Boothe v. Squaw Springs Water Co.

76 P. 385, 142 Cal. 573, 1904 Cal. LEXIS 979
CourtCalifornia Supreme Court
DecidedMarch 19, 1904
DocketL.A. No. 1209.
StatusPublished

This text of 76 P. 385 (Boothe v. Squaw Springs Water Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boothe v. Squaw Springs Water Co., 76 P. 385, 142 Cal. 573, 1904 Cal. LEXIS 979 (Cal. 1904).

Opinion

CHIPMAN, C.

Plaintiff by an amended complaint, sets forth two causes of action: First, an action on a written contract, dated April 9, 1898, at Los Angeles, to furnish to defendant a certain pumping outfit complete, near Johannesburg, California, including certain extra material in addition to that mentioned in said contract, also for board of man while engaged in erecting the plant, and alleges a balance of $793.31 to be due, with interest from August 15, 1898; second, that after the completion and acceptance of said pumping-plant, at defendant’s request, plaintiff “changed said plant by taking out the one O. M. A. deep-well puinp-head and otherwise changing said original plant so contracted for, and furnished the labor and material necessary for said change on or before November 11, 1898,” valued at $854.97, for which judgment is asked.

Defendant admits the execution of the written contract referred to in plaintiff’s complaint, denies that plaintiff erected the plant in accordance therewith, denies that the alleged change in the plant was made at defendant’s instance, and alleges that such changes were made by plaintiff at his own instance in an endeavor to make said plant comply with the. written contract; alleges, by way of counterclaim, and ■ also a cross-complaint, mutual mistake in the contract, in its not providing for a definite time within which the plant should be completed, and that the agreement was that it should be completed within thirty days, which, it is alleged, t was a reasonable time; alleges great and unnecessary delay in erecting the plant; that said pump was not delivered until July 7, 1898, and proved entirely insufficient, in consequence of which plaintiff undertook to and did, at his own instance, make, changes in the original plan without defendant’s consent, thus causing further delay; that the new plant did not comply with the terms of the contract, and that the pump as constructed on this latter plan was also insufficient; alleges *575 damages of one thousand dollars, by reason of these delays and the failure of plaintiff to comply with his said contract.

The court found the facts to be true as alleged in plaintiff’s first cause of action. As to the second cause of action, that the said new pump-head pumping-plant was erected, but “was by the mutual agreements and understanding of plaintiff and defendant to be furnished without additional cost to defendant therefor”; that there was no mutual mistake of the parties to the written contract; “but said contract contained all the conditions agreed upon by plaintiff and defendant, that plaintiff furnished said pumping-plant on July 7, 1898, at which time it was placed in position ready for operation, and all the other allegations in said second paragraph of said counterclaim are untrue.”

Judgment passed for plaintiff on his first cause of action, with interest from August 15, 1898. Both parties appeal upon the same transcript from the judgment and from the order denying the motion of each for a new trial.

Plaintiff’s Appeal.

Plaintiff’s contention is, that the evidence does not sustain the finding that the pump-head and other material furnished by plaintiff as a substitute for the first was to be furnished without additional cost to defendant. Without considering the somewhat significant fact that the original complaint made no mention of anything due from defendant for the material substituted for certain parts of the first pump erected, there is much evidence tending to show that the substitution as alleged in defendant’s answer was resorted to by plaintiff on his own initiative to make the plant do the work it was originally inadequate to perform. The first plant was installed on July 7th, and when put to the test broke down in some of its parts, and at the suggestion of plaintiff’s expert, Mr. Futhey, who was sent to erect the pump, plaintiff began the construction of a different and stronger pump-head, and after two months’ or more delay the new pump was installed. Subsequently, on October 6, 1898, plaintiff sent defendant a statement of his account, and in it he made no reference to any claim for the substituted machinery. Upon Mr. Futhey’s return to Los Angeles, after it was found that the first pump was insufficient for the service, plaintiff wrote defendant, *576 July 9, 1898, “that he had ordered a heavier pump to he got just as quickly as possible by the factory,” and about July 14th wrote defendant he had signed the agreement sent him by defendant, providing that the pumping-plant being furnished by him to defendant “is not to be considered completed until the heavier castings and bearings now being constructed are furnished and in place, and that the use of the plant in its present condition is not to be considered acceptance thereof by said company” (defendant). There is no evidence of any express contract on defendant’s part to pay for this work, nor is there, in our opinion, evidence from which any contract to do so can be implied. The utmost effect that can be given to the evidence is, that the new pump-head and other appliances were to make good the deficiencies of the first pump.

We conclude that the finding of the court complained of by plaintiff is justified by the evidence.

Defendant’s appeal.

Defendant claims that there is no evidence to support the finding in favor of plaintiff’s first cause of action. The written contract was in the form of a proposal by plaintiff, accepted by defendant. Some of its provisions should be stated, and are as follows: “We [plaintiff] herewith propose to furnish you [defendant] a pumping-plant to be erected on your property ... to consist of the following described machinery which is intended to be a complete pumping-plant . . . [describing it in detail and including “one O. M. A. deep well power pump-head of our own design”], all to be erected in complete working order at the above-described place. It is agreed that we furnish one skilled man to take charge of the erection of the engine and pump.” Defendant was to convey this expert and his tools from Johannesburg to Squaw Springs, board him while there, and return him with , his tools to Johannesburg “on completion of the plant.” Defendant was also to furnish foundation for engine ami pump. The contract further provided: “We guarantee that the above-described plant will be of the capacity to deliver ninety' (90) gallons of water per minute continuously (if necessary amount is in the well), lifting it not exceeding 100 feet to the surface of the ground, and delivering it through 1,640 feet of 4-inch interior diameter iron pipe to a *577 point 450 feet above the surface of the ground at the well. We also guarantee the machinery in this plant against all defects in material and workmanship. The price to be paid for above described plant, when erected, as specified is,” etc.

Defendant contends that there was a material and radical change made in the pump-head without its consent, and that in fact plaintiff never did erect the plant called for by the contract, and hence the court was not justified by the evidence in finding, as alleged in the complaint, that “plaintiff completed the erection of said pumping-plant in complete working order ... in accordance with said proposal, . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
76 P. 385, 142 Cal. 573, 1904 Cal. LEXIS 979, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boothe-v-squaw-springs-water-co-cal-1904.