Boston Edison Company v. Federal Energy Regulatory Commission, Towns of Norwood, Intervenors

611 F.2d 8, 1979 U.S. App. LEXIS 9423
CourtCourt of Appeals for the First Circuit
DecidedDecember 21, 1979
Docket79-1179, 79-1287
StatusPublished
Cited by3 cases

This text of 611 F.2d 8 (Boston Edison Company v. Federal Energy Regulatory Commission, Towns of Norwood, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boston Edison Company v. Federal Energy Regulatory Commission, Towns of Norwood, Intervenors, 611 F.2d 8, 1979 U.S. App. LEXIS 9423 (1st Cir. 1979).

Opinion

LEVIN H. CAMPBELL, Circuit Judge.

Boston Edison appeals from the Federal Energy Regulatory Commission’s orders striking down Edison’s temporary fuel adjustment surcharge. The surcharge was designed to recover approximately $2 million in fuel expenses which Edison incurred in generating power for certain of its wholesale customers, intervenors herein, during January and February 1976. These expenses were left unrecovered allegedly as a result of Edison’s conversion, in March 1976, from a two month lag billing formula to a current month formula. Under Edison’s old fuel adjustment clause, customers’ bills were based upon the cost of fossil fuel two months previous to the billing month. Thus, for example, customers’ bill for January were based on November fuel cost figures and February bills on December figures. When, in March 1976, Edison switched to a current month system (i. e., basing March bills on March figures) two months of fuel cost increases were allegedly left uncollected. According to Edison, it is entitled to the surcharge in order to recoup the January and February increases which would have been collected in March and April had the old, two month lag formula remained in effect; to deny the surcharge is to effect a gift of nearly $2 million to the intervenors.

Fuel adjustment clauses enable a utility to automatically pass on to its customers augmentations in the cost of fuel without continually having to file for rate increases. Public Service Co. of New Hampshire v. Federal Energy Regulatory Commission, 195 U.S.App.D.C. 130, 133, 600 F.2d 944, 947 (D.C.Cir.1979), petition for cert. filed 48 U.S.L.W. 3049 (Aug. 1, 1979) (No. 79-169). There are two basic types of fuel adjustment clauses: cost of service and fixed rate. With the first type, the utility recovers its precise actual fuel expenditures, but on a deferred basis. Under the second, reimbursement is only approximated — customers’ bills are calculated on the basis of costs incurred during a past test period. If the costs established in the test period differ from those actually experienced, over or under collection may result; however, once the customer pays the amount due as determined by the filed formula no more is owed regardless whether the utility has in fact recovered its actual costs. While the Commission prescribes certain guidelines to which fuel adjustment clauses must conform, 18 C.F.R. § 35.14, it does not dictate which type of clause must be utilized and thus the utility may choose either type.

The Commission rejected Edison’s argument that its old clause was of the first type — designed to recover all fuel costs from past months on a deferred basis — and concluded that it instead “used costs from the second preceding month only to calculate the current month’s fuel adjustment charge.” Quoting from the Administrative Law Judge, the Commission stated

“[T]he intent of the [superseded] fuel adjustment [clause] . . . was not to permit the recovery in March of expenses incurred in January, but to permit the use of January fuel cost data as a measure of March fuel costs . . . . When in March 1976 Edison switched to a system which did not rely on data from the second preceding month, it was therefore current in its cost recovery.”

In reaching this conclusion the Commission looked not only at the wording of the clause 1 but also to its actual operation. The old clause was not designed to achieve *10 dollar for dollar recovery as would a true cost of service tariff nor did it accomplish that result since fuel costs and energy use were not matched under the clause; rather, fuel costs from one month were applied to energy use in the second succeeding month. Thus, in periods of rising energy consumption, under recovery would result while over recovery would occur in seasons when energy use fell. 2 While the clause may have functioned over the long run with satisfactory precision to Edison, this does not detract from the Commission’s conclusion that the clause was not designed to actually match revenues with costs in the manner of a cost of service clause. Nor did Edison assess any additional charges on customers who left the system as would be expected had Edison operated with a true deferred billing system.

We think the superseded clause’s discrepancies in operation from that of a cost of service tariff — mismatching of fuel costs with energy use and failing to assess additional sums on customers who left the service — considered in light of the wording of the clause support the Commission’s decision that once a monthly bill was paid nothing more was owed; the fuel clause was not of the cost of service variety and did not guarantee recovery of deferred fuel costs. See Public Service Co. of New Hampshire v. Federal Energy Regulatory Commission, supra, 195 U.S.App.D.C. 130, 600 F.2d 944, and Virginia Electric Power Co. v. Federal Energy Regulatory Commission, 580 F.2d 710 (4th Cir. 1978), rejecting similar claims by utilities that their superseded fuel adjustment clauses had provided for recovery of actual past costs on a deferred billing basis. 3

In Maine Public Service Co. v. Federal Energy Regulatory Commission, 579 F.2d 659 (1st Cir. 1978), this court was presented with a question of the legality of a similar surcharge designed to bridge the gap between prior and later fuel adjustment clauses. The court vacated- the Commission’s order disallowing the surcharge because it felt the Commission had erroneously viewed itself as being automatically precluded by inapposite judicial authority from approving the surcharge and had not undertaken an indepth analysis of the propriety of the surcharge as a matter of rate-making policy. 4

The Commission did, in this cáse, undertake the policy appraisal called for in Maine *11 Public Service and has concluded that the surcharge should not be allowed. The Commission also indicates that it still adheres to at least part of its prior legal analysis, and now presents cogent arguments for this position, but its decision distinctly states that under either its legal or its policy analysis the surcharge falls.

At the root of the Commission’s decision is the determination that, as between customer and utility, it is the utility which should bear the risk of any under recovery stemming ultimately from the utility’s choice of fuel adjustment clause. The Commission stated:

“[T]he self-inflicted nature [Edison’s] alleged undercollection [is] readily apparent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
611 F.2d 8, 1979 U.S. App. LEXIS 9423, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boston-edison-company-v-federal-energy-regulatory-commission-towns-of-ca1-1979.