Boots v. Seinberg

58 N.W. 657, 100 Mich. 134, 1894 Mich. LEXIS 772
CourtMichigan Supreme Court
DecidedApril 17, 1894
StatusPublished
Cited by12 cases

This text of 58 N.W. 657 (Boots v. Seinberg) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boots v. Seinberg, 58 N.W. 657, 100 Mich. 134, 1894 Mich. LEXIS 772 (Mich. 1894).

Opinion

Hooker, J.

Complainant, having performed labor upon defendant’s building,' filed the bill in this cause to enforce a mechanic’s lien for a balance which he claims to be due upon the contract, including some extras not embraced in the specifications, which were made a part of the contract. This contract was made September 14, 1891. According to the complainant’s testimony, the work was commenced September 17, 1891, and completed on December 29, following. The statutory notice was filed on February 11, 1892, and was in strict conformity to the requirements of the statute. Laws of 1891, p. 231. The defense is interposed that nothing is, or at the time of such notice was,, due, it being claimed that, by the terms of the contract, [136]*136the amount would not become payable until the building was completed to the satisfaction of the defendant, which has not been done. It is further asserted that, by the terms of the contract, the price for extras was to be settled by arbitrators, unless agreed upon; that it never has been determined in either way, and hence the same is not due, nor is it the proper subject of a lien. It is also alleged that, owing to careless or unskillful work, the building is not as valuable as it would otherwise have been, by reason of which the defendant has suffered damage, exceeding the amount of complainant's claim. Defendant also claims that he has furnished goods to the workmen of complainant, and has furnished materials for him in and about the erection of the building, which should be applied in payment. The further claim is made that the complainant has filed an excessive lien, and that It is therefore void.

The brief of defendant's counsel states the matters in •dispute relating to the non-performance of the contract •as follows, viz.:

1. Failure to properly put in concrete footings, in that some were not as deep as required, and that the concrete was put in the water, instead of being put in dry.
2. Failure to finish and clean the front elevation.
3. Failure to line, clean, and “rub smooth" the flues in the building.
4. Failure to point up under the window sills and the stonework of the foundation.

The contract provides that — •

“ The contractor shall and will well and efficiently perform and finish, under the direction and to the satisfaction of Julius Steinberg, or his superintendent, if he shall .appoint one (acting as agent of said owner), all the work hereinafter mentioned to be performed," etc.

It further provides that—

“The owner, Julius Steinberg, shall have power to act [137]*137.as superintendent of said work, or to appoint some one to act in such capacity.”

The payments are provided for as the work progresses, reserving 10 per cent, from each amount mentioned, and it is further provided that—

“Within 10 days from the completion of said work to the satisfaction of Julius Steinberg, the entire balance due the contractor shall be paid.”

This contract clearly required that the work should be done to the satisfaction of the owner or his superintendent, as it progressed, and that it should not be fully paid for until completed to the satisfaction of the owner., Some of the matters complained of were, according to our view of the evidence, approved by the owner and the superintendent, as the building went. up. We think that was true of the concrete footings, which were not constructed according to the specifications, but which were discussed, and the course taken acquiesced in. There might be some force in the contention that the same is true of the cqnstruction of the flues, as to lining and rubbing, were there evidence that it was knowingly permitted, or if the facts were such as to make it plain that the owner or superintendent must have acquiesced. To go further, and say that the fact of such construction without interference is conclusive of the question of approval, would be, in effect, to say that whatever the contractor could succeed in doing must be taken as approved, — a proposition that would put such a premium upon bad faith as to be untenable. While the contractor may rely upon what was actually approved under the contract, he is supposed to understand the specifications and how the work should be performed as well as the superintendent, and as well as, if not better than, the owner; and he cannot be permitted to invoke the doctrine of estoppel where some of its elements are lacking, making it “a sword, and not a shield.” But, whatever may be said [138]*138about tbe construction of tbe flues, it cannot be' claimed that any one approved of their stoppage. The complainant claims he succeeded in cleaning them out, — i. e., knocking the obstructions out, — and this is a controverted fact. We are satisfied from the evidence, including that of the architect, that such flues were not effectually cleaned out, and that they were not constructed as the specifications required, and that defendant never was satisfied with them.

The stonework was injured by the cleaning, acid being used, which, m connection with the iron in the stone, gave them a yellow appearance, the effect of iron rust. It is claimed by the complainant that this was because too much acid was used, and that for this the defendant was responsible, having directed the workmen to use more than was prudent. Complainant also claims that the stone rvere not injured by using the brush and pail used upon the brickAvork, upon which this acid might properly and safely be used. The evidence is conflicting upon these subjects, but we think the complainant did not perform his whole duty in the premises. He undertook to erect an ornamental front, one for which the defendant went to the expense of importing stone, that it might be such. The complainant assumed to know how to treat it, and it was his place to see that care was used. We do not find evidence which justifies the conclusion that the owner took the matter out of his hands, and thereby relieved him from responsibility.

It is admitted that the sills were not pointed, but were overlooked. There is no dispute but that the defendant asked that it be done. Complainant said that he Avould attend to it, and asked defendant to send around some lime,, but, when complainant Avent to do the work, no lime was there, and soon after it froze up, and it is claimed that defendant's failure to send the lime when required was sufficient excuse. ■ If the case turned upon [139]*139this question, we, might not feel constrained to deny complainant relief because the sills were not pointed.

Upon the whole case, we think that the defendant had some cause for being dissatisfied, and that the claim that the work was not completed to his satisfaction had a substantial basis, and was not captiously made. That being so, there was nothing due upon the contract, and could not be until the building was completed to defendant’s satisfaction, unless, as complainant claims, the defendant has accepted the work, thereby acknowledging satisfaction.

In the case of Hanley v. Walker, 79 Mich. 607, 618, Mr. Justice Chahplin, speaking for the whole Court, says:

“The principles laid down in Allen v. McKibbin [5 Mich.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Siewek v. F. Joseph Lamb Co.
241 N.W. 807 (Michigan Supreme Court, 1932)
Porath v. Village of Highland Park
179 N.W. 229 (Michigan Supreme Court, 1920)
Mondioli & Stewart v. American Building Co.
145 P. 577 (Washington Supreme Court, 1915)
Evans v. Woodley
138 N.W. 275 (Michigan Supreme Court, 1912)
Scheible v. Klenk
137 N.W. 106 (Michigan Supreme Court, 1912)
Steltz v. Armory Co.
99 P. 98 (Idaho Supreme Court, 1908)
Gier v. Daiber
111 N.W. 773 (Michigan Supreme Court, 1907)
Mosaic Tile Co. v. Chiera
95 N.W. 537 (Michigan Supreme Court, 1903)
Lamson v. City of Marshall
95 N.W. 78 (Michigan Supreme Court, 1903)
United States ex rel. Croll v. Jack
82 N.W. 1049 (Michigan Supreme Court, 1900)
Weggner v. Greenstine
72 N.W. 170 (Michigan Supreme Court, 1897)
Norton v. Hayden
67 N.W. 909 (Michigan Supreme Court, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
58 N.W. 657, 100 Mich. 134, 1894 Mich. LEXIS 772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boots-v-seinberg-mich-1894.