BorgWarner Thermal Sys., Inc. v. Carlisle Brake & Friction, Inc.

CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 22, 2021
Docket20-1344
StatusUnpublished

This text of BorgWarner Thermal Sys., Inc. v. Carlisle Brake & Friction, Inc. (BorgWarner Thermal Sys., Inc. v. Carlisle Brake & Friction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BorgWarner Thermal Sys., Inc. v. Carlisle Brake & Friction, Inc., (6th Cir. 2021).

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 21a0098n.06

No. 20-1344

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT FILED Feb 22, 2021 BORGWARNER THERMAL SYSTEMS, INC., ) DEBORAH S. HUNT, Clerk ) Plaintiff-Appellee, ) ) ON APPEAL FROM THE v. ) UNITED STATES DISTRICT ) COURT FOR THE EASTERN CARLISLE BRAKE & FRICTION, INC., ) DISTRICT OF MICHIGAN ) Defendant-Appellant. ) )

BEFORE: COOK, GRIFFIN, and LARSEN, Circuit Judges.

GRIFFIN, Circuit Judge.

Plaintiff BorgWarner Thermal Systems contends defendant Carlisle Brake & Friction

breached its contractual obligations when it failed to comply with a transition-of-supply provision

contained in BorgWarner’s Terms and Conditions. The district court agreed, entered summary

judgment in BorgWarner’s favor, and awarded $585,127.94 in damages. We affirm.

I.

BorgWarner and Carlisle are parts suppliers. In 2015, they entered into an agreement for

Carlisle to supply friction liners to BorgWarner’s Cadillac, Michigan plant at certain prices. These

terms were printed on a standard BorgWarner “Purchase Order.” The parties dispute what

obligations Carlisle had to BorgWarner after the contract expired in April 2018. BorgWarner

claims Carlisle was required to continue filling orders at the agreed prices for a “reasonable” time

until BorgWarner could secure an alternate supplier; Carlisle responds that it had no such No. 20-1344, BorgWarner Thermal Sys., Inc. v. Carlisle Brake & Friction, Inc.

obligation and could charge a different price. Resolving this dispute centers on which, if any, of

the parties’ standard terms and conditions are part of the contract.

During negotiations, the parties wanted their own respective terms and conditions to apply.

This was a non-starter for BorgWarner—“it repeatedly and in writing expressed to Carlisle [that

this was] non-negotiable.” Eventually, however, Carlisle “decided to just not push . . . anymore,

and . . . sign[ed] the [Purchase Order] as it was written.” Carlisle’s negotiator testified that Carlisle

still “disagree[d]” with the application of BorgWarner’s Terms and Conditions, and that if any

issue arose, “the lawyers could work [it] out later.” But Carlisle also admitted in district court both

that the Purchase Order “became the contract” when its Vice President of Finance approved it

internally on July 28, 2015, and that it “also indicated its acceptance by immediately shipping

parts.”

The Purchase Order provided it was “governed by and subject to BorgWarner Purchase

Order Terms and Conditions” and that “[a]ny other different or additional terms proposed by

Supplier are expressly rejected, unless separately agreed to in writing by BorgWarner.” Section

12 of those Terms and Conditions, in turn, mandates that “[i]n connection with the expiration,

cancellation or termination of the Purchase Order,” the seller of goods, here Carlisle, must

“cooperate in the transition of supply.” In BorgWarner’s view, this obligated Carlisle to “continue

production and delivery of all goods and services . . . at the prices and in compliance with the terms

of the Purchase Order . . . during the entire period reasonably needed by [BorgWarner] to complete

the transition to the alternate supplier(s).”

Carlisle acknowledges this, but claims that when it shipped the friction liners, it included

its own terms and conditions on invoices. And Carlisle’s Terms and Conditions do not contain

any post-contract, transition-of-supply language. Rather, they just provide that “[u]nless otherwise

-2- No. 20-1344, BorgWarner Thermal Sys., Inc. v. Carlisle Brake & Friction, Inc.

set forth in the Sale Documents, the price for the products or services shall be Seller’s price in

effect on the date of shipment.”

The parties operated under these terms for the duration of the contract without issue, with

Carlisle regularly shipping its friction liners upon receipt of BorgWarner’s daily orders. And

Carlisle continued to process orders after the contract’s April 30, 2018 termination date. But that

changed in the summer of 2018, when Carlisle determined that it had economic and environmental

concerns with continuing to fill BorgWarner’s orders. The parties met on July 30, 2018, at which

time Carlisle told BorgWarner that it was “in the best interest of both parties to discontinue the

manufacturing of these parts.” Carlisle offered to continue providing the friction liners at a

substantially increased price for a six-month period. BorgWarner eventually, and reluctantly,

agreed, but reserved its right to recoup its losses. And in the meantime, it worked to successfully

secure a new supplier in about nine months. Carlisle stopped supplying its friction liners to

BorgWarner in May 2019.

This breach-of-contract action originally began as one for injunctive relief, with

BorgWarner requesting in September 2018 that the district court order Carlisle to continue to

perform its obligations under the 2015 agreement. BorgWarner subsequently withdrew that

request, and the district court ultimately resolved BorgWarner’s claims (and Carlisle’s

counterclaims) on the merits at summary judgment. It found BorgWarner was entitled to summary

judgment in its favor on its breach of contract and declaratory judgment counts, concluding that

“the parties’ contract required Carlisle to continue to supply the Friction Liners to [BorgWarner],

under the prices set forth in the Purchase Order, until [BorgWarner] could reasonably secure a new

supplier, and that [BorgWarner] is entitled to damages in the amount of $585,127.94.” And it

-3- No. 20-1344, BorgWarner Thermal Sys., Inc. v. Carlisle Brake & Friction, Inc.

summarily entered summary judgment in BorgWarner’s favor on Carlisle’s contract-based

counterclaims. Carlisle timely appeals.

II.

This is an appeal from the district court’s resolution of the parties’ cross-motions for

summary judgment. Our standard of review “does not differ from the standard applied when a

motion is filed by only one party to the litigation.” Ferro Corp. v. Cookson Grp., 585 F.3d 946,

949 (6th Cir. 2009). Summary judgment is appropriate “if the movant shows that there is no

genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”

Fed. R. Civ. P. 56(a). “The moving party bears the burden of showing that no genuine issues of

material fact exist.” Rafferty v. Trumbull County, 915 F.3d 1087, 1093 (6th Cir. 2019). All

reasonable inferences will be drawn in favor of the non-moving party. Mutchler v. Dunlap Mem’l

Hosp., 485 F.3d 854, 857 (6th Cir. 2007). “[A]t the summary judgment stage the judge’s function

is not himself to weigh the evidence and determine the truth of the matter but to determine whether

there is a genuine issue for trial.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249 (1986).

III.

Carlisle contends the district court wrongly entered summary judgment in BorgWarner’s

favor for three reasons: (1) BorgWarner’s Terms and Conditions are not part of the contract

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Ferro Corp. v. Cookson Group, PLC
585 F.3d 946 (Sixth Circuit, 2009)
Power Press Sales Co. v. MSI Battle Creek Stamping
604 N.W.2d 772 (Michigan Court of Appeals, 2000)
American Parts Co., Inc. v. American Arbitration Ass'n
154 N.W.2d 5 (Michigan Court of Appeals, 1967)
Challenge MacHinery Co. v. Mattison MacHine Works
359 N.W.2d 232 (Michigan Court of Appeals, 1984)
Thomas M. Cooley Law School v. Kurzon Strauss, LLP
759 F.3d 522 (Sixth Circuit, 2014)
Michele Rafferty v. Trumbull Cty., Ohio
915 F.3d 1087 (Sixth Circuit, 2019)
Beverly Swanigan v. FCA
938 F.3d 779 (Sixth Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
BorgWarner Thermal Sys., Inc. v. Carlisle Brake & Friction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/borgwarner-thermal-sys-inc-v-carlisle-brake-friction-inc-ca6-2021.