Boyd v. Amoco Production Co.

786 S.W.2d 528, 1990 Tex. App. LEXIS 559, 1990 WL 27431
CourtCourt of Appeals of Texas
DecidedMarch 15, 1990
Docket11-89-164-CV
StatusPublished
Cited by8 cases

This text of 786 S.W.2d 528 (Boyd v. Amoco Production Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boyd v. Amoco Production Co., 786 S.W.2d 528, 1990 Tex. App. LEXIS 559, 1990 WL 27431 (Tex. Ct. App. 1990).

Opinion

DICKENSON, Justice.

The trial court granted Amoco Production Company’s motion for summary judgment that it recover contractual indemnity from Shelton Boyd, d/b/a Boyd’s Welding Service, for $240,000.00 which Amoco paid in settlement of a lawsuit filed by Boyd’s employee, Jay Ernest Hunt, plus stipulated attorney’s fees and prejudgment interest. We affirm.

Factual Background

Amoco and Boyd executed a “Well and Lease Service Master Contract” on September 15, 1977, which provided in pertinent part:

10. In order to eliminate controversies between Contractor, its Subcontractors and Amoco and its joint owners, if any, and their respective insurers, Contractor assumes all liability for and hereby agrees to defend, indemnify and hold Amoco, its joint owner or owners, if any, and their insurers, harmless from and against any and all losses, costs, expenses and causes of action, including attorney’s fees and court costs for injuries to and death of Contractor’s and its Subcontractor’s employees, arising out of, incident to, or in connection with any and all operations under this contract and whether or not such losses, costs, expenses and causes of action are occasioned by or incident to or the result of the negligence of Amoco, its joint owner or owners, if any, and its agents, representatives and employees. Contractor agrees to insure this assumption of liability. The liability assumed by Contractor pursuant to this clause shall be limited to the amounts carried by Contractor’s current liability insurance, but in no event shall it be less than the minimum limits set out in Paragraph 11(b), below. (Emphasis added)

Pursuant to that contract Amoco employed Boyd from time to time to provide welding services on Amoco’s equipment.

On January 30, 1984, Amoco asked Boyd to send a welder to one of its leases to cut the anchor bolts which secured a pumping unit to a concrete pad. Boyd’s employee, Jay Ernest Hunt, went to the lease. He met two Amoco roustabouts, David Martin Anderson and William Veri Palmer. They drove to the well in one vehicle, and Hunt followed them in a welding truck. When they got to the well, they began doing the work which was to be done in preparation for the removal of the pumping unit. It was to be replaced with a larger pumping unit. After filling a hole with dirt where a pole had been removed, the two Amoco roustabouts proceeded to disconnect the sucker rods from the pumping unit. In the meantime Hunt had laid out his welding equipment lines and commenced to cut the anchor bolts. He was cutting the third bolt (out of the ten anchor bolts which secured the pumping unit to the pad) when the Amoco roustabouts loosened the bridle on the “horse’s head” of the pump’s rocker arm. The sucker rods slipped down, and then the large counterweights caused the rocker arm to move down. One of the counterweights grazed Hunt’s head, and the rocker arm caught and mangled his left arm.

All three of the men at the scene made res gestae statements in which each of them accepted some of the blame for failing to make sure that the brake was set on the pumping unit. If the brake had been set, the accident would not have occurred.

*530 Amoco and Boyd have stipulated that the $240,000.00 which was paid to Hunt by Amoco was a reasonable settlement; that Boyd has liability insurance with St. Paul Insurance Company in the amount of $300,-000.00 to cover any liability which he might have to Amoco under the indemnity agreement; that the attorney’s fees and expenses which Amoco incurred in the sum of $4,378.63 were reasonable and necessary for the defense of the lawsuit filed by Hunt against Amoco; and that the attorney’s fees and expenses which Amoco incurred in the sum of $7,180.30 were reasonable and necessary for the handling of the lawsuit filed by Amoco against Boyd.

Legal Issue

Do the undisputed facts show that the injuries to Boyd’s employee “arose out of, was incident to, or in connection with” Boyd’s welding operations? Boyd argues that his man was doing one “operation” (cutting the anchor bolts) while the Amoco roustabouts were doing a completely different “operation” (disconnecting the sucker rods from the pumping unit) and that the injuries arose from the Amoco operations rather than from the welding operations. Amoco argues that the welder and the roustabouts were all working to get the pumping unit ready for removal and replacement and that the welder’s injuries clearly arose out of, were incident to, and were in connection with “any and all operations under this contract.”

Points of Error

Boyd presents three points of error. He argues (Point One) that the trial court erred in denying his motion for summary judgment because the summary judgment evidence conclusively establishes that the injury to his employee “did not arise out of, was not incident to, and was not in connection with” the work being performed for Amoco. Then, he argues in the alternative (Point Two) that the trial court erred in granting Amoco’s motion for summary judgment because there is a genuine fact issue as to whether the injury to his employee “did not arise out of, was not incident to, or was not in connection with” the work being performed. In his final point, Boyd argues that the trial court erred in granting summary judgment for Amoco because there is no summary judgment evidence of the “current insurance” on September 15, 1977 (when the indemnity contract was executed).

The Indemnity Agreement

The first two points of error are overruled. We agree with the trial court’s ruling that the summary judgment evidence conclusively establishes that the welder’s injuries arose out of, were incident to, and were connected with operations covered by the indemnity agreement.

The indemnity agreement is valid. See TEX.CIV.PRAC. & REM.CODE ANN. secs. 127.001 to 127.008 (Vernon 1986 and Supp.1990). It was also valid under the prior law. TEX.REV.CIV.STAT.ANN. art. 2212b (Repealed when the Civil Practice and Remedies Code was enacted). The indemnity agreement satisfies the “express negligence” test which was established in Ethyl Corporation v. Daniel Construction Company, 725 S.W.2d 705 at 708 (Tex.1987). See also Atlantic Richfield Company v. Petroleum Personnel, Inc., 768 S.W.2d 724 at 726 (Tex.1989).

The indemnity provision involved in this case is quite broad. It covers “all” losses and costs for personal injuries to the welding contractor’s employees which are incidental to, or connected with, “any and all operations” conducted by the welding contractor pursuant to the master contract dated September 15, 1977, and it expressly states that it covers causes of action resulting from the negligence of Amoco and its employees.

The cases upon which appellant relies are clearly distinguishable. McClane v. Sun Oil Company, 634 F.2d 855 at 859 (5th Cir.1981) (applying Texas law), and Sun Oil Company v. Renshaw Well Service, Inc., 571 S.W.2d 64

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
786 S.W.2d 528, 1990 Tex. App. LEXIS 559, 1990 WL 27431, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boyd-v-amoco-production-co-texapp-1990.