Boston Fish Market Corporation v. Universal Insurance Company, Libellant

388 F.2d 773, 1968 U.S. App. LEXIS 8292
CourtCourt of Appeals for the First Circuit
DecidedJanuary 24, 1968
Docket6978_1
StatusPublished
Cited by7 cases

This text of 388 F.2d 773 (Boston Fish Market Corporation v. Universal Insurance Company, Libellant) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boston Fish Market Corporation v. Universal Insurance Company, Libellant, 388 F.2d 773, 1968 U.S. App. LEXIS 8292 (1st Cir. 1968).

Opinion

McENTEE, Circuit Judge.

This is a libel in admiralty 1 to recover for damage to the fishing vessel Terra Nova and its contents as the result of a fire that occurred aboard the vessel on June 26, 1964, while it was berthed at respondent’s fish pier in Boston 2 undergoing repairs.

As part of its operation, respondent maintained eight fire hydrants at its pier. Three of these, including Hydrant No. I, which was situated nearest to the Terra Nova, had been previously shut off by the respondent and were not operative on the day of the fire. No notice of this inoperative condition was given to those connected with the vessel or to the Boston Fire Department, nor was this apparent to anyone attempting to use these three hydrants.

On the morning of June 26th a passerby on the pier yelled to one DeVeau, who was working for an independent contractor aboard the Terra Nova, that the vessel was on fire. DeVeau immediately asked him to call the Boston Fire Department. The first fire engine to arrive connected its 2% inch hose to hydrant No. I but, getting no water, *775 disconnected it and proceeded to the next nearest hydrant that, was in working condition. Libellant contends that because respondent did not maintain No. I hydrant in proper working order, the fire department’s efforts were substantially delayed; that during this delay the fire grew worse and did much more damage than would otherwise have been done. The ultimate question is whether the respondent is liable for the aggravated damage caused by the delay and, if so, in what amount.

The district court, sitting without a jury, found that the fire started “at or about 10 A.M.” and that because of the failure of hydrant No. I to function there was a delay of five to eight minutes, for which it held the respondent liable. It also found that the total damage to the vessel and its contents by reason of the fire was $76,750; that only about 50% of this damage would have occurred “had the fire department not been delayed by hooking to and unhooking from hydrant No. I” and that “the other 50% was due to the delay in getting water from the second hydrant, a delay exclusively caused by the ineffectual effort to get water from hydrant I.” Accordingly, the court entered judgment for libellant for one-half of the amount of the total damage, plus interest. 3

Respondent’s first contention on appeal is that the libellant did not show any aggravated damage attributable to inadequacy of water supply beyond mere speculation and conjecture; also, that the trial court’s findings with reference thereto are not supported by the evidence.

Briefly, the pertinent evidence is as follows. DeVeau, the workman above mentioned, testified that the fire burned for about twenty-five minutes before the fire department arrived, during which period he applied two fire extinguishers to no avail; that when the first fire truck arrived there was smoke but no flame in the pilot house and by the time the firemen got water on the fire there was smoke, heat and flames extending half way to the top of the pilot house. He also stated that the delay occasioned by the inoperative hydrant was about twenty minutes. This witness did not testify, however, as to the actual time the fire started or was called to his attention.

The fire chief testified that his department received the call for assistance at 10:25 a. m., and that he arrived at the scene about three minutes later. He stated that when he arrived the hose was laid from hydrant No. 1 as far as the pier, and that they were disconnecting at the hydrant because it was inoperative. “I ordered them to shift the line. I would say it would take about a minimum of three minutes to shift that line to the next hydrant, which would make it 10:31.” While the witness testified that 5 to 8 minutes elapsed from the time of his arrival to the time water was brought through a large hose to the fire, in the light of this other testimony, and the absence of any direct testimony to that effect, it is not clear that he considered that all of the 5 to 8 minute interval before water was brought to the fire was delay occasioned by the inoperative hydrant. In addition, the chief stated that during this interval in getting water for their regular 2y2 inch hose, the firemen used a % inch hose from one of the trucks but the water supply was exhausted in about three minutes and apparently little benefit resulted. He further testified that he observed no change in the fire during this interval except that it got smokier. One Dorgan, a fish pier employee, testified that the pilot house and winch room were both ablaze before the fire department arrived.

Libellant’s expert Williams, a professor at the Massachusetts Institute of Technology and a chemical engineer who specializes in combustion, testified as to *776 the amount of damage likely to have been caused by the delay. His opinion was not based on personal observation of the vessel but was in answer to a hypothetical question. This question assumed that there was only a five to eight minute delay due to the faulty hydrant but made no mention whatever of how long the fire had been burning before the fire department arrived. He stated explicitly, however, that if the fire had been burning for twenty to twenty-five minutes before the fire department arrived it would be impossible to say what damage was occasioned by the delay; also, that if the fire had been going in the winch room for twenty-five minutes he could not tell how much heat damage had occurred in the pilot house.

Libellant’s marine surveyor was asked substantially the same hypothetical question in which the time of the fire department’s arrival was also omitted. In cross-examination he acknowledged that he did not know how long the fire had been burning before the fire department arrived and that this knowledge was essential in determining the effect of the subsequent five to eight minute delay.

The most important single question on the issue of aggravated damage is the length of time the fire had been burning before the fire department arrived, or more precisely, what period of time elapsed from the time the fire started to the time when water would have been brought to it if hydrant No. I were functioning. There is no direct testimony as to when this fire started. The nearest approach is DeVeau’s estimate that “possibly 25 minutes” elapsed between the discovery of the fire and the arrival of the first fire truck. The fire chief placed this latter time as 10:28 A.M. The trial court, as we have said, found that the fire started “about 10 A.M.”

Apart from the ultimate question of whether the court arrived at a proper result in this case, the more immediate one is the adequacy of the court’s findings. If the finding that the fire started “about 10 A.M.” is to be construed as a mere approximation or as a general introductory description of the occurrence, as libellant suggests, then we think it is imprecise and does not meet the requirements of Fed.R. Civ.P. 52(a). It seems unlikely, however, that an experienced judge would be unmindful of his obligation under this rule and neglect to make a finding on such a vital issue in the case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fry v. Jay Hatfield Mobility
Court of Appeals of Kansas, 2016
Gomes v. Commercial Union Insurance
783 A.2d 462 (Supreme Court of Connecticut, 2001)
Dado v. Jeeninga
743 N.E.2d 291 (Indiana Court of Appeals, 2001)
Lee v. Bell
379 S.E.2d 464 (Supreme Court of Virginia, 1989)
Alonso v. Fernandez
379 So. 2d 685 (District Court of Appeal of Florida, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
388 F.2d 773, 1968 U.S. App. LEXIS 8292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boston-fish-market-corporation-v-universal-insurance-company-libellant-ca1-1968.