Bouton v. Potomac Edison Co.

383 A.2d 669, 282 Md. 142, 1978 Md. LEXIS 356
CourtCourt of Appeals of Maryland
DecidedMarch 10, 1978
Docket[No. 96, September Term, 1977.]
StatusPublished
Cited by6 cases

This text of 383 A.2d 669 (Bouton v. Potomac Edison Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bouton v. Potomac Edison Co., 383 A.2d 669, 282 Md. 142, 1978 Md. LEXIS 356 (Md. 1978).

Opinion

Orth, J.,

delivered the opinion of the Court.

This appeal concerns an eminent domain action 1 in the Circuit Court for Frederick County by which The Potomac Edison Company (the Company) obtained, by an easement in perpetuity, land in Frederick County owned by Donald M. Bouton and wife (Bouton) 2 for the route of an overhead electric transmission line, designed to carry in excess of 69,000 volts, 3 to run from its Carroll Station in Carroll County to its proposed Mt. Airy Station in Frederick County. The inquisition of the jury awarded Bouton $24,200 as damages for the easement. Maryland Rule U 19 g. Bouton appealed from the final judgment entered thereon to the Court of Special Appeals. We issued a writ of certiorari before decision by the intermediate court.

I

A prerequisite to the exercise of the Company’s right of eminent domain was that it obtain from the Maryland Public Service Commission (the Commission) a certificate of public convenience and necessity for the construction of the line. Maryland Code (1957, 1975 Repl. Vol.) Art. 78, “The Public Service Commission Law” (the Law), § 54A and § 54B (a). Upon application by the Company, the Commission granted the certificate by its order No. 61016, issued 13 November 1974 after due compliance with the Law as to application, notice, public hearing and factors to be considered. See § 54A and § 54B (a) and (d).

*145 In granting the certificate to construct the line, the Commission ordered:

“(1) That a Certificate of Public Convenience and Necessity be, and it is hereby, granted to [the Company] for the construction of a 230 kv transmission line as set forth in the application, except as hereinafter modified.
“(2) That the following conditions are made part of said Certificate of Public Convenience and Necessity:
“(g) That with respect to the area where the proposed transmission line passes in the vicinity of the Boy Scout Camp, the Company be required to make a modification of its proposed line routing so as to place approximately an additional 100 feet between the transmission line and the pond; the movement of the line, in order to effectuate this modification, should be confined to and remain within the wooded area southwest of the pond____”

On 22 July 1975 the Company wrote Wilson B. Stringer, Executive Assistant-Chief Examiner of the Commission (the Examiner) that it had modified the proposed line routing and that based upon its belief that the route modifications “comply fully with the conditions stated in the Commission certificate,” it was moving forward to acquire right of way and to construct the line. We observe that the authority of the Commission to prescribe the exact location of the line route is not raised by the parties and we do not consider it.

II

Subsequent to the filing of the initial pleading by Bouton in the condemnation action, the Company filed a motion for summary judgment on the issue contained in paragraph THIRD of its petition for condemnation. Maryland Rule 610 *146 a 1 and 3. Paragraph THIRD stated that the Company was fully authorized to negotiate for and to buy from the owners of real estate in Maryland a right of way or easement in perpetuity for transmission and power lines and that, in the event it was unable to agree with such owners on the acquisition of such estate or interest, it had authority to exercise the power of eminent domain and to condemn such estate or interest for its use in perpetuity as provided by Maryland Code (1974) Real Property Article, Title 12, “Eminent Domain.” The Company declared that there was no genuine dispute as to any material fact and that it was entitled to judgment as a matter of law. 4

In their answer to the motion, Bouton, asserting that there was dispute as to material fact, sought a denial of the motion on two grounds. The first ground, that the Company did not have the basic power to acquire property by condemnation, is not raised on appeal, and we do not consider it. 5 The second ground was that, assuming the Company possessed the basic power to condemn, it had no authority to acquire by the exercise of its right of eminent domain the easement which it sought over Bouton’s land. The Company did not have such authority, the answer asserted, because it was “guilty of exercising bad faith and abuse of discretion in the location of the proposed transmission line route on [Bouton’s land],” because “the transmission line route approved by the [Commission] was modified by the [Company] in accordance with the request of a private property owner for a strictly private purpose, without notice to [Bouton],” and because Bouton was “deprived of due process of law and equal *147 protection of the laws when an ex parte hearing was held at the [Commission] to consider modification and relocation of the proposed transmission line route on [Bouton’s land] and adjoining property.”

The Company’s position, which it presents on appeal and which it consistently relied upon below, is simply that “[hjaving failed to appeal the Commission’s order approving the location of the transmission line, Bouton may not collaterally attack that order in condemnation proceedings.” This position is unsound for two reasons. First, it is bottomed on the incorrect premise that the Commission order of 13 November 1974 approved the line route which was the basis of the easement sought to be condemned. The order did no more than approve the line route as originally proposed by the Company subject to the modification to be made by the Company pursuant to condition (2) (g). It is true that the Examiner sought a review of the modified line route by the Engineering Division of the Commission and received a memorandum from the Chief Engineer which concluded, on the basis of a review by a staff engineer, whose memorandum was attached, that “[w]e have determined that the modification as proposed by Potomac Edison is in compliance with paragraph (g) of Order 61016.” In argument on the motion for summary judgment the Company’s attorney stated: “[W]e later got a letter from the Public Service Commission saying, ‘The rerouting is in accordance with the Public Service Commission order.’ ” The letter mentioned is not in the record before us. The statement of the Chief Engineer was only an expression of his opinion, and even if shared by the Examiner, is not a determination by the Commission itself. 6 In any event, it is obvious that the Commission order of 13 November 1974 may not be considered as approving whatever modification of the original route the Company believed to be in compliance with the condition, or, specifically, as approving the line route as here subsequently modified. We have not been referred to, nor do *148 we find in the record, a final order or decision by the Commission confirming that the modified route fulfilled the condition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mayor of Baltimore City v. Valsamaki
916 A.2d 324 (Court of Appeals of Maryland, 2007)
County Commissioners v. Schrodel
577 A.2d 39 (Court of Appeals of Maryland, 1990)
ALABAMA ELEC. CO-OP., INC. v. Watson
419 So. 2d 1351 (Supreme Court of Alabama, 1982)
Mayor of Baltimore v. Chertkof
441 A.2d 1044 (Court of Appeals of Maryland, 1982)
Bouton v. Potomac Edison Co.
418 A.2d 1168 (Court of Appeals of Maryland, 1980)
Potomac Edison Co. v. Bouton
405 A.2d 755 (Court of Special Appeals of Maryland, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
383 A.2d 669, 282 Md. 142, 1978 Md. LEXIS 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bouton-v-potomac-edison-co-md-1978.