This text of 947 N.E.2d 544 (Boston Edison Co. v. Massachusetts Water Resources Authority) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boston Edison Co. v. Massachusetts Water Resources Authority, 947 N.E.2d 544, 459 Mass. 724, 2011 Mass. LEXIS 346 (Mass. 2011).

Opinion

Gants, J.

Boston Edison Company (Boston Edison) brought this action under G. L. c. 79, § 12, to recover damages caused by four eminent domain takings by the Massachusetts Water Resources Authority (MWRA) on property known as the Fore River Station (site) in the town of Weymouth and city of Quincy. After a lengthy trial, the jury answered special questions and awarded damages of $8,100,000 for takings on the north parcel of the property (which lies north of Route 3A) and $2,900,000 for takings on the south parcel (which lies south of Route 3A). The parties cross-appealed from the judgment, and we granted the MWRA’s application for direct appellate review.

Background. The site on the banks of the Fore River comprises 78.1 acres of land divided by Route 3A, all zoned for industrial use; there are 20.2 acres on the north parcel and 57.9 acres on the south parcel. In the 1920s, Boston Edison built a coal-fired electrical plant on the south parcel, which it converted to oil in the 1960s; it built oil storage facilities on the north parcel. Although Boston Edison decommissioned this plant in the late 1970s, it continued to run two turbines intermittently to cope with peak demand and maintained on the south parcel a “switch house” that transmitted power from the electrical grid into Quincy.

Under the deregulation of the energy industry accomplished by the electric utility industry restructuring act, St. 1997, c. 164, which became effective on November 25, 1997 (see Shea v. Boston Edison Co., 431 Mass. 251, 252-258 [2000] [discussion of act]), Boston Edison could own either electrical generating facilities or transmission facilities, but not both. Boston Edison chose to retain its transmission facilities and sell its generating facilities. On December 10, 1997, as part of a broader agree[726]*726ment to sell its generation facilities, Boston Edison entered into a purchase and sale agreement with Sithe Edgar LLC (Sithe) to sell the site, retaining a large easement on the south parcel that included the switch house.2

Schedule 3.10 of the agreement acknowledged that discussions had taken place with the MWRA over several years regarding the potential taking by eminent domain of a portion of the site for construction of a sewage pumping station and tunnel as part of the Braintree-Weymouth Sewer Relief Facilities Project (sewage project). The agreement noted that no formal taking had yet occurred, and no schedule for completion of the discussions had been established.

In April, 1998, prior to the closing, representatives of MWRA, Boston Edison, and Sithe met to discuss the anticipated takings for the MWRA’s sewage project and Sithe’s plans to construct a power plant on the site. All agreed that the site could accommodate both projects but that the sequencing and staging of construction, as well as the location of the structures, needed to be resolved. After a Sithe representative declared that Sithe could not place the new power plant on the south parcel because of the size and orientation of the site, a Boston Edison representative suggested that Boston Edison could move its switch house to a different location to enable Sithe to build on the south parcel. Under the closing agreement between Boston Edison and Sithe entered into on May 15, 1998, and a supplementary agreement entered into on October 29, 1999, Boston Edison agreed to transfer to Sithe much of the easement it had retained in the south parcel, including the part of the easement that contained the switch house, and to relocate the switch house to the smaller easement it retained on the south parcel. Sithe agreed to assign to Boston Edison its rights against the MWRA regarding the eminent domain takings on the site.3

MWRA’s first order of taking, recorded on August 13, 1999, [727]*727included an area of land in fee for a pumping station, a permanent drainage easement, two permanent subsurface and access easements, and three temporary easements to provide access to workers, machinery, and materials, and storage for construction materials and equipment, most of which were on the north parcel. A second and third order of taking recorded on February 20, 2001, and April 10, 2003, included permanent and temporary easements connected to the sewage project on the south parcel. Because of construction delays, the MWRA recorded a fourth order of taking on June 24, 2003, to extend by nine months the temporary access and storage easements on the north parcel specified in the first order of taking, which were originally set to expire on June 30, 2003.

At trial, Boston Edison contended that the highest and best use of the north parcel was as a mixed-use residential development that would include residential condominium units, a commuter boat terminal, a public marina, and a public waterfront park. Based on that highest and best use, its experts opined that the fair market value of the property interests taken on the north parcel was $11,400,000. The MWRA argued that it was not reasonably probable that the north parcel could be used for such a residential development because it was zoned for industrial use at the time of the first taking on August 13, 1999, and there was no reasonable probability that it would be rezoned for residential development.

In addition, the MWRA argued that, apart from the zoning restriction, the north parcel consisted of filled tidelands within a designated port area (DPA), as defined in 301 Code Mass. Regs. § 25.02 (1994), and a developer could not obtain a license from the Department of Environmental Protection (DEP) for the proposed residential project because it was within a DPA. The MWRA moved in limine before trial to bar all evidence and expert testimony regarding the proposed residential development, but the motion was denied. In answer to special questions, the jury found that it was “reasonably probable that the [728]*728[n]orth [p]arcel could be rezoned for residential development notwithstanding that the property was zoned for industrial use as of August 13, 1999,” and that it was “reasonably probable that the [n]orth [p]arcel could be developed for residential use notwithstanding that the property consisted of filled tidelands within a [DEA] as of August 13, 1999.” The jury awarded Boston Edison $8,100,000 as damages arising from the takings on the north parcel.

As to the south parcel, Boston Edison argued that the takings and the sewage project caused the relocation of the switch house. Boston Edison maintained that it agreed to transfer to Sithe a substantial share of its retained easement and relocate its switch house because, based on the MWRA’s plans for the taking in April, 1998, Sithe would otherwise have been unable to build its power plant on the site. This would have jeopardized not only the sale of the site but the sale of Boston Edison’s other generating facilities to Sithe. Boston Edison, therefore, contended that the costs of relocating the switch house should be included as damages arising from the takings, and claimed damages in the amount of $11,820,000. Of this sum, $1,800,562 were direct damages arising from the takings on the south parcel, and $10,019,438 were damages arising from the relocation. The MWRA argued that the takings did not cause the relocation of the switch house, because its initial plans for the takings on the south parcel changed before the actual takings, in part to accommodate Sithe’s construction of the power plant and Boston Edison’s relocation of its switching facility.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stern Taylor v. Sawyer
D. Massachusetts, 2022
Barkan v. Zoning Bd. of Appeals of Truro
126 N.E.3d 1008 (Massachusetts Appeals Court, 2019)
Property Acquisition Group, LLC v. Ivester
122 N.E.3d 10 (Massachusetts Appeals Court, 2019)
Clemmey v. Commonwealth
119 N.E.3d 354 (Massachusetts Appeals Court, 2018)
Dubuque v. Cumberland Farms, Inc.
101 N.E.3d 317 (Massachusetts Appeals Court, 2018)
Cadle Co. v. Lyons
103 N.E.3d 766 (Massachusetts Appeals Court, 2018)
Deutsche Bank National Trust Co. v. Shelzi
33 Mass. L. Rptr. 581 (Massachusetts Superior Court, 2016)
Three Registered Voters v. Board of Selectmen of Lynnfield
55 N.E.3d 1018 (Massachusetts Appeals Court, 2016)
Fyffe v. Massachusetts Bay Transportation Authority
17 N.E.3d 453 (Massachusetts Appeals Court, 2014)
Athanasiou v. Town of Westhampton
30 F. Supp. 3d 84 (D. Massachusetts, 2014)
Watts v. Commonwealth
8 N.E.3d 717 (Massachusetts Supreme Judicial Court, 2014)
Smith v. Massachusetts Bay Transportation Authority
968 N.E.2d 884 (Massachusetts Supreme Judicial Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
947 N.E.2d 544, 459 Mass. 724, 2011 Mass. LEXIS 346, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boston-edison-co-v-massachusetts-water-resources-authority-mass-2011.