Border Gas Co. v. Windrow

3 F.2d 974, 1925 U.S. App. LEXIS 3845
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 6, 1925
DocketNo. 4376
StatusPublished
Cited by4 cases

This text of 3 F.2d 974 (Border Gas Co. v. Windrow) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Border Gas Co. v. Windrow, 3 F.2d 974, 1925 U.S. App. LEXIS 3845 (5th Cir. 1925).

Opinion

DAWKINS, District Judge.

This case was tried below before the judge on a signed stipulation waiving the jury, and at the request of plaintiff in error (defendant below) the court made a special finding of facts as follows:

'“(1) That the plaintiffs, D. Z. and N. C. Windrow, at all of the times involved in this suit, were, and still are, partners doing business as druggists on Salinas avenue in the city of Laredo, Tex.; that the said plaintiffs were tenants of the building they occupied; that all of the times involved in this suit, the defendant, Border Gas Company, was, and still is, a corporation, engaged in the business of distributing and selling to consumers in the city of Laredo natural gas for lighting and heating purposes, and that the said Border Gas Com- . pany had a gas main on Salinas avenue and furnished gas to the plaintiffs in said drug store.

“(2) That for a period of time before and after the explosion involved in this case, the city'of Laredo was engaged in a very extensive program of the construction of permanent street pavements and curb-ings and said work of constructing the street pavements, the city required all public utilities, including this defendant, to renew their mains in the streets and to put down new service pipes, running from the mains to a point inside of where the new curb lines would be, before the pavement was laid, in order that the pavements would not have to be dug up after they were laid; that the city planned to and did finally widen Salinas avenue, move back the curb line, and pave the said avenue; that this defendant in order to keep ahead of the city in said paving program, had to do a very large amount of work in the way of installing new gas mains and new service pipes; as a part of this work, and in obedience to the ordinance that had been passed by the city, this defendant in the month of February, 1923, installed a new gas main in the said Salinas avenue in front of the drug store of the plaintiffs; the city had furnished .to this defendant a line, showing that the new curb line of the city street would be 18 inches or 2 feet back nearer to the property line than the old curb line had been; that before the new main and new service pipe was run into the plaintiff’s drug store, there was an old service pipe running in from the old main, which had on it a valve or cut-off, which was within a few inches inside of the old curb line, and above this valve or cut-off there was in the cement sidewalk what is known as a curb box, the top of which could be raised and through which a key could be put down and the said old valve in [975]*975the old service pipe could be turned, so as to cut off the gas; that when the defendant put down the said new gas main it removed the said old service pipe and the said valve in the said old service pipe and ent off the lower part of the said old curb box, but left in the old sidewalk, which was to be torn up and destroyed when the street was widened, the top part of the said old eurb box, and the defendant then installed from its main a new service pipe to run into and connect with tbe said Windrow Bros. Drug Store, and it installed a new valve or cutoff on said service pipe at a point where it would be inside of the new curb line which had been given to this defendant by the city, which new valve or cut-off was then about 18 inches farther in towards the property line than the old eurb box was; the defendant had to put in several hundred such new service pipes and valves, and in plenty of time the defendant ordered a sufficient number of new curb boxes, which they proposed to install at a point where they would be over the now valves or cutoffs in the service pipes, but the factory did not ship all of the eurb boxes promptly, and in order to keep ahead of the- paving program, and in order to get their new pipes under the ground before the city paved the street and widened the eurb, this defendant company had to put down some of its mains and some of its new service pipes and some of its new valves, and had to do so in the case of the Windrow Bros. Drug Store, before they received the eurb boxes and before they could install the curb boxes; and that after sueh new service pipe and new valve was installed, the gas pipes were again connected up with the meter and fixtures inside of Windrow Bros. Drug Store, and they continued to use the gas up to about July 16, 1923.

“(3) That before any improvement work was done on the said Salinas avenue, the sidewalk in front of the Windrow Drug ■Store was very narrow, being only about 2 feet wide and the front wall of the drug store stuck out into the street further than the building immediately adjacent to the said drug store building, and the plaintiffs •and the owners of the said building desired ■and planned to tear down the front wall of the said building and to make a new wall back on the line with the other building, so that there would be a sidewalk between the new eurb line and the now front wall of the said building of some 6 or 7 feet and contractors were engaged to tear down the old front part of the said building to remove the old wall floor and roof thereof to saw off the floor and building at a point where the new wall was to be installed and to build a new front wall on the said building, and on or abont July 16th tbe said contractor started in with said construction work.

“(4) On or about July 16, 1923, the defendant company was requested by the said contractor and by the plaintiffs to remove the gas meter on said premises and to cut off the gas and to remove the pipe that was in the way of the work, and advised that the owner of the building wanted the gas cut off because the owner intended to move back the front wall of said building and change the location and arrangement of the gas pipes. The defendant company sent a man to the said drug store to do said work on or about July 16th, and he found that the old wall of the building was still up and the old floor of the building between the old wall and the new wall was still in place, and he tried to turn off the gas with his wrench by putting his wrench down through the said old eurb box above mentioned, and when he found no valve under said old curb box he realized that the new service pipe had been installed, and that the new valve was further in towards the property line and could not be reached through the said old eurb box; tbe new valve being under and near tbe middle of the old sidewalk. The said representative of the defendant found piled up in the roadway, next to the curb, a lot of brick, lumber, and building material, and the old front wall and old floor of the building were still in place, and this made it very difficult for him to reach the said new valve or cut-off, and for this reason the said representative of the defendant did not cut off the gas by turning the said valve in the service pipe under the sidewalk, but the defendant company disconnected the meter, and after taking out a piece of pipe, at a place near the old floor line, the defendant company put in the end of the pipe a metal plug with threads, which is regularly made for such purpose and is of the best and most approved pattern for plugging up a pipe to prevent gas from escaping therefrom, and the said pipe was tested, and it did not leak, and no gas escaped or could eseape from it. The defendant thus shut off and cut off the gas at a point a few inches inside of the old front wall and at a point several feet on the outside of where the new front wall would be placed, and several feet outside of the place where a temporary [976]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

(PC) Williams v. Thompson
E.D. California, 2021
United States v. Morow
182 F.2d 986 (D.C. Circuit, 1950)
United States v. New York, C. & St. L. R.
32 F.2d 887 (Sixth Circuit, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
3 F.2d 974, 1925 U.S. App. LEXIS 3845, Counsel Stack Legal Research, https://law.counselstack.com/opinion/border-gas-co-v-windrow-ca5-1925.