Bowery v. Babbit

128 So. 801, 99 Fla. 1151
CourtSupreme Court of Florida
DecidedMay 20, 1930
StatusPublished
Cited by34 cases

This text of 128 So. 801 (Bowery v. Babbit) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowery v. Babbit, 128 So. 801, 99 Fla. 1151 (Fla. 1930).

Opinions

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 1153 The appellant, whom we shall refer to as intervenor, was permitted by the court to intervene and file a cross-complaint for the enforcement of a lien for labor and material in a suit for the foreclosure of a real estate mortgage instituted by Searles Babbit, one of the appellees, whom we shall refer to as complainant, against L. F. Hart and his wife, Stella G. Hart, the other appellees, whom we shall refer to as the defendants. *Page 1154

In his amended bill of complaint, the original bill having been filed on the 14th day of June, 1927, the intervenor alleged substantially that on the 22nd day of October, 1925, he entered into an agreement with the defendant, L. F. Hart, whereby he, the intervenor, was to erect for said defendant a residence and garage on certain described property, being the same property described in the mortgage sought to be foreclosed by the complainant, for the amount of the costs of labor and materials furnished and used in the construction of said buildings and in addition thereto, 10% of the costs of said labor and material; that he furnished such labor and materials until the 19th day of June, 1926, at which time the defendant was and is still indebted to him on said contract in the sum of $10,800.12, with legal interest from said 19th day of June, 1926; that the complainant claims a lien against the property by reason of a mortgage in the sum of $10,000.00, executed by the defendants on March 27, 1926, and filed for record April 1, 1926, which lien intervenor alleges is inferior in dignity and subject to the lien and claim of intervenor, because at the time it was executed and delivered, intervenor was engaged in furnishing materials and labor for the said buildings and that said buildings were then in an uncompleted state and were in progress of construction. Intervenor's amended bill was taken as confessed by the defendants. The complainant filed an answer to the said amended bill and in his answer denied that the buildings, at the time of the execution and delivery of the mortgage and recording of same, were in an uncompleted state and also denied that they were at said time in progress of construction, and averred the truth to be that at such time, the buildings were not in an uncompleted state and were not in progress of construction, but on the contrary were in a completed state and that *Page 1155 when he took the said mortgage, he had no knowledge of the claim of the intervenor. He further denied that the intervenor furnished labor and material until the 19th day of June, 1926, and averred the truth to be that said buildings were completed not later than March 27, 1926. The complainant in his said answer did not invoke Section 3530, Rev. Gen. Stats., 1920, Section 5393, Comp. Gen. Laws of Fla., 1927, as a bar to the enforcement of the alleged claim of the intervenor upon the issues made. Testimony was taken before a special examiner, and upon his report, the chancellor made and entered a final decree in which he dismissed the "bill of intervention or cross-complaint of" the intervenor and foreclosed the mortgage of complainant.

In the findings of the chancellor, as embodied in said decree, appears the following paragraph:

"That the building in question had been substantially completed at the time complainant's lien accrued; that complainant had no notice of Bowery's (intervenor's) lien when complainant's lien accrued; and that the Bowery suit was not brought within twelve months from the completion of the work and the furnishing of materials."

Prior to the entry of the decree, the intervenor, being advised by the chancellor of what his findings would be, moved the court to incorporate into the final decree certain other findings which he, the intervenor, desired to have made and which were specifically set out in the motion, but this motion was denied. From the final decree, the intervenor appealed to this Court and has assigned here as error, the denial of the motion that certain findings be incorporated into the final decree, the entering of the final decree and finding therein that the buildings in question had been substantially completed at the time complainant's *Page 1156 lien accrued and that intervenor's suit was not brought within twelve months from the completion of the work and the furnishing of the materials and also the dismissal of intervenor's bill of complaint.

The court committed no error in denying intervenor's motion that certain findings be incorporated in the final decree. 10 R. C. L., Section 346, page 560. Equity Rule 88.

In the above quoted paragraph of the decree, the court used the words "that the building in question had been substantially completed at the time complainant's lien accrued." This language implies that something remained to be done which required the use of labor or material or both tocomplete the building. As to whether the building was completed, there is a conflict in the evidence; that is, if we are to consider the hanging and placing of screens, putting hardware on the windows, easing up the doors, placing a medicine cabinet in the bathroom, and putting hardware on the garage doors as being necessary to the completion of the building. Having in mind such conflict in the evidence, as well as the finding of the court, we are not prepared to say that the building was not in an uncompleted state, or that it was not in progress of construction when the mortgage to the complainant was executed and delivered. The court must have concluded from the evidence that the work on the building, though only substantially completed when the mortgage was given, was completed soon after the accrual of complainant's mortgage lien, for in the same quoted paragraph, it is made to appear that the court found that the "Bowery (intervenor's) suit was not brought within twelve months from the completion of the work and the furnishing of materials."

We are not advised upon what ground intervenor's bill was dismissed. It might have been dismissed because of *Page 1157 the finding of the court that the building was "substantially completed" when the mortgage was executed; hence it is necessary for us to decide whether a "substantial" completion of the labor on and the furnishing of materials for the building, gave priority to the mortgage over the statutory lien for labor and materials, notice of which had not been filed as the law requires.

Paragraph 1 of Section 3517, Rev. Gen. Stats., 1920, Section 5380, Comp. Gen. Laws of Florida, 1927, reads as follows:

"As against the owner, absolute or limited, of the property, real or personal, upon which a lien is claimed, or person deriving through his death, or purchasers or creditors with notice, the lien hereinbefore provided for shall be acquired by any person, in privity with such owner, by the performance of the labor or the furnishing of the materials. Any purchaser or creditor whose title, interest, lien or claim in or to the property shall be created, or shall arise, while the construction or repair of such property as aforesaid is in progress shall be deemed and held to be a purchaser or creditor with notice."

It is well settled here that:

"Under paragraph 1 of Sec. 3517, Rev. Gen. Stats. (Section 5380, Comp. Gen.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alvarado v. Estate of Kidd
205 So. 3d 1188 (Supreme Court of Alabama, 2016)
Dove v. McCormick
698 So. 2d 585 (District Court of Appeal of Florida, 1997)
Beach v. Great Western Bank
692 So. 2d 146 (Supreme Court of Florida, 1997)
Beach v. Great Western Bank
670 So. 2d 986 (District Court of Appeal of Florida, 1996)
SPECIAL DISABILITY TR. FUND v. Southern Bell Telephone and Telegraph Co.
551 So. 2d 575 (District Court of Appeal of Florida, 1989)
Air Ambulance Network, Inc. v. Floribus
511 So. 2d 702 (District Court of Appeal of Florida, 1987)
DIVERSIFIED MORTG. INV. v. Benjamin
345 So. 2d 392 (District Court of Appeal of Florida, 1977)
Neil W. Gillies v. Aeronaves De Mexico, S. A.
468 F.2d 281 (Fifth Circuit, 1972)
Culbertson v. Seacoast Towers East, Inc.
232 So. 2d 753 (District Court of Appeal of Florida, 1970)
Culbertson v. Seacoast Towers East, Inc.
212 So. 2d 646 (Supreme Court of Florida, 1968)
Hughey v. Stevmier, Inc.
190 So. 2d 410 (District Court of Appeal of Florida, 1966)
Fowler v. Matheny
184 So. 2d 676 (District Court of Appeal of Florida, 1966)
Stilley v. Post
148 So. 2d 569 (District Court of Appeal of Florida, 1963)
Adams v. Kenson Supply Co.
137 So. 2d 27 (District Court of Appeal of Florida, 1962)
Trushin v. Brown
132 So. 2d 357 (District Court of Appeal of Florida, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
128 So. 801, 99 Fla. 1151, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowery-v-babbit-fla-1930.