Bowles Construction Company v. Vernon Bridwell D/B/A Tri-State Mechanical

CourtCourt of Appeals of Texas
DecidedNovember 7, 2002
Docket11-02-00079-CV
StatusPublished

This text of Bowles Construction Company v. Vernon Bridwell D/B/A Tri-State Mechanical (Bowles Construction Company v. Vernon Bridwell D/B/A Tri-State Mechanical) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowles Construction Company v. Vernon Bridwell D/B/A Tri-State Mechanical, (Tex. Ct. App. 2002).

Opinion

                                                             11th Court of Appeals

                                                                  Eastland, Texas

                                                                        Opinion

Bowles Construction Company

Appellant

Vs.                   No. 11-02-00079-CV -- Appeal from Comanche County

Vernon Bridwell d/b/a Tri-State Mechanical

Appellee

This is an appeal from a judgment in favor of Vernon Bridwell d/b/a Tri-State Mechanical in a pipeline construction case.  A jury awarded damages under a theory of quantum meruit.  The jury also awarded attorney=s fees.  Because we find that the evidence was factually and legally sufficient to support the awards, we affirm. 


Upper Leon River Municipal Water District (Water District) awarded Bowles Construction Company a 1.6 million dollar contract which, among other things, provided for the construction of a 15-mile pipeline from Comanche into De Leon.  Vernon Bridwell, owner of Tri-State Mechanical, contacted Bowles Construction Company and indicated an interest in performing the pipeline part of the project.  The parties met in Houston to discuss the job and to determine whether Bridwell could do the work.  Later, R. E. (Potter) Bowles, Bridwell, and Bridwell=s superintendent met in Comanche to discuss a contract for the pipeline project.  The three drove to the job site from Comanche to De Leon looking at the area where the pipeline would be laid.  During this time, the three discussed the type of sub-surface to be dug.  The surface appeared to be sandy peanut farms.  The Water District had drilled test holes along the pipeline right-of-way, and the bore logs showed no rock in the area.  The three agreed that a contractor could dig about 1,000 feet a day.  After driving the route and discussing the bore logs and the project, Bowles Construction Company and Bridwell entered into an oral contract for $2.90 per lineal foot. Bridwell=s crew began work in November 1996.  Shortly after beginning digging, the crew ran into rock.  Bridwell=s crew did not have the proper equipment to dig in rock.  Both Bridwell and Bowles testified that Bridwell informed Bowles Construction Company of the rock problem.  At Bowles Construction Company=s direction, Bridwell then moved to another location on the pipeline project, and the digging went fairly easily into Comanche. The crew then returned to where it first encountered rock but could not dig the rock with the equipment they had.  Bridwell testified that he spoke with Bowles and again told him of the problem.  Bridwell testified that Bowles told him to get rock equipment to dig the rock and that they would settle up at the end of the job.  Bowles denied making such a statement to Bridwell.

Bridwell finished the job in November 1997.  The superintendent for Bridwell testified that Bridwell dug about 17,038 lineal feet of rock.  An estimator for Bridwell testified that $10 per lineal foot is a reasonable charge for digging rock.  By their answer, the jury found that Bowles Construction Company had knowledge that Bridwell had expended extra labor and expected to be paid for that labor.  The jury also found that Bowles Construction Company committed no fraud.  The jury awarded Bridwell $70,266 as damages under a quantum meruit theory.  The jury also awarded attorney=s fees to Bridwell.  

In its first point of error, Bowles Construction Company argues that, because there was an express contract between the parties that covered all work necessary to complete the job and because the jury found that there was no fraud on the part of Bowles Construction Company, Bridwell cannot recover under quantum meruit. 

A party cannot recover under quantum meruit if the subject matter is covered by an express contract unless there is a finding of fraud.  Truly v. Austin, 744 S.W.2d 934 (Tex.1988).  If there is no contract or if there is a contract and fraud exists, a party may recover under the theory of quantum meruit if it is shown that valuable services were rendered or materials furnished for the person sought to be charged; that the services and materials were accepted by the person sought to be charged and were used and enjoyed by him; and that the circumstances reasonably notified the person sought to be charged that the claimant in performing such services was expecting to be paid by the person sought to be charged.  Vortt Exploration Company, Inc. v. Chevron U.S.A. Inc., 787 S.W.2d 942 (Tex.1990).


In reviewing a legal insufficiency claim, the court must consider only the evidence and inferences supporting the judgment and disregard all the evidence and inferences to the contrary.  Leitch v. Hornsby, 935 S.W.2d 114 (Tex.1996).  A legal sufficiency point will be sustained when:  (a) there is a complete absence of evidence of a vital fact; (b) the court is barred by rules of law or of evidence from giving weight to the only evidence offered to prove a vital fact; (c) the evidence offered to prove a vital fact is no more than a mere scintilla; or (d) the evidence conclusively establishes the opposite of a vital fact.  Merrell Dow Pharmaceuticals, Inc. v. Havner, 953 S.W.2d 706, 711 (Tex.1997), cert. den=d, 523 U.S. 1119 (1998).  A legal insufficiency challenge must be overruled if the record contains any evidence of probative force to sustain the finding.  Leitch v. Hornsby, supra.  When reviewing a factual insufficiency challenge, the court must consider, weigh, and examine all of the evidence which supports or undermines the jury's finding.  Plas‑Tex, Inc. v. U.S. Steel Corporation, 772 S.W.2d 442, 445 (Tex.1989).  It is the jury's role to judge the credibility of the evidence, to assign the weight to be given to testimony, and to resolve inconsistencies within or conflicts among the witnesses= testimony.  Corpus Christi Area Teachers Credit Union v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

De Los Santos v. Southwest Texas Methodist Hospital
802 S.W.2d 749 (Court of Appeals of Texas, 1990)
Merrell Dow Pharmaceuticals, Inc. v. Havner
953 S.W.2d 706 (Texas Supreme Court, 1997)
Corpus Christi Area Teachers Credit Union v. Hernandez
814 S.W.2d 195 (Court of Appeals of Texas, 1991)
Truly v. Austin
744 S.W.2d 934 (Texas Supreme Court, 1988)
Shearer v. Allied Live Oak Bank
758 S.W.2d 940 (Court of Appeals of Texas, 1988)
Plas-Tex, Inc. v. U.S. Steel Corp.
772 S.W.2d 442 (Texas Supreme Court, 1989)
Vortt Exploration Co., Inc. v. Chevron USA, Inc.
787 S.W.2d 942 (Texas Supreme Court, 1990)
Roylex, Inc. v. Avco Community Developers, Inc.
559 S.W.2d 833 (Court of Appeals of Texas, 1977)
Wiley v. Bertelsen
770 S.W.2d 878 (Court of Appeals of Texas, 1989)
Jones v. Kelley
614 S.W.2d 95 (Texas Supreme Court, 1981)
Western Casualty & Surety Co. v. Preis
695 S.W.2d 579 (Court of Appeals of Texas, 1985)
In Re Barr
13 S.W.3d 525 (Texas Supreme Court, 1999)
Leitch v. Hornsby
935 S.W.2d 114 (Texas Supreme Court, 1996)
MacKey v. MacKey
721 S.W.2d 575 (Court of Appeals of Texas, 1986)
Pic Realty Corp. v. Southfield Farms, Inc.
832 S.W.2d 610 (Court of Appeals of Texas, 1992)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Bowles Construction Company v. Vernon Bridwell D/B/A Tri-State Mechanical, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowles-construction-company-v-vernon-bridwell-dba--texapp-2002.