answered, ‘Tes, the Vera Murray #11 [wjell was incapable of producing in paying quantities when it was shut-in on June 13, 2012.” To question 4, it answered, ‘Tes, a reasonably prudent operator would not continue to operate the well.”

The court signed a judgment declaring the Vera Murray lease had “lapsed and terminated for the lease being incapable of producing in paying quantities when the Vera Murray Well #11 was shut in on June 13, 2012 and that a reasonably prudent operator would not continue to operate the well.”

Analysis

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
466 S.W.3d 335, 2015 Tex. App. LEXIS 5052, 2015 WL 2400252, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bp-america-production-company-v-red-deer-resources-llc-texapp-2015.