Boundless Energy NE, LLC v. Public Service Commission

57 Misc. 3d 610, 63 N.Y.S.3d 182
CourtNew York Supreme Court
DecidedJanuary 13, 2017
StatusPublished

This text of 57 Misc. 3d 610 (Boundless Energy NE, LLC v. Public Service Commission) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boundless Energy NE, LLC v. Public Service Commission, 57 Misc. 3d 610, 63 N.Y.S.3d 182 (N.Y. Super. Ct. 2017).

Opinion

OPINION OF THE COURT

Denise A. Hartman, J.

In this CPLR article 78 proceeding, petitioner Boundless Energy NE, LLC seeks to vacate a Public Service Commission (PSC) order finding transmission needs driven by public policy requirements, dated December 17, 2015 (transmission needs order). The PSC, following a comparative evaluation process, identified a need driven by public policy requirements to provide additional transmission capacity in the upstate-to-downstate corridor; invited specific applicants to submit all or part of their transmission development proposals to respondent New York Independent System Operator, Inc. (NYISO) for further review; and asked other applicants, including petitioner, to withdraw their original proposals or provide an explanation or statement of intent. Petitioner also challenges a PSC order dated February 23, 2016, denying rehearing and asks the court to direct NYISO to hold in abeyance further decisions with respect to the transmission needs order.

Because NYISO is not a proper party to this proceeding, NYISO’s motion to dismiss the petition as against it is granted.1 And because Boundless has not demonstrated that the PSC’s transmission needs order is contrary to law or irrational, the petition against the PSC is denied.

[612]*612The Alternating Current Transmission Proceedings

In 2012, the PSC solicited proposals to “increase transfer capacity through the congested transmission corridor, which includes the Central East and the [Upstate New York/Southeast New York (UPNY/SENY)] interfaces,” by 1,000 megawatts (proceeding on motion to examine alternating current transmission upgrades, R1323 at 2).2 Four transmission developers submitted 22 proposals, with Boundless submitting two of them. The proposals were submitted pursuant to the licensing and siting procedures of Public Service Law article VII. Referring to them as the alternating current transmission proceedings (AC transmission proceedings), the PSC performed a comparative analysis of the proposals, taking into consideration the anticipated transfer capacity increase, cost, and environmental impacts. In July 2015, PSC staff produced an interim report (R631). According to that report, the approval of a new 720 megawatt generation facility required the staff to update its analysis before issuing a final report (interim report at ii). The interim report recommended that a number of projects be eliminated from consideration, but proposed continued study of seven projects, including the Boundless proposals (interim report at 7-8).

NYISO’s Public Policy Transmission Planning Process

In August 2014, while the AC transmission proceedings were underway, NYISO commenced parallel proceedings to fulfill its public policy transmission planning role pursuant to NYISO’s Open Access Transmission Tariff (Tariff) with the Federal Energy Regulatory Commission (FERC) (see R729). FERC’s regulatory authority focuses on ensuring that generators have nondiscriminatory access to transmission facilities and that rates for such access are reasonable. NYISO’s solicitation of proposed public policy transmission needs resulted in multiple proposals, which NYISO forwarded to the PSC. Pursuant to the FERC Tariff, the PSC was required to identify public policy requirements driving transmission needs after notice-and-comment rulemaking in accordance with the State Administrative Procedure Act. In a July 20, 2015 order addressing public policy requirements for transmission needs, the PSC issued its determination with respect to other areas of the state, but [613]*613deferred its determination of public policy-driven transmission needs in the Eastern New York transmission corridor pending the staffs review in the AC transmission proceedings (R729).

The Combined Proceeding

In September 2015, PSC staff issued its final report, recommending that the PSC declare public policy needs for transmission facilities consistent with its identification of three proposals, not including Boundless’s, as best meeting transmission needs in a cost-effective manner, with minimal environmental impacts (R604).

After receiving the final report, on October 7, 2015, the PSC published a notice of proposed rulemaking, which stated that the PSC was “considering whether to adopt, modify, or reject, in whole or in part, certain proposals to relieve congestion between Upstate and Downstate New York to be transmission needs driven by Public Policy Requirements” (NY Reg, Oct. 17, 2015 at 91). The PSC then held hearings and conducted additional analyses.

The Challenged Orders

On December 17, 2015, the PSC issued an order finding transmission needs driven by public policy requirements (R464). In the order, the PSC, among other things, identified the transmission needs as a detailed portfolio of projects, divided into two segments; set criteria for NYISO to apply in evaluating proposed transmission solutions; requested the entities that had proposed the projects recommended in the final report to submit those project proposals to NYISO; requested that the remaining entities, including Boundless, withdraw their proposals; and required any entity that declined to withdraw its proposal to submit to the PSC a written explanation and declaration of future intent. It also declared that the transmission needs order constituted a written statement provided to NYISO as part of its public policy transmission planning process under FERC’s Tariff and a rule adopted under the State Administrative Procedure Act. On February 23, 2016, the PSC denied Boundless’s request for a rehearing after concluding that no error of law or fact had affected the December 2015 order (R463).

[614]*614Analysis

NYISO’s motion to dismiss is granted.

NYISO is not a proper party to this proceeding. The verified petition does not challenge any action by NYISO. Boundless does not contend that NYISO is a state agency.3 Therefore, the petition must be dismissed against NYISO unless it is a necessary party in this proceeding. CPLR 1001 requires joinder of a party if complete relief cannot be achieved without that party or if it would be inequitably affected by the outcome of the matter. “[I]n the context of governmental policies and programs which inevitably entail the involvement of numerous agencies, departments and officials, only those governmental entities that are primarily responsible for the challenged policy are necessary parties” (Matter of Mid Is. Therapy Assoc., LLC v New York State Dept. of Educ., 99 AD3d 1082, 1083 [3d Dept 2012] [internal quotation marks omitted]). Here, the challenged orders were issued by the PSC. Accordingly, the petition is dismissed against NYISO.

Boundless has not established a basis to invalidate the order finding transmission needs driven by public policy requirements.

Boundless argues that the PSC’s transmission needs order violates the State Administrative Procedure Act because it is not a rule of general applicability and instead addresses a specific portfolio of projects. According to Boundless, the challenged order effectively constitutes an adjudication of the AC transmission licensing proceeding commenced in 2012.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Medical Society v. Serio
800 N.E.2d 728 (New York Court of Appeals, 2003)
AAA Carting & Rubbish Removal, Inc. v. Town of Southeast
951 N.E.2d 57 (New York Court of Appeals, 2011)
Matter of Entergy Nuclear Indian Point 2, LLC v. New York State Department of State
130 A.D.3d 1190 (Appellate Division of the Supreme Court of New York, 2015)
Council of City v. Department of Homeless Services
3 N.E.3d 128 (New York Court of Appeals, 2013)
New York City Transit Authority v. New York State Department of Labor
666 N.E.2d 1336 (New York Court of Appeals, 1996)
Alca Industries, Inc. v. Delaney
709 N.E.2d 97 (New York Court of Appeals, 1999)
Roman Catholic Diocese v. New York State Department of Health
109 A.D.2d 140 (Appellate Division of the Supreme Court of New York, 1985)
California ex rel Lockyer v. Dynegy, Inc.
375 F.3d 831 (Ninth Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
57 Misc. 3d 610, 63 N.Y.S.3d 182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boundless-energy-ne-llc-v-public-service-commission-nysupct-2017.