Boston Gas Co. v. Century Indemnity Co.

793 F. Supp. 2d 511, 2011 U.S. Dist. LEXIS 69019, 2011 WL 2552639
CourtDistrict Court, D. Massachusetts
DecidedJune 28, 2011
DocketCivil Action 02-12062-PBS
StatusPublished
Cited by1 cases

This text of 793 F. Supp. 2d 511 (Boston Gas Co. v. Century Indemnity Co.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boston Gas Co. v. Century Indemnity Co., 793 F. Supp. 2d 511, 2011 U.S. Dist. LEXIS 69019, 2011 WL 2552639 (D. Mass. 2011).

Opinion

MEMORANDUM AND ORDER

PATTI B. SARIS, District Judge.

INTRODUCTION

Boston Gas seeks indemnity from Century for costs incurred in remediating environmental contamination at its former manufactured gas plant sites. The site at issue in these motions, Commercial Point, was the subject of a nine-day trial in 2007. The jury returned a verdict in favor of Boston Gas for approximately $1.7 million, but judgment was never entered. In the interim, the First Circuit and the Massachusetts Supreme Judicial Court (“SJC”) have ruled on issues raised by Century’s appeal of the verdict on another site, Everett, and now the parties contest the impact that those rulings should have on the Commercial Point action. In the present motions, both parties request that judgment be entered in their favor.

I. Background

Boston Gas operated a number of manufactured gas plants (“MGPs”) in the latter half of the 19th and into the 20th centuries. These plants created substantial environmental contamination requiring remediation. Under Massachusetts state law, Boston Gas is liable for the costs of that environmental remediation. See Mass. Gen. Laws ch. 21E (2006). Boston Gas had purchased liability insurance policies from Century’s predecessor, INA, providing for coverage between the years 1951 and 1969. Faced with environmental response costs at a number of former MGP sites, Boston Gas sought indemnity from Century for the costs of remediation, but Century argued that the clean-up costs were not covered by Boston Gas’ policies.

So far, trials have been held on two sites, Everett and Commercial Point, before another judge of this Court. The Everett trial occurred first, in 2005; the jury found for Boston Gas, and Century appealed to the First Circuit. A primary subject of the appeal was the question of how costs should be allocated across multiple insurers in cases of so-called “long-tail claims” involving environmental damage occurring over an extended period of time. Based on governing state case law at the time, the District Court in the Everett trial utilized an “all sums” or “joint and several” allocation method, whereby an insurer is responsible for an insured’s total remediation costs as long as some property damage for which the insured is legally obligated to pay occurs during the policy period. The First Circuit certified the allocation question to the Massachusetts Supreme Judicial Court, which ruled that the proper method of allocation was not joint and several, but rather pro rata; that is, each insurer should be required to pay only those costs associated with damage happening during its policy period. See Boston Gas Company v. Century Indemnity Company, 454 Mass. 337, 910 N.E.2d 290, 306 (2009).

*515 The Commercial Point was tried in 2007, prior to the SJC’s ruling on allocation. Boston Gas operated an MGP at Commercial Point from 1886-1930, and Boston Gas has spent approximately $2.7 million for environmental remediation at the site. The jury at trial was asked to determine the amount of Boston Gas’ damages, which involved first determining Boston Gas’ total liability and then subtracting any amounts excluded by the policy language.

The parties disagreed over the jury instructions. Based on the “all sums” theory of allocation, Boston Gas argued that the jury should only be asked whether property damage existed at Commercial Point at any point during Century’s policy period. See Trial Tr., March 8, 2007 at 14 (“We don’t have to prove that all of the damage to the entire site happened during their policy period. Once we’ve showed there’s continuous damage during their policy period, under the caselaw in Massachusetts, they have to pay ... all sums of our liability, including for damage before the policy period and damage after the policy period.”).

Century argued that, regardless of the allocation issue, the policies only required it to indemnify for third party liability; as such, Century requested that the jury be asked whether property damage resulting in liability occurred during Century’s policy period. See id. at 19 (“This is a liability policy. So, let’s just focus on not was there some damage on the site, but is it the damage for which they’re' being held liable.”). A prominent theme of Century’s third party liability argument at trial had been that, while groundwater contamination existed at the site, that contamination was mild and did not require remediation under the Massachusetts Contingency Plan (“MCP”), the governing regulatory scheme. See id. at 20 (“THE COURT: Well, as I understand the Massachusetts law, if there is contaminated groundwater, ipso facto, there is liability. MS. SANTELLE [for Century]: That’s not the liability they’re addressing, your Honor. This is the disconnect.”). Century’s proposed verdict question would have emphasized that liability was required in order to trigger Century’s duty to pay. See Century’s Proposed Jury Questions, Doc. No. 527 (“Do you find that during any, some, or all of the years between 1951 and 1969, there was physical injury to property at the Commercial Point site for which Boston Gas is liable and is seeking coverage from Century Indemnity?”).

The final version of the jury question on property damage (Question 1) seemed to favor Century’s approach, asking: “Was the Commercial Point site exposed to hazardous materials in one or more years during the policy period, 1951 to 1969, and did the release of these hazardous materials result in liability from continuing contamination of soil, groundwater, air and/or sediment on the site (property damage)?” (emphasis added). In the oral instructions to the jury on Question 1, the Court stated, “If you find that the plaintiff has proven that there was property damage that resulted in continuing contamination, then the answer is ‘Yes’ for any year in which you so found.” Trial Tr., March 8, 2007 at 136. This oral instruction did not include the requirement that such contamination had to have resulted in third party liability on the part of Boston Gas. The Court did specify later, though, in its instruction on the “damages” question (Question 5), that “the plaintiff is entitled to recover only that portion of its costs attributable to its liability or potential liability for contamination.” Id. at 143. The jury answered Question 1 “Yes” for all of the policy years.

The verdict form also required the jury to make findings on whether certain costs were excluded from coverage. Two poten *516 tial exclusions existed. The first was the “expeeted/intended” exclusion, under which the policies did not provide coverage for any damage that Boston Gas caused knowingly or intentionally. The second was the “owned property” exclusion, which barred coverage for any costs spent on remediating the insured’s own property (as opposed to addressing liability for damage to third party property). The jury found that the owned property exclusion did apply to one area of the site (the “Keyspan upland” portion), but that the “expected/intended” exclusion did not apply.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Malpica-Cue v. Fangmeier
2017 COA 46 (Colorado Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
793 F. Supp. 2d 511, 2011 U.S. Dist. LEXIS 69019, 2011 WL 2552639, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boston-gas-co-v-century-indemnity-co-mad-2011.