Boykin Brothers, LLC v. Laborde Construction Industries, LLC, John Laborde, Catamount Constructors, Inc., LMK Baton Rouge Construction, LLC, and The Standard of Baton Rouge, LLC

CourtLouisiana Court of Appeal
DecidedJanuary 21, 2020
Docket2018CW1120
StatusUnknown

This text of Boykin Brothers, LLC v. Laborde Construction Industries, LLC, John Laborde, Catamount Constructors, Inc., LMK Baton Rouge Construction, LLC, and The Standard of Baton Rouge, LLC (Boykin Brothers, LLC v. Laborde Construction Industries, LLC, John Laborde, Catamount Constructors, Inc., LMK Baton Rouge Construction, LLC, and The Standard of Baton Rouge, LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boykin Brothers, LLC v. Laborde Construction Industries, LLC, John Laborde, Catamount Constructors, Inc., LMK Baton Rouge Construction, LLC, and The Standard of Baton Rouge, LLC, (La. Ct. App. 2020).

Opinion

NOT DESIGNATED FOR PUBLICATION

STATE OF LOUISIANA COURT OF APPEAL FIRST CIRCUIT

2018 CA 1528 and 2018 CW 1120

BOYKIN BROTHERS, LLC

VERSUS

LABORDE CONSTRUCTION INDUSTRIES, LLC, JOHN LABORDE, CATAMOUNT CONSTRUCTORS, INC., LMK BATON ROUGE CONSTRUCTION, LLC, AND THE STANDARD OF BATON ROUGE, LLC

CONSOLIDATED WITH

2018 CA 1529

CATAMOUNT CONSTRUCTORS, INC.

LMK BATON ROUGE CONSTRUCTION, LLC AND THE STANDARD AT BATON ROUGE, LLC

Judgment rendered ' JAN 2 12020

On Appeal from the Nineteenth Judicial District Court In and for the Parish of East Baton Rouge State of Louisiana No. C637569 c/ w 639816, Sec. D

The Honorable Janice Clark, Judge Presiding

Russel W. Wray Attorneys for Plaintiff/Appellee Jacob A. Altmyer Boykin Brothers, LLC St. Francisville, Louisiana

Jacob B. Huddleston Attorneys for Defendant/ Appellee Scott Edward Frazier Catamount Constructors, Inc. Baton Rouge, Louisiana

James A. Hatch Attorneys for Intervenor/ Appellee

h Paul E. Mayeaux Osman Construction, LLC Metairie, Louisiana

Jeanne C. Comeaux Attorneys for Defendant/Appellee Druit G. Gremillion Laborde Constructions Industries, John T. Andrishok LLC, and John Laborde Jordan L. Faircloth Baton Rouge, Louisiana

Kelsey K. Funes Attorneys for Defendant/Appellant # 1 Amanda W. Messa Hanover Insurance Company H. Alston Johnson, III Baton Rouge, Louisiana

Kelsey K. Funes Attorneys for Defendant/Appellant #2 Amanda W. Messa LMK Baton Rouge Construction, H. Alston Johnson, III LLC Baton Rouge, Louisiana and

Patrick Schwedler Athens, Georgia

BEFORE: McDONALD, GRAIN,' AND HOLDRIDGE, JJ.

i Justice Will Crain is serving as judge ad hoc by special appointment of the Louisiana Supreme Court. HOLDRIDGE, J.

LMK Baton Rouge Construction, LLC ( LMK) and The Hanover Insurance

Company ( Hanover) appeal a partial summary judgment entered in favor of

Boykin Brothers, LLC ( Boykin) in this action to enforce a lien perfected pursuant

to the Louisiana Private Works Act ( PWA). LMK also seeks supervisory review

of the trial court' s denial of its motion for summary judgment. We reverse the trial

court' s ruling granting the partial summary judgment. We affirm the denial of

LMK and Hanover' s motion for summary judgment and deny LMK' s writ

application as moot.

FACTUAL AND PROCEDURAL BACKGROUND

In 2014, an apartment complex known as the Standard at Baton Rouge was

constructed pursuant to the PWA ( herein referred to as " the Project"). LMK

served as a contractor and later as the general contractor on the Project. LMK

entered into a subcontract with Catamount Constructors, Inc. ( Catamount) to

perform foundation work for the Project. Laborde Construction Industries, LLC

Laborde) entered into a subcontract with Catamount to furnish all labor, materials,

tools, and equipment necessary to furnish and install a complete " Driven Piles

P] ackage" for the Project. Laborde solicited a quote from Boykin to fabricate and

deliver concrete pilings, to be furnished by Boykin and incorporated by Laborde on

the Project. On or about March 14, 2014, Boykin issued a " Written Proposal" to

Laborde, which set forth the price for the fabrication of 858 pieces of 14" pilings,

each measuring 65 linear feet, and 281 pieces of 18" pilings, each measuring 95

linear feet. The proposal sets forth separate delivery charges, with the 14" pilings

charged a delivery fee of $2. 05 per linear foot and the 18" pilings charged at $ 7. 37

per linear foot. The Written Proposal was not signed by Boykin or Laborde.

t3 On March 3, 2014, LMK and the owner of the project executed a Standard

Form Agreement, pursuant to which, LMK became the general contractor on the

project. On July 21, 2014, Laborde' s subcontract with Catamount was assigned to

LMK.

Boykin was paid $ 1, 549,230. 11 for its work on the Project. Payments to

Boykin for its work on the Project were made by checks issued by Catamount to

both Laborde and Boykin, which were endorsed by Laborde to Boykin. Boykin

claimed that it had not been paid in full for the materials it furnished on the Project

and that $ 589, 548. 99 remained unpaid for the amounts Boykin invoiced to

Laborde. On January 28, 2015, Boykin filed a " Lien Affidavit Statement of Claim

and Privilege" with the East Baton Rouge Parish Recorder of Mortgages. Therein,

Boykin asserted a privilege pursuant to the PWA for the amount of $589, 548. 99,

together with interest at the legal rate, a recording fee of approximately $ 25. 00,

and all other sums allowed by law for the materials. On February 20, 2015, LMK,

as principal, and Hanover, LMK' s surety on the Project, filed a " Release of Lien

Bond" with the East Baton Rouge Parish Clerk of Court in order to secure the

cancellation of Boykin' s lien in the amount of $736,936.24, representing 125% of

the amount of the lien. The " Release of Lien Bond" was accepted by the Recorder

of Mortgages, and Boykin' s lien was cancelled.2

On March 4, 2015, Boykin filed this lawsuit against Laborde and its agent,

John Laborde, Catamount, and LMK,3 asserting various claims for nonpayment of

sums allegedly due to Boykin for the fabrication and delivery of concrete piles

furnished on the Project. As to LMK, Boykin asserted a claim under the PWA,

2 On September 25, 2015, the owner of the Project filed a notice of termination or substantial completion of the Project.

3 Boykin also sued the owner of the Project, but later dismissed it from the litigation. seeking the enforcement of its lien, along with other relief. Specifically, Boykin

sought to recover $ 589, 548.99 from LMK for the materials supplied, delivered,

and incorporated into the Project which Laborde failed to pay Boykin, as well as 115. 00 to record its lien. Boykin asserted breach of contract and PWA claims

against Laborde.

In an amended and supplemental petition, Boykin added Hanover as a

defendant in the litigation and also asserted breach of contract claims against LMK

and Catamount. Generally, as to LMK, Boykin claimed that: ( 1) LMK promised

to continue to pay Boykin until Boykin had been paid in full for its work on the

Project and breached that agreement; ( 2) LMK assumed a contractual obligation in

its contract with Catamount to make all payments on the Project by joint check to

Boykin and Laborde and breached that agreement by issuing a check in August of

2014 solely to Laborde; ( 3) alternatively, prevailing custom implied an obligation

on LMK' s part to issue joint checks, or at the very least, imposed an obligation on

LMK to give Boykin notice of the issuance of any check to Laborde alone, and

LMK' s failure to do so constituted a breach of the obligation of good faith and fair

dealing.

On May 4, 2017, Boykin filed a motion for partial summary judgment

against LMK and Hanover (sometimes collectively referred to as " LMK") in which

it asked the trial court to determine those defendants' liability under the PWA.

Boykin claimed that it was beyond genuine dispute that the principal sum of

589, 548. 99 remained unpaid to Boykin for amounts invoiced to Laborde for

Boykin' s work on the Project. It further asserted that of that principal sum, it is

beyond genuine dispute that $ 587, 317. 12 ( including delivery/ freight charges)

represents the adjusted principal amount remaining unpaid to Boykin and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burdette v. Drushell
837 So. 2d 54 (Louisiana Court of Appeal, 2002)
Parish Concrete, Inc. v. Fritz Culver, Inc.
399 So. 2d 694 (Louisiana Court of Appeal, 1981)
Judson v. Davis
916 So. 2d 1106 (Louisiana Court of Appeal, 2005)
Belanger v. Gabriel Chemicals, Inc.
787 So. 2d 559 (Louisiana Court of Appeal, 2001)
RJ Messinger, Inc. v. Rosenblum
894 So. 2d 1113 (Supreme Court of Louisiana, 2005)
Fils v. Allstate Insurance Co.
186 So. 3d 152 (Louisiana Court of Appeal, 2015)
Neighbors Federal Credit Union v. Anderson
196 So. 3d 727 (Louisiana Court of Appeal, 2016)
Fonseca v. City Air of Louisiana, LLC
196 So. 3d 82 (Louisiana Court of Appeal, 2016)
Jones v. Anderson
224 So. 3d 413 (Louisiana Court of Appeal, 2017)
Thompson v. Ctr. for Pediatric & Adolescent Med., L.L.C.
244 So. 3d 441 (Louisiana Court of Appeal, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Boykin Brothers, LLC v. Laborde Construction Industries, LLC, John Laborde, Catamount Constructors, Inc., LMK Baton Rouge Construction, LLC, and The Standard of Baton Rouge, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boykin-brothers-llc-v-laborde-construction-industries-llc-john-laborde-lactapp-2020.