Boyd v. Ibbetson

265 P. 887, 90 Cal. App. 298, 1928 Cal. App. LEXIS 55
CourtCalifornia Court of Appeal
DecidedMarch 21, 1928
DocketDocket No. 6138.
StatusPublished
Cited by2 cases

This text of 265 P. 887 (Boyd v. Ibbetson) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boyd v. Ibbetson, 265 P. 887, 90 Cal. App. 298, 1928 Cal. App. LEXIS 55 (Cal. Ct. App. 1928).

Opinion

WELCH, J., pro tem.

Appellant, in November, 1922, was the owner of a tract of land in Los Angeles County which he proposed to subdivide into residence lots. Respondent, a contractor, entered into a memorandum of agreement with appellant whereby he agreed to grade the streets of said subdivision and to construct sidewalks and curbs therein. Respondent entered upon the work of grading the streets of the subdivision and continued to do so until February 17, 1923, when a dispute arose between the parties. On March 7th the parties entered into another agreement which was supplemental to and in amplification of the memorandum agreement above mentioned. This dispute being unsettled in May respondent ceased work under the contracts and commenced three separate actions against appellant, one for grading and leveling work, one for specific enforcement of the contracts and one for sand and gravel alleged to have been furnished appellant by respondent, independent of the contracts.

It being stipulated that the three actions may be tried together and that the testimony introduced in any one cause may be applied to all three causes, the trial court made but one decision and one judgment in all three cases. In so doing it considered that the three complaints were contained in one pleading and that the three answers thereto were contained in one pleading; that the cross-complaint of appellant and the answer thereto be considered as a separate action.

The trial court gave respondent judgment for $4,422.20, from which this appeal is taken upon the judgment-roll and a bill of exceptions. Included in the appeal is an order denying appellant a new trial.

*300 The theory of respondent is that appellant was in default in his payments and in keeping his agreements and for these reasons respondent may recover a reasonable value for his work and services already performed without first completing his entire contract. It appears from appellant’s pleadings and his claims here that his theory of the case is that the contract between the parties is entire; that respondent did not complete the entire contract, but ceased to perform the same long before its completion, that he thereby breached his contract and is entitled to nothing, but, on the contrary, is liable to appellant for the money necessarily expended beyond the contract price in completing the work.

In response to an attack made by appellant upon the sufficiency of the pleadings of respondent and upon the trial court’s decision, respondent’s counsel admits that the complaints are not “paragons of pleadings” and that their shortcomings might imperil the judgment, were it not for the protecting provisions of section 4% of article VI of the state constitution. Considering all the pleadings in the three actions together, as did the parties and the trial court, in which pleadings all the facts of the contracts and of the transaction are set forth and also considering the bill of exceptions wherein a full transcription of the evidence is brought here, this court does not find it necessary to resort either to said constitutional provision, which covers a multitude of errors, or to the broad provisions of section 956a of the Code of Civil Procedure [Stats. 1927, p. 583], in regard to insufficient findings.

The first question of inquiry is: Was there a breach of contract by the appellant? The answer to this question will practically decide this case on appeal.

In the preliminary agreement appellant authorized respondent to commence at once the grading of the streets of appellant’s subdivision and agreed to pay him “35c a yard for the dirt removed.” The contract further provided for laying sidewalks and installing curbs by appellant on the subdivision at agreed prices; sixty per cent of the value of all work was to be paid for in cash and forty per cent in lots of the tract at sale prices; of the sixty per cent, seventy-five per cent thereof was to be paid as the work progressed *301 and the balance of twenty-five per cent upon the completion o£ the work.

Respondent immediately entered upon the execution of his contract and continued his work of grading the streets until February 17, 1923, when, as stated above, a dispute arose between the parties as to payments, yardage of dirt moved and other differences. At that time all of the rough grading down to the laying of the sidewalks and installing curbs had practically been done. The engineer, who was the agent of the appellant owner, had given to respondent an estimate of 29,000 cubic yards of earth moved in so grading the streets, while respondent claimed that by reason of his being compelled by no fault of his to move certain earth two or three times the yardage moved and re-moved by him was 41,000 cubic yards. On this point of yardage the trial court held that by reason of errors of the engineer of appellant in placing grade stakes, respondent had been compelled to move large quantities of earth more than once, but that the amount of which could not be ascertained, and thereupon fixed the amount of dirt moved in grading under the contract at 22,492 cubic yards. For this yardage the court allowed the appellant 35 cents per cubic yard, amounting to $8,222.20. Upon this amount $4,920 had been paid, leaving a balance of $3,302.20. This balance on February 17, 1923, had been earned and respondent, if not in default, was then entitled to an adjustment and settlement under the terms of the contract. The supplemental agreement recited that respondent in grading the streets had followed the specifications and directions of the owner’s engineers.

Exclusive of an item of $1,120, which we will hereafter notice, the appellant had overpaid respondent on February 17th the seventy-five per cent of the sixty per cent cash payment to be made as the work progressed; but in our judgment respondent at that time was entitled to payment and liquidation of his forty per cent, which had been earned and which was to be liquidated in lots. The supplemental complaint provides that “as to the manner and time of payment for such services and work performed’’ said owner shall pay in money seventy-five per cent of the sixty per cent of the price of dirt moved on the 1st and 15th of each month and the balance of forty per cent shall be liquidated *302 by respondent receiving- different lots to be picked out by him from lots over the entire tract not already sold. Under the terms of the contracts and the evidence in the case respondent did not have to wait until he had completed all his contract work before receiving his lots in liquidation for the forty per cent earned as the work progressed. Respondent with the knowledge and consent of appellant had on February 17th exercised his right to select his lots in liquidation of his forty per cent of the contract price. The evidence shows and the court found that appellant agreed to deed these lots, to respondent, but failed to do so. In excuse for his failure to keep his promise appellant now claims that the deeds of conveyance were to be executed to respondent upon the payment by respondent of twenty-five per cent assumed for the proportional amount of an existing mortgage on the subdivision. The weakness of this argument is that he made no such condition to his promise to deed the lots selected as payment for the forty per cent earned under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ferrari v. Mambretti
136 P.2d 326 (California Court of Appeal, 1943)
Mathewson v. Alderman
290 P. 317 (California Court of Appeal, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
265 P. 887, 90 Cal. App. 298, 1928 Cal. App. LEXIS 55, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boyd-v-ibbetson-calctapp-1928.