Bowman v. Globe Steam Heating Co.

80 Mo. App. 628, 1899 Mo. App. LEXIS 219
CourtMissouri Court of Appeals
DecidedMay 27, 1899
StatusPublished
Cited by2 cases

This text of 80 Mo. App. 628 (Bowman v. Globe Steam Heating Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowman v. Globe Steam Heating Co., 80 Mo. App. 628, 1899 Mo. App. LEXIS 219 (Mo. Ct. App. 1899).

Opinion

BIGGS, J.

On the thirtieth day of August, 1895, the Globe Steam Heating Company, one of the defendants herein, entered into a contract with Samuel Bowman and Joseph Wolfort, the plaintiffs herein, whereby it agreed to erect and install a heating apparatus for plaintiffs in a building then being built by them, for $4,800. By the terms of the contract the plaintiffs were to pay $1,000 when the pipe work was completed; $1,500 when the boilers were set in the building; $1,000 when the radiators were connected, and the remainder of the contract price when the apparatus was tested and accepted by the architect. It was also stipulated that the heating company might substitute for the boilers mentioned in the specifications their incandescent super-heating boilers and smoke consumer, upon a guaranty of satisfactory work, and if not, to replace them with boilers and smoke consumers according to the original specifications. It was further agreed that the work should be completed by the fifteenth day of October, 1895, and in case of failure the [631]*631heating company agreed to pay as liquidated damages $50 for every day thereafter that the work should remain unfinished. Eor the faithful performance .of the contract the heating company as principal and the American Surety Company as surety, entered into a bond in the penal sum of $2,500, upon the following conditions, to wit: “Now, if said Globe Steam Heating Company shall well and truly perform and fulfill all and every the covenants, conditions, stipulations and agreements in said contract mentioned to be performed and fulfilled, and shall keep the said Samuel Bowman and Joseph 'YVolfort harmless and indemnified from and against all and every claim, demand, judgment, liens and mechanics’ liens, costs and fees of every description incurred in suits or otherwise that may be had against them or the work to be done under said contract, and if the said Globe Steam Heating Company shall pay to said Samuel Bowman and Joseph Wolfort all damages they may sustain and all forfeitures to which they may be entitled by reason of the nonperformance or mal-performanee of said contract by it, then said obligation shall be void, otherwise to remain in full force and effect.” The present action is on the bond. The alleged breaches are that in addition to $2,000 paid on account of the contract the plaintiffs were compelled to pay judgments for materials sold and delivered to the heating company in the erection of the apparatus, amounting to $4,029.41; for completion of the work $39; that the boilers furnished were inferior in value and differing from those specified in the contract, which difference amounted to $1,200; that there was a delay of fifteen days in the completion of the work, which entitled the plaintiffs to claim as liquidated damages the sum of $750; that on account of the inferior condition of the boilers the plaintiffs were unable to light the building with their own dynamos, and were compelled to purchase electricity elsewhere at an additional cost of $797.40. The plaintiffs claimed damages to the amount of $3,865.82 in excess of the contract price. [632]*632Judgment was asked for tke penalty of the bond to be satisfied upon the payment of $2,500. The answer of the heating company is a general denial, except the admission that the company executed the bond and contract. The American Surety Company, after admitting the execution of the bond as surety, interposed the following defenses, to wit, that the plaintiffs first violated the conditions of the bond in that they failed to pay the instalments for the work as they fell due, and that by reason of this the heating company was unable to pay the materialmen, which resulted in the filing and enforcement of mechanics’ liens by them; that after the execution of the bond and without the consent of defendant the plaintiffs entered into an independent contract with the Springfield Boiler and Manufacturing Company to furnish the boilers for the apparatus, and that subsequently the boiler company took possession of the premises and put in the boilers to the exclusion of the steam heating company, and further that the plaintiffs voluntarily z-eleased the heating company from the full performance of the contract. The . new matter in the answer was put in issue by the reply. Upon the issues thus framed the cause was tried before the court without the intervention of a jury, resulting in a judgment for the surety company and a judgment against the heating company for the penalty of the bond and an assessment of plaintiffs damages at the sum of twenty-five hundred dollars. The plaintiffs have appealed from the judgment releasing the surety company and the heating company has appealed from the judgment against it. The two appeals are submitted here upon a joint record.

¥e will first dispose of plaintiffs’ exceptions. As before stated the claim of the surety company was, that as to the boilers the plaintiffs had made an independent contract with the Springfield Boiler and Manufacturing Company, and that in respect to the instalment to be paid when the boilers were set, the contract was changed by plaintiffs, the boiler [633]*633company and the heating company, by- which that instalment was not to be paid until certain tests were applied to the boilers, and then only if the boilers proved adequate to furnish heat 'and light for the building, and that these subsequent agreements were made and carried out without its (the surety company) knowledge. In opposition to this the plaintiffs asserted that there was no independent agreement with the boiler company, and that the agreement between the plaintiffs, the steam heating company and the boiler company, that the third instalment should not be paid until the boilers were thoroughly tested, did not have the effect of releasing the surety company. Plaintiffs’ theory of this branch of the case was presented by the following instructions, which the court refused to give:

[634]*634 Declaration of law.

[633]*633“The court, sitting as a jury, declares the law to be, that if it appear and be found from the evidence in this case that the defendant Globe Steam Heating Company entered into a contract with the Springfield Boiler and Manufacturing Company for the construction of the boilers in question, that in pursuance of the said contract the latter company did build and construct the said boilers and ship them to St. Louis, that upon their arrival at St. Louis the defendant Globe Steam Heating Company set up and installed them in the Fraternal Building, that owing to delays in the construction of the said boilers they did not arrive in St. Louis until after the time when the said Globe Steam Heating Company was required to complete its contract with plaintiffs, that in consequence of this delay and before the arrival of the boilers, Bowman, one of the plaintiffs, wrote the Springfield Boiler and Manufacturing Company urging the speedy completion of the boilers and suggested in the letter addressed to the latter company about the time the said boilers were finished the desirability of making arrangements whereby the payment of the contract price of said boilers be made direct to the manufacturers thereof by plaintiffs; that after the arrival of the said boilers [634]*634in St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martin v. Whites
106 S.W. 608 (Missouri Court of Appeals, 1907)
Exchange Bank v. Thuringia Insurance
83 S.W. 534 (Missouri Court of Appeals, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
80 Mo. App. 628, 1899 Mo. App. LEXIS 219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowman-v-globe-steam-heating-co-moctapp-1899.