Bonsack & Pearce, Inc. v. School District

49 S.W.2d 1085, 226 Mo. App. 1238, 1932 Mo. App. LEXIS 82
CourtMissouri Court of Appeals
DecidedMay 2, 1932
StatusPublished
Cited by20 cases

This text of 49 S.W.2d 1085 (Bonsack & Pearce, Inc. v. School District) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bonsack & Pearce, Inc. v. School District, 49 S.W.2d 1085, 226 Mo. App. 1238, 1932 Mo. App. LEXIS 82 (Mo. Ct. App. 1932).

Opinions

Plaintiff is an incorporated company engaged in the business of an architect and defendant is a town school district. Plaintiff sued on a contract to recover for architectural services rendered and for the loss of prospective profits which it would have earned if it had been permitted to complete the contract. The contract is made a part of the petition. It was executed May 29, 1929, *Page 1239 and was signed by the president and secretary of the plaintiff under its seal, and signed by the president and secretary of the school board of the defendant district. By its terms plaintiff agreed to furnish complete architectural and engineering services required in a proposed school building program to be decided upon by the school board after the architect submitted a report upon the condition of school buildings, and after sketches and estimates of cost and of construction work necessary to meet the needs of the district were submitted. Plaintiff was required to furnish sketches, estimates of cost, and a water color picture of proposed new work for use in submitting a proposition to vote bonds, and the contract was to be void if the proposed bond issue should fail to carry within six months. The services to be rendered by plaintiff also included conferences, working plans, scale and full size details, engineering drawings, heating, plumbing and equipment layouts, specifications, and general supervision of the work. It was agreed that in consideration of said services the district would pay a sum equal to five per cent of the total cost of the entire building construction work and the contract provided a method of installment payment as the work progressed.

Plaintiff proceeded with the work under the contract, made a survey or examination of the old structures, and prepared the preliminary estimates, sketches, drawings, and plans practically covering in its entirety the proposed improvement. While continuing said work, and after having performed services of the value of $850, plaintiff was notified by letter from the secretary of the school board under date of June 12, 1929, that at an adjourned meeting of the board of education held on June 11, 1929, it was ascertained that the contract entered into with plaintiff was not in accordance with law and was void for the reason that a majority of the members of the board did not vote favorably on the proposition. The letter further stated: "We find that we have in force a previous contract, and therefore are cancelling the contract with your firm that was signed without the necessary legal right. We regret the necessity of taking this action in the matter, and trust that it has caused you no great inconvenience." A representative of the plaintiff went to Marceline and saw the individual members of the board and endeavored to get them to meet, which they refused to do. Plaintiff proposed to continue the work which it was obligated to do under the contract, but was denied the privilege. The board employed another architect at the same rate of compensation and under whose supervision the building program was concluded.

A previous attempt to vote bonds had failed and, while not expressly called for in the contract, plaintiff was to aid in another campaign to procure the authorization of bonds in an amount found necessary and was to furnish advertising and other publicity matter *Page 1240 for use by the board, and had such matter prepared ready for use. A bond issue of $90,000 was duly voted and authorized within the time specified in the contract.

The petition sets forth all of the foregoing facts and alleges that in addition to the value of the service actually performed, plaintiff would have made a profit of something in excess of $2000 if defendant had permitted plaintiff to proceed under the contract and had not terminated it.

The answer admits the corporate existence of defendant as a town school district; denies each and every allegation of the petition; alleges that the purported contract sued on was at all times void; that defendant had no authority to enter into such contract for the reason that the board of education of said school district consisted of six members and that no contract with the plaintiff was ever at any time authorized by a majority of said board; that said contract was not made upon a consideration wholly to be performed or executed subsequent to the alleged making of said contract; and that no consideration for said contract was ever reduced to writing.

The reply denied all new matter contained in the answer, and detailed circumstances, acts, and conduct at the meeting of the board of directors said to constitute legal authority for the execution of the contract as made.

There is little controversy over the facts in the case and the only subject upon which there is conflict in the testimony is in reference to what occurred during the meeting of the school board at the time the contract is said to have been authorized and signed. The board consisted of six members and met on May 29, 1929, expressly for the purpose of engaging the services of plaintiff. The president of the board had requested a member of the plaintiff company to attend the meeting in person which he did. The representative of plaintiff brought with him a prepared contract, the same as that heretofore referred to, and already signed by the plaintiff, and presented it to the board for its consideration. There were five members of the board in attendance. The whole subject matter of the proposed improvement, as well as the contract, was discussed between the members of the board present and the representative of the plaintiff, and in the requested absence of said representative. The representative was then recalled and a discussion of the contract was resumed. Over the objection of defendant, plaintiff was permitted to introduce testimony as to what was said and done by the members of the board when a motion was made to accept the contract and to authorize its execution. The objection was on the ground that the testimony would be in conflict with the written minutes of the board. As we read the abstract the evidence was received not as a contradiction of the record *Page 1241 of the board, but to show the facts and the actual transactions at the time not shown by the minutes of the meeting.

Such evidence favorable to the plaintiff shows that upon the presentation of the contract to the board a motion was made by one member and seconded by another that the contract be let to plaintiff, and that the president and secretary execute the same on behalf of the school board. The motion was put to a vivavoce vote and certain members responded in the affirmative. Dissenting votes were called for, but no member voted in the negative and no one showed dissent in any manner. The president of the board thereupon declared the motion carried. Immediately after the motion was adopted the contract and a duplicate were signed by the president and secretary of the school board and each party retained a copy.

The minutes of the meeting of the school board held on May 29, were offered in evidence by the defendant. They show the presence of five members of the board and the presence of the representative of plaintiff; that plans and drawings of various school buildings were exhibited with explanations as to details or arrangement and construction; that it was moved and seconded that Bonsack Pearce be employed as architects on the proposed high school building at the customary fee of five per cent of the total cost. Then follows the part upon which defendant relies: "Motion being put by the president, it was carried by a majority of members present, there being three affirmative votes, president and secretary not voting."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Forbis v. Fremont County School District No. 38
842 P.2d 1063 (Wyoming Supreme Court, 1992)
Mississippi-Fox River Drainage District 2 of Clark County v. Plenge
735 S.W.2d 748 (Missouri Court of Appeals, 1987)
Braddy v. Zych
702 S.W.2d 491 (Missouri Court of Appeals, 1985)
Opinion No. 136-81 (1981)
Missouri Attorney General Reports, 1981
Opinion No. 65-81 (1981)
Missouri Attorney General Reports, 1981
State ex rel. Stewart v. King
562 S.W.2d 704 (Missouri Court of Appeals, 1978)
Opinion No. 162-77 (1977)
Missouri Attorney General Reports, 1977
Opinion No. 168-76 (1976)
Missouri Attorney General Reports, 1976
Williams v. Longtown School District No. 71
468 S.W.2d 673 (Missouri Court of Appeals, 1971)
STATE Ex Rel ROBERTS v. GRUBER
373 P.2d 657 (Oregon Supreme Court, 1962)
Scales v. Butler
323 S.W.2d 25 (Missouri Court of Appeals, 1959)
School District of Kirkwood R-7 v. Zeibig
317 S.W.2d 295 (Supreme Court of Missouri, 1958)
Fulton v. City of Lockwood
269 S.W.2d 1 (Supreme Court of Missouri, 1954)
State v. Sappington
261 S.W.2d 385 (Missouri Court of Appeals, 1953)
Mullins v. Eveland
234 S.W.2d 639 (Missouri Court of Appeals, 1950)
State v. School Dist. No. 7, Lewis County
203 S.W.2d 881 (Missouri Court of Appeals, 1947)
Martin v. Ballinger
77 P.2d 888 (California Court of Appeal, 1938)
State Ex Rel. School District of Affton v. Smith
80 S.W.2d 858 (Supreme Court of Missouri, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
49 S.W.2d 1085, 226 Mo. App. 1238, 1932 Mo. App. LEXIS 82, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bonsack-pearce-inc-v-school-district-moctapp-1932.