Borough of Lansdowne v. Public Service Commission

74 Pa. Super. 203, 1920 Pa. Super. LEXIS 122
CourtSuperior Court of Pennsylvania
DecidedFebruary 28, 1920
DocketAppeals, Nos. 30, 31, 32, 33, and 34
StatusPublished
Cited by11 cases

This text of 74 Pa. Super. 203 (Borough of Lansdowne v. Public Service Commission) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Borough of Lansdowne v. Public Service Commission, 74 Pa. Super. 203, 1920 Pa. Super. LEXIS 122 (Pa. Ct. App. 1920).

Opinion

Opinion by

Keller, J.,

Complaints were filed with the Public Service Commission by various boroughs and private consumers alleging that the rates charged by the Springfield Consolidated Water Company were unjust, unreasonable, excessive and discriminatory. The complaints were consolidated and hearings had which received widespread publicity. An exhaustive investigation was made of the company’s plant and its value for rate making purposes, the cost of operation, the revenue which the company was entitled to receive and its apportionment between municipal and private consumers) or between fire protection and domestic consumption, and all the other matters proper to be considered by the commission for the purpose of fixing an equitable schedule of rates, in the course of which an immense amount of testimony and engineering data was received. A report was filed which one needs only to read to be convinced of the care and thoroughness which the commission gave the whole subject. In this report a schedule of rates was fixed which somewhat reduced the revenues of the company, lowered the rates for domestic consumers very considerably and largely increased the amounts to be paid for fire protection service by various boroughs and townships, which had theretofore paid only $15 per annum for each fire hydrant installed, in accordance with contracts entered into between the parties prior to the passage of the Public Service Company Law. Thereupon a number of the boroughs and townships affected by said order filed complaints alleging that the rates for public fire protection made operative by the order of the commission were excessive, unfair, unreasonable and prohibitive, and illegal because impairing the obligation of the several contracts made between them and the company. After hearing the parties and such proofs as were submitted, the original order was upheld and the complaints were dismissed. From this last order separate appeals were taken by the above-named complain[208]*208ants, but as the same questions are raised in all of them we will consider them together and dispose of them in one opinion.

In its report on the original complaints, the commission fixed the fair value of the company’s property for rate-making purposes at $7,203,320, ordered additional improvements estimated to cost $1,048,100, and found that the company was entitled to a gross annual revenue of $899,732, of which it apportioned $719,602 to be charged against domestic and industrial service and $180,130, to be paid by the various boroughs and townships served by the company, for fire protection. In securing this sum, $180,130, for fire protection service, it was necessary to distribute it as equitably as possible among the various municipalities affected, and the plan adopted by the commission was to make a small charge of $7 per annum for every fire hydrant in use, deduct the amount received from this source, plus the revenue received from private fire protection, from $180,130, and divide the remainder by the number of miles of mains four inches and over in diameter which were furnishing fire protection service. The result, $355, represented the amount per mile of assessable pipe, (as before described), within its limits to be charged annually against every borough or township receiving fire protection, and, together with $7 per fire hydrant, fixed the sum to be paid for fire service and fire protection by the several municipal divisions. It is this charge which is complained of in these proceedings.

The stipulation entered into between the several appellants and the intervening appellee, has materially narrowed the scope of our inquiry. Under its provisions no question is raised “concerning the valuation and rate of return, gross and net revenues, and operating expenses of the Springfield Consolidated Water Company fixed in the original proceeding.” For the purposes of these appeals, it is thus admitted that the value of the company’s property was rightly fixed at $7,203,320, and [209]*209that the company was entitled to receive a gross annual revenue of $899,732. The appellants’ objections are confined to the commission’s action in allotting $180,130 of these revenues to fire protection service and its apportionment of this amount among the several boroughs and townships receiving fire protection service.

In reviewing the order of the commission it is not our province to substitute our judgment as to the rates to be charged for that of the commission or usurp administrative functions committed to it. Power to make the order and not the mere expediency or wisdom of having made it, is the question: Ben Avon Boro. v. Ohio Valley Water Co., 260 Pa. 289, p. 297. The order of the commission in the premises is final unless (1) beyond the power which it could constitutionally exercise; or (2) beyond its statutory power; or (3) based upon a mistake of law; or (4) the result of the commission’s having arbitrarily fixed the rates contrary to evidence, or without evidence to support it, or in a grossly unreasonable manner. With this chart to guide us we will consider the reasons advanced by the several appellants why the order of the commission is illegal and invalid.

(1) It was not necessary that the appellant boroughs should be made parties to or have special notice of the proceedings under the original complaints. The hearings were held publicly, were widely advertised, were largely attended and were a matter of great public interest. The appellants must have had knowledge of the proceeding — “for this thing was not done in a corner”'— and could have intervened and been heard had they so desired. But apart from that, it is not feasible to require that notice of hearings on schedules of rates should be given to every person who may be affected thereby. Otherwise no complaint by a private consumer as to rates could be considered without making every other consumer a party to the proceeding. The rights of the appellants were fully protected by the provisions of article VI, section 14, of the act, authorizing a rehearing, [210]*210or by permitting them to file complaints as to the new rates ordered by the commission and to show if possible in the proceedings held in pursuance thereof, the unfairness, injustice, and unreasonableness of the schedule complained of. That they are here as appellants from the order of the commission following such a complaint is the best proof possible that they have not been denied a hearing.

(2) Charges for public fire protection service cannot fairly be computed on the same basis as for domestic or industrial consumption. They are not to be measured by the quantity of water consumed for that may be negligible in amount. Nor should they be reckoned solely by the number of fire hydrants in use. The hydrant is merely the opening through which to deliver the water supplied by the pumping plant and pipe lines, and the number of such hydrants does not fairly determine the cost of the service. The old method of paying the company what the municipality was willing to give has no basis whatever to rest upon. The consensus of modern engineering and accounting opinion is that the amount to be paid for such service should be based on the cost of the plant devoted to public fire protection, in connection with its fair share of the cost of maintenance, operation and depreciation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Erie v. Pennsylvania Electric Co.
383 A.2d 575 (Commonwealth Court of Pennsylvania, 1978)
Crown Products Co. v. Pennsylvania Public Utility Commission
31 A.2d 913 (Superior Court of Pennsylvania, 1943)
Porter v. Board of Plumbing Supervision of Department of Health
43 Pa. D. & C. 616 (Philadelphia County Court of Common Pleas, 1942)
Logan City v. Public Utilities Commission
271 P. 961 (Utah Supreme Court, 1928)
In re Tuberculosis Hospital
7 Pa. D. & C. 725 (Northampton County Court of Common Pleas, 1926)
Dickson v. Drexel
132 A. 284 (Supreme Court of Pennsylvania, 1926)
City of Philadelphia v. Public Service Commission
84 Pa. Super. 135 (Superior Court of Pennsylvania, 1924)
Borough of Lewistown v. Public Service Commission
80 Pa. Super. 528 (Superior Court of Pennsylvania, 1923)
Borough of Carlisle v. Public Service Commission
81 Pa. Super. 475 (Superior Court of Pennsylvania, 1923)
Pottsville Water Co. v. Public Service Commission
78 Pa. Super. 56 (Superior Court of Pennsylvania, 1921)
Wayne Sewerage Co. v. Fronefield
76 Pa. Super. 491 (Superior Court of Pennsylvania, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
74 Pa. Super. 203, 1920 Pa. Super. LEXIS 122, Counsel Stack Legal Research, https://law.counselstack.com/opinion/borough-of-lansdowne-v-public-service-commission-pasuperct-1920.