Boykin Brothers, LLC v. Laborde Construction Industries, LLC, John Laborde, Catamount Constructors, Inc., LMK Baton Rouge Construction, LLC, and The Standard of Baton Rouge, LLC

Louisiana Court of Appeal·Decided January 21, 2020·No. 2018CW1120·Unknown

Opinion

NOT DESIGNATED FOR PUBLICATION

STATE OF LOUISIANA

COURT OF APPEAL

FIRST CIRCUIT

2018 CA 1528 and 2018 CW 1120 BOYKIN BROTHERS, LLC

VERSUS

LABORDE CONSTRUCTION INDUSTRIES, LLC, JOHN LABORDE, CATAMOUNT CONSTRUCTORS, INC., LMK BATON ROUGE CONSTRUCTION, LLC, AND THE STANDARD OF BATON ROUGE, LLC

CONSOLIDATED WITH

2018 CA 1529

CATAMOUNT CONSTRUCTORS, INC.

VERSUS

LMK BATON ROUGE CONSTRUCTION, LLC AND THE STANDARD AT BATON ROUGE, LLC

Judgment rendered ' JAN 2 12020

On Appeal from the

Nineteenth Judicial District Court In and for the Parish of East Baton Rouge State of Louisiana

No. C637569 c/ w 639816, Sec. D

The Honorable Janice Clark, Judge Presiding

Russel W. Wray Attorneys for Plaintiff/Appellee Jacob A. Altmyer Boykin Brothers, LLC St. Francisville, Louisiana

Jacob B. Huddleston Attorneys for Defendant/ Appellee Scott Edward Frazier Catamount Constructors, Inc. Baton Rouge, Louisiana

James A. Hatch Attorneys for Intervenor/ Appellee

h

Paul E. Mayeaux Osman Construction, LLC Metairie, Louisiana

Jeanne C. Comeaux Attorneys for Defendant/Appellee Druit G. Gremillion Laborde Constructions Industries, John T. Andrishok LLC, and John Laborde Jordan L. Faircloth Baton Rouge, Louisiana

Kelsey K. Funes Attorneys for Defendant/Appellant # 1 Amanda W. Messa Hanover Insurance Company H. Alston Johnson, III Baton Rouge, Louisiana

Kelsey K. Funes Attorneys for Defendant/Appellant #2 Amanda W. Messa LMK Baton Rouge Construction, H. Alston Johnson, III LLC Baton Rouge, Louisiana and

Patrick Schwedler Athens, Georgia

BEFORE: McDONALD, GRAIN,' AND HOLDRIDGE, JJ.

i Justice Will Crain is serving as judge ad hoc by special appointment of the Louisiana Supreme Court.

HOLDRIDGE, J.

LMK Baton Rouge Construction, LLC ( LMK) and The Hanover Insurance Company ( Hanover) appeal a partial summary judgment entered in favor of Boykin Brothers, LLC ( Boykin) in this action to enforce a lien perfected pursuant to the Louisiana Private Works Act ( PWA). LMK also seeks supervisory review of the trial court' s denial of its motion for summary judgment. We reverse the trial court' s ruling granting the partial summary judgment. We affirm the denial of LMK and Hanover' s motion for summary judgment and deny LMK' s writ application as moot.

FACTUAL AND PROCEDURAL BACKGROUND

In 2014, an apartment complex known as the Standard at Baton Rouge was constructed pursuant to the PWA ( herein referred to as " the Project"). LMK

served as a contractor and later as the general contractor on the Project. LMK

entered into a subcontract with Catamount Constructors, Inc. ( Catamount) to

perform foundation work for the Project. Laborde Construction Industries, LLC

Laborde) entered into a subcontract with Catamount to furnish all labor, materials, tools, and equipment necessary to furnish and install a complete " Driven Piles P] ackage" for the Project. Laborde solicited a quote from Boykin to fabricate and

deliver concrete pilings, to be furnished by Boykin and incorporated by Laborde on the Project. On or about March 14, 2014, Boykin issued a " Written Proposal" to

Laborde, which set forth the price for the fabrication of 858 pieces of 14" pilings,

each measuring 65 linear feet, and 281 pieces of 18" pilings, each measuring 95 linear feet. The proposal sets forth separate delivery charges, with the 14" pilings charged a delivery fee of $2. 05 per linear foot and the 18" pilings charged at $ 7. 37 per linear foot. The Written Proposal was not signed by Boykin or Laborde.

t3

On March 3, 2014, LMK and the owner of the project executed a Standard Form Agreement, pursuant to which, LMK became the general contractor on the project. On July 21, 2014, Laborde' s subcontract with Catamount was assigned to LMK.

Boykin was paid $ 1, 549,230. 11 for its work on the Project. Payments to

Boykin for its work on the Project were made by checks issued by Catamount to both Laborde and Boykin, which were endorsed by Laborde to Boykin. Boykin

claimed that it had not been paid in full for the materials it furnished on the Project and that $ 589, 548. 99 remained unpaid for the amounts Boykin invoiced to Laborde. On January 28, 2015, Boykin filed a " Lien Affidavit Statement of Claim and Privilege" with the East Baton Rouge Parish Recorder of Mortgages. Therein,

Boykin asserted a privilege pursuant to the PWA for the amount of $589, 548. 99,

together with interest at the legal rate, a recording fee of approximately $ 25. 00, and all other sums allowed by law for the materials. On February 20, 2015, LMK, as principal, and Hanover, LMK' s surety on the Project, filed a " Release of Lien Bond" with the East Baton Rouge Parish Clerk of Court in order to secure the

cancellation of Boykin' s lien in the amount of $736,936.24, representing 125% of

the amount of the lien. The " Release of Lien Bond" was accepted by the Recorder

of Mortgages, and Boykin' s lien was cancelled.2 On March 4, 2015, Boykin filed this lawsuit against Laborde and its agent,

John Laborde, Catamount, and LMK,3 asserting various claims for nonpayment of sums allegedly due to Boykin for the fabrication and delivery of concrete piles furnished on the Project. As to LMK, Boykin asserted a claim under the PWA,

2 On September 25, 2015, the owner of the Project filed a notice of termination or substantial completion of the Project.

3 Boykin also sued the owner of the Project, but later dismissed it from the litigation.

seeking the enforcement of its lien, along with other relief. Specifically, Boykin sought to recover $ 589, 548.99 from LMK for the materials supplied, delivered,

and incorporated into the Project which Laborde failed to pay Boykin, as well as 115. 00 to record its lien. Boykin asserted breach of contract and PWA claims

against Laborde.

In an amended and supplemental petition, Boykin added Hanover as a

defendant in the litigation and also asserted breach of contract claims against LMK and Catamount. Generally, as to LMK, Boykin claimed that: ( 1) LMK promised to continue to pay Boykin until Boykin had been paid in full for its work on the Project and breached that agreement; ( 2) LMK assumed a contractual obligation in

its contract with Catamount to make all payments on the Project by joint check to Boykin and Laborde and breached that agreement by issuing a check in August of 2014 solely to Laborde; ( 3) alternatively, prevailing custom implied an obligation on LMK' s part to issue joint checks, or at the very least, imposed an obligation on LMK to give Boykin notice of the issuance of any check to Laborde alone, and LMK' s failure to do so constituted a breach of the obligation of good faith and fair

dealing.

On May 4, 2017, Boykin filed a motion for partial summary judgment against LMK and Hanover (sometimes collectively referred to as " LMK") in which it asked the trial court to determine those defendants' liability under the PWA. Boykin claimed that it was beyond genuine dispute that the principal sum of

589, 548. 99 remained unpaid to Boykin for amounts invoiced to Laborde for

Boykin' s work on the Project. It further asserted that of that principal sum, it is

beyond genuine dispute that $ 587, 317. 12 ( including delivery/ freight charges) represents the adjusted principal amount remaining unpaid to Boykin and

associated with the materials/ concrete piles that were delivered to the Project job

site ( and presumably incorporated or consumed thereon), and thus subject to

protection under the PWA. Boykin maintained that the prices and expenses agreed to by Boykin and Laborde are not genuinely disputed. Boykin asked for summary judgment decreeing that LMK and Hanover are liable in solido for the sum of 587,317. 12, together with interest legally due, and the fees associated with the filing of its lien under the PWA.

Boykin and LMK submitted considerable evidence in support of and in opposition to Boykin' s motion for partial summary judgment. LMK urged that

Free access — add to your briefcase to read the full text and ask questions with AI

Boykin Brothers, LLC v. Laborde Construction Industries, LLC, John Laborde, Catamount Constructors, Inc., LMK Baton Rouge Construction, LLC, and The Standard of Baton Rouge, LLC, (La. Ct. App. 2020).

Boykin Brothers, LLC v. Laborde Construction Industries, LLC, John Laborde, Catamount Constructors, Inc., LMK Baton Rouge Construction, LLC, and The Standard of Baton Rouge, LLC (Boykin Brothers, LLC v. Laborde Construction Industries, LLC, John Laborde, Catamount Constructors, Inc., LMK Baton Rouge Construction, LLC, and The Standard of Baton Rouge, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Burdette v. Drushell
837 So. 2d 54 (Louisiana Court of Appeal, 2002)
Parish Concrete, Inc. v. Fritz Culver, Inc.
399 So. 2d 694 (Louisiana Court of Appeal, 1981)
Judson v. Davis
916 So. 2d 1106 (Louisiana Court of Appeal, 2005)
Belanger v. Gabriel Chemicals, Inc.
787 So. 2d 559 (Louisiana Court of Appeal, 2001)
RJ Messinger, Inc. v. Rosenblum
894 So. 2d 1113 (Supreme Court of Louisiana, 2005)
Fils v. Allstate Insurance Co.
186 So. 3d 152 (Louisiana Court of Appeal, 2015)
Neighbors Federal Credit Union v. Anderson
196 So. 3d 727 (Louisiana Court of Appeal, 2016)
Fonseca v. City Air of Louisiana, LLC
196 So. 3d 82 (Louisiana Court of Appeal, 2016)
Jones v. Anderson
224 So. 3d 413 (Louisiana Court of Appeal, 2017)
Thompson v. Ctr. for Pediatric & Adolescent Med., L.L.C.
244 So. 3d 441 (Louisiana Court of Appeal, 2018)