Book v. Everitt Lumber Co., Inc.

542 P.2d 669, 218 Kan. 121, 1975 Kan. LEXIS 522
Supreme Court of Kansas·Decided November 8, 1975·No. 47,752·Published·Cited by 6 cases

Opinion

The opinion of the court was delivered by

Kaul, J.:

The litigation involved in this appeal was initiated by appellants-landowners, Eldon and Roberta Book, who filed an action under K. S. A. 60-1108, to secure early adjudication of a mechanics lien filed by appellees against the Books’ newly constructed house. This appeal is from an order nunc pro tunc entered by the trial court in the original action two years after the original action was terminated by an order sustaining the Books’ motion for involuntary dismissal of an ^amended cross-petition filed by the defendantappellee, Everitt Lumber Company, Inc. Appellee, Paul Gay Construction Company, is no longer involved in the litigation.

The Books entered into a contract with Everitt Lumber Company, Inc. (hereafter referred to as Everitt), whereby the latter agreed to supply various specified building materials to Books for the construction of a new house. The contract called for building materials in the total amount of $16,000.00 to be furnished by Everitt.

*122 By the time their house was completed, Books had made payments to Everitt totaling $17,365.37 for materials furnished. Everitt, however, maintained that it still had money coming for “extras” consisting of materials furnished over and above those contemplated in the original written contract. In April 1971 Everitt filed a mechanic’s lien statement asserting a lien against the property in the amount of $8,003.01 for materials furnished.

In October 1971 Books filed in district court of Dickinson County an action entitled “Petition to- Adjudicate Liens” in which they contested the validity of Everitt’s lien. Everitt filed an answer and cross-petition in which it alleged that it furnished materials for the Books’ house in the sum of $25,368.38, of which $17,365.37 had been paid by Books, leaving a balance due of $8,003.01 plus interest. Everitt prayed that the lien and claim for principal and interest be ascertained and adjudged and the property be sold to satisfy the amount of the debt established by the court. Books filed a reply to Everitt’s cross-petition in which they admitted payment of $17,-365.37 to Everitt, but denied there was any balance due and owing. In their reply Books alleged that the lien statement was deficient in numerous respects including lack of proper itemization.

After the pleadings were completed a pretrial conference was held on April 5, 1972. As a result of the conference a pretrial order was entered which, among other things, directed Everitt to furnish Books a detailed itemization to show all of the materials allegedly furnished and to specify all of the materials that were included under the $16,000.00 original contract, and to show any “extras” above that amount.

The pretrial order further stated that a later pretrial hearing would be conducted after the items referred to had been furnished to Books.

On June 5, 1972, Books filed a motion for involuntary dismissal of Everitt’s counterclaim alleging that Everitt had failed to provide the itemization called for in the pretrial order and that by its non-action had violated an order of the court as proscribed by K. S. A. 1974 Supp. 60-241 (b) and (c), and that the counterclaim of Everitt should be involuntarily dismissed.

The trial court heard the motion on June 13, 1972, and on July 3, 1972, the court’s order was journalized. The substance of the journal entry reads:

“Whereupon, the Court hears the Motion of Plaintiff for Involuntary-Dismissal of the Amended Cross-Petition of Defendant, Everitt Lumber Com *123 pany, Inc., and the Court after hearing arguments of counsel and being fully advised in the premises finds that said motion for Involuntary Dismissal as provided by K. S. A. 60-241 (b) (c) should be sustained and said Amended Cross-Petition dismissed.
“It IS THEREFORE, BY THE COURT, CONSIDERED, ORDERED, ADJUDGED AND, decreed That the Motion of both Defendants for continuance be and it is hereby denied; that the motion of Plaintiffs for involuntary dismissal of the Amended Cross-Petition of the Defendant, Everitt Lumber Company, Inc., be and the same is hereby granted and sustained one-half of tire total costs of the above entitled action are hereby assessed against the Defendant, Everitt Lumber Company, Inc.”

No appeal was taken from the order of dismissal.

We are informed in Everitt’s brief that following the dismissal of the Dickinson County lawsuit it replaced some specially ordered materials which Books contended were not satisfactory and that thereafter Everitt filed an action against Books in the district court of Saline County. In this latter action, filed on December 26, 1973, Everitt alleged $8,0003.01 was due and owing on the bill for materials. Books filed an answer in the Saline County action on January 23, 1974, setting up the Dickinson County judgment of June 13, 1972, as a bar to the action. On April 17, 1974, the Saline County district court entered an order directing that the dispute over the construction and intention of the journal entry of June 13, 1972, be resolved by a nunc pro tunc proceeding by the judge who made the decision in the district court of Dickinson County. Neither party objected to, nor challenged, this order of the Saline County district court.

Thereafter, on May 31, 1974, Everitt filed a motion for an order nunc pro tunc in the district court of Dickinson County. The motion reads in pertinent part as follows:

“2. In support of said motion, the Defendant, Everitt Lumber Company, Inc., states that the adjudication the Court made in sustaining the motion of the Plaintiffs determined only the question of the Defendant’s right to establish a hen on property owned by the Plaintiffs; that at no time did this Court make a judicial determination of the rights of the Defendant, Everitt Lumber Company, Inc., to pursue a claim for money judgment against the Plaintiffs.
“3. In further support of the motion, the Defendant, Everitt Lumber Company, Inc., states that the provisions of K. S. A. 60-241 (b) provides that if the Court is to render judgment on the merits, it must make findings as provided by Section 60-252 (a); that no findings of fact were made as shown in the Journal Entry of June 13, 1972.
“4. The Court, at no time, intended the Journal Entry of June 13, 1972, to be a determination of all of the rights of the parties to that action, and that a question has arisen as to the construction of the wording of the Journal *124 Entry of June 13, 1972. As a result of a clerical error, the Journal Entry of June 13, 1972, contains an omission to the extent that it does not state that the sustaining of the motion for involuntary dismissal determined only the rights of the Defendant to establish a lien on property owned by the plaintiffs.
“Wherefore, the Defendant, Everitt Lumber Company, Inc., prays for an Order nunc pro tunc modifying and correcting the Order of this Court dated June 13, 1972, in order that the same might accurately reflect the action taken by the Court on that date.”

Free access — add to your briefcase to read the full text and ask questions with AI

Book v. Everitt Lumber Co., Inc., 542 P.2d 669, 218 Kan. 121, 1975 Kan. LEXIS 522 (kan 1975).

542 P.2d 669 (Book v. Everitt Lumber Co., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Smith
441 P.3d 1041 (Supreme Court of Kansas, 2019)
State v. Vaughan
Court of Appeals of Kansas, 2019
Holman v. Stapleton
Court of Appeals of Kansas, 2018
State v. Moore
Court of Appeals of Kansas, 2017
State v. Storer
382 P.3d 467 (Court of Appeals of Kansas, 2016)
State v. Coryell
Court of Appeals of Kansas, 2016
State v. Little
Court of Appeals of Kansas, 2015
In re the Marriage of Leedy
109 P.3d 1130 (Supreme Court of Kansas, 2005)
City of Salina v. Star B, Inc.
731 P.2d 1290 (Court of Appeals of Kansas, 1987)
DeForest v. DeForest
694 P.2d 1241 (Court of Appeals of Arizona, 1985)