Bopst v. District of Columbia

90 F. Supp. 286, 1948 U.S. Dist. LEXIS 1997
CourtDistrict Court, District of Columbia
DecidedDecember 23, 1948
DocketCiv. A. No. 10329
StatusPublished
Cited by2 cases

This text of 90 F. Supp. 286 (Bopst v. District of Columbia) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bopst v. District of Columbia, 90 F. Supp. 286, 1948 U.S. Dist. LEXIS 1997 (D.D.C. 1948).

Opinion

MORRIS, District Judge.

The complaint in this action was filed February 25, 1941, seeking recovery from the District of Columbia of three items: One in the amount of $3,510, claimed as damages for delays occasioned to the plaintiff while performing work as a contractor under a contract dated August 20, 1935, between the plaintiff as contractor and the District of Columbia, for which corporation the work was being performed, and for the performance of which contract the Maryland Casualty Company was surety upon the performance bond; one in the amount of $6,000, which amount was deducted as liquidated damages in the final payment made on October 1, 1937, by the District of Columbia with respect to said contract, on the ground that the plaintiff was not responsible for any delays; and one in the amount of $28,-450, also deducted from the final payment, representing the contract price for pumps which the District of Columbia rejected as not meeting the requirements of the con[287]*287tract, on the ground that said deduction was improper, as the pumps were in all respects in conformity with the contract and the failure to meet required tests was due to improper testing instruments and construction work for which the plaintiff was not responsible. The District of Columbia filed answer on April 7, 1941, with copy of contract, specifications and other exhibits attached, in which it denied any delays on its part in the work of the plaintiff, asserted the right to make the deduction for liquidated damages, and denied any responsibility for the failure of the pumps to meet contract specifications, asserting that all conditions of testing and construction were in accordance with the contract and specifications. Subsequently, on May 6, 1941, the defendant filed an amended answer and counterclaim, the Maryland Casualty Company having been made a counterclaim defendant, in which the District of Columbia claimed the sum of $37,201, representing the difference between the contract price of the four pumps rejected and the sum of $65,651 which was the cost to the District of Columbia for pumps and work furnished by Worthington Pipe and Machinery Corporation, claimed to have been made necessary by the failure of the plaintiff to furnish the four pumps meeting contract and specifications requirements. Answer to said counterclaim was filed by the plaintiff, and a motion to dismiss said counterclaim was filed by the Maryland Casualty Company. This motion was denied, and answer to the counterclaim was filed by the Maryland Casualty Company. Motions for summary judgment on the counterclaim, first by the Maryland Casualty Company and later by the District of Columbia, were denied. Thereafter, upon order of the Court, records were inspected and depositions were taken. Upon failure of the plaintiff to comply with certain orders of the Court respecting the taking of his deposition, his complaint was dismissed with prejudice. Subsequent thereto the counterclaim defendants, upon the basis of certain records of the District of Columbia revealed by the inspection of records and depositions, moved for summary judgment in their favor and against the District of Columbia on the counterclaim. Hearings were had and memoranda submitted by the parties.

The contract involved related to work and equipment of the value of $128,695, in addition to the contract value of the rejected pumps, all in connection with the construction of a sewage disposal plant. It is quite apparent from the record that, after the installation of the four pumps around which the present controversy revolves, numerous tests were made, the results of which were below the efficiency and capacity requirements of the contract. The correspondence in the record reveals numerous attempts and extensions of time to bring about the desired result. An extension of time, prior to December 31, 1936, was granted in an order by the Commissioners of the District of Columbia for 234 calendar days, “cause of delay beyond control and without fault or negligence of the contractor.” On April 30, 1937, the plaintiff was notified that four pumps were rejected, and the contractor directed to remove and reclaim said pumps at his own expense, and repay the District of Columbia in full any sums which may have been paid under the terms of said contract for the equipment so rejected, all under the provisions of section V of the specifications of the contract. On September 1, 1937, the District of Columbia, through its Assistant Engineer Commissioner, addressed a communication to the Maryland Casualty Company, advising that the District of Columbia proposed to make final payment on the work of the plaintiff under the contract here involved. This communication stated that the four main sewage pumps were formally rejected by the District under date of April 30, 1937, and no credit was being allowed the contractor on account of these items. The communication further stated that the final payment to the contractor would amount to the net of $13,945, after the deduction of $6,000 on account of liquidated damages resulting from 120 days’ delay in the completion of the contract. The communication requested comment respecting the release of this final payment. Under date of September 17, 1937, a further communication to the Maryland Casualty Company requested comment [288]*288which had not been received, and, on September 18, 1937, the Maryland Casualty Company, replying to the two communications mentioned, requested that the payment be made — it being understood that the payment was to be accepted by the plaintiff under protest for reasons outlined in correspondence. On October 1, 1937, as previously stated, final payment was made by the District of Columbia to the plaintiff, accompanied by a statement showing the contract price of $127,700, to which was added items of change amounting to $995, a total of $128,695 (omitting the contract value of the four rejected pumps, $28,450), from which was deducted previous payments of $108,750 and liquidated damages of $6,000, leaving a balance of $13,945. This payment was accepted by the plaintiff under protest as to the omission of the value of the rejected pumps and the deduction of $6,000 liquidated damages.

It further appears from the record in this case that, subsequent to the rejection of the plaintiff’s pumps and prior to the final payment, the District of Columbia solicited and received bids for the construction of pumps and the performance of certain miscellaneous construction which resulted in a contract between the District of Columbia and the. Worthington Pump and Machinery Corporation dated September 10, 1937, in the contract amount of $65,651, which included not only the cost of furnishing the pumps, but the miscellaneous construction item in the contract amount of $10,675. It is not disputed that the pumps furnished by the Worthington Corporation were of somewhat different guaranteed efficiency and capacity than those specified in the plaintiff’s contract, but it is contended that this was due to conditions effected by the installation of certain motor equipment by the plaintiff, and to which the Worthington contract had to be accommodated. Somewhat the same contention is made with respect to the necessity for the miscellaneous construction work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McGee v. Marbury
83 A.2d 157 (District of Columbia Court of Appeals, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
90 F. Supp. 286, 1948 U.S. Dist. LEXIS 1997, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bopst-v-district-of-columbia-dcd-1948.