Boucher & Slack Contractors, Inc. v. McLean

397 So. 2d 45, 1981 La. App. LEXIS 3809
CourtLouisiana Court of Appeal
DecidedMarch 23, 1981
DocketNo. 14490
StatusPublished
Cited by2 cases

This text of 397 So. 2d 45 (Boucher & Slack Contractors, Inc. v. McLean) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boucher & Slack Contractors, Inc. v. McLean, 397 So. 2d 45, 1981 La. App. LEXIS 3809 (La. Ct. App. 1981).

Opinion

MARVIN, Judge.

In Boucher & Slack Contractors, Inc. v. McLean, 382 So.2d 1030 (La.App.2d Cir. 1980), writ recalled, 391 So.2d 840 (La.1980), we upheld the right of the defendant, owner of an apartment complex, to exercise against the plaintiff, contractor for the complex, a letter of credit executed by the contractor in lieu of a performance bond for the contract. The owner’s exercise of the draw under the letter of credit was founded upon the owner’s supporting affidavit that $440,000 was owed in damages because the contractor failed to complete the contract with due and reasonable diligence, as required by the contract, which otherwise did not have a completion date.

The contractor then sought a declaratory judgment that it had timely performed the contract and that it was entitled to damages from the owner for exercising the letter of credit. The owner, of course, sought to prove the damages asserted in the exercise of the letter of credit.

. The trial court found that the contractor had not performed with due and reasonable diligence and rendered judgment for the owner for $77,228. The trial court denied attorney fees claimed by the owner for dissolving a TRO which earlier restrained hon[46]*46oring of the letter of credit. Both litigants appeal. The owner, in addition to attorney fees, seeks to increase the damage award. We affirm for the excellently detailed and supported reasons assigned by the trial court.

The contractor generally contends that the trial court erred in finding that 13 months was a reasonable time in which the contract should have been completed according to the particular circumstances under industry standards. The contractor argues that factors such as the effect of inclement weather, a fire during construction, labor and material shortages, and the owner’s unsuccessful negotiation for a guaranteed completion time of 18 months in the contract, support the contrary finding that the substantial completion in I6V2 months was fulfillment of the contract requirement of completion with due and reasonable diligence.1

The owner generally contends that the evidence supports the claimed increase in damages, based particularly upon a 10-month “reasonable” completion date, and that the law compels that the owner be awarded attorney fees for dissolution of a wrongly issued TRO.2

The essence of the several contentions of the litigants is whether or not the trial court manifestly erred or abused its discretion in weighing the evidence presented and in determining the amount and the basis of tile eventual award. We find no such error or abuse.

The trial judge was impressed with the testimony of the owner’s expert witnesses. While the contractor’s experts testified in generalities and did not exhibit specific familiarity with the project, the owner’s experts exhibited specific and der tailed knowledge of the project. The testimony of the owner’s experts was given greater weight. This was within the trial court’s discretion and should not be disturbed on appeal unless that discretion is abused. See State, Department of Highways v. DeJean, 322 So.2d 265 (La.App.2d Cir. 1975) and Maddox v. Percy, 351 So.2d 1249 (La.App.1st Cir. 1977). The owner’s expert and lay testimony constitutes substantial evidence supporting the judgment and the trial court’s conclusion that 13 months was a reasonable completion time for a contract pursued with “due and reasonable diligence”.

The trial court’s award of damages was also well within its discretion. See CC Art. 1934(3). The basis of this award (loss of rental income) was particularized by the trial court. We find no error in the trial court’s analysis or assessment of damages and decline to reduce or to increase the judgment in this respect.

The trial court denied the owner attorney’s fees for dissolving the TRO after considering the background of the litigation, the manner in which it arose, the evidence [47]*47presented, the briefs filed, and all factors in the case.3 CCP 3608 states:

“Attorney’s fees for the services rendered in connection with the dissolution of a restraining order or preliminary injunction may be included as an element of damages ...” Our emphasis.

The clear language of the article gives the trial judge discretion to award attorney’s fees as a part of damages. We find no error or abuse of discretion in the denial of attorney’s fees.

We adopt, as our opinion, but do not publish, the very excellent and detailed reasons given in 23 pages by the trial court, and, at plaintiff’s cost, AFFIRM the judgment appealed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boucher & Slack Contractors, Inc. v. McLean
401 So. 2d 974 (Supreme Court of Louisiana, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
397 So. 2d 45, 1981 La. App. LEXIS 3809, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boucher-slack-contractors-inc-v-mclean-lactapp-1981.