Bond Bros. v. Robinson

1983 Mass. App. Div. 280
CourtMassachusetts District Court, Appellate Division
DecidedSeptember 8, 1983
StatusPublished
Cited by3 cases

This text of 1983 Mass. App. Div. 280 (Bond Bros. v. Robinson) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bond Bros. v. Robinson, 1983 Mass. App. Div. 280 (Mass. Ct. App. 1983).

Opinion

Banks, J.

This is a report, in the form of a case stated, in a third-party action for a subcontractor’s indemnification under a comprehensive general liability policy of insurance.

On August 11, 1978, pláintiff Bond Bros., Inc. (“Bond”) executed a contract for the installation by defendant D&R Steel Erectors, Inc. (“D&R”) of reinforcing steel and welded wire mesh (rebar work) in the concrete construction of a power substation for the MBTA in Revere, Massachusetts. The subcontractor expressly required D&R’s coverage under a comprehensive general liability insurance contract.

D&R concluded its installation work on the north wall of the power station on October 18, 1978 and so notified Bond. On October 26, 1978, Bond completed the form of the north wall and poured concrete therein. Bond subsequently discovered that D&R had incorrectly placed, in deviation from subcontract specifications, the reinforcing steel in the north wall, and had also failed to install a portion of steel required by the subcontract. D&R’s performance resulted in a wall which “did not meet design criteria, was structurally unstable, and would require remedial measures.” Bond, as general contractor, was ordered by the MBTA to undertake all necessary remedial measures which ultimately consisted of the “construction of corbels as exterior reinforcing members.”

Summary judgment was entered herein for plaintiff Bond against defendant D&R in the sum of $33,239.00 for the full costs of all repair measures undertaken by Bond.

Third-party defendant American Insurance Company (“American”) denied D&R’s third-party claim for reimbursement for this judgment on the basis that such remedial costs did not constitute a loss indemnified under the comprehensive, general liability insurance policy (“GCL”) issued by American to D&R. The trial court entered judgment on August 21, 1980 for American on D&R’s third-party complaint.

1. There was no error in the trial court’s judgment for third-party defendant [281]*281American. The liability of defendant/third-party plaintiff D&R, upon Bond’s claim for D&R’s breach of contract, breach of warranty and negligence, was not a loss covered by the third parties’ insurance contract.

The policy in question obligated American to:

“pay on behalf of the insured all sums which the insured shall become legally obligated to pay as damages because of. . .
“property damage. . .
“to which this insurance applies, caused by an occurence. . .”

2. “Property damage” is defined in the CGL as:

“ (1) physical injury to or destruction of tangible property which occurs during the policy period, including the loss of use thereof at any time resulting therefrom. ...”

Third-party plaintiff D&R asserts that its rebar work resulted in compensable “property damage” herein because such work caused “physical injury” to “tangible property” in the form of north wall of the MBTA station.

The federal case authority relied upon by D&R for its assertion is factually distinguishable from the instant action. Each of these cases involved the installation of a latently defective component part into a larger structural entity which resulted in damage to, or destruction of, such entity. See, e.g., Dakota Block Co. v. Western Casualty & Sur. Co., 132 N.W.2d 826 (S.D. 1965) (concrete blocks subject to discoloration and fading used in construction of school building); Pittsburgh Plate Glass Co. v. Fidelity & Gas Co. of N.Y., 281 F.2d 538 (3 Cir. 1960) (peeling, flaking paint baked into window jalousies); Bundy Tubing Co. v. Royal Indem. Co., 298 F.2d 151 (6 Cir. 1962) (defective tubing installed in radiant heating system); Hauenstein v. St. Paul-Mercury Indem. Co., 65 N.W.2d 122 (Minn. 1954) (plaster prone to cracking and shrinking used as a principal component in hospital walls and ceilings). Similarly, in United States Fidel. & Guar. v. Nevada Cement Co., 561 P.2d 1335 (Nev. 1977), a case characterized by D&R as “virtually identical” to the instant action, compensable property damage was held to have occurred when the structural integrity of a building was impaired by the use of concrete which had been defectively manufactured with an insufficient amount of chemical compound. The Supreme Court of Nevada stated:

the mere presence of a defective product in an entity can constitute property damage. . . .In the instant case, the presence of defective cement weakened the total structure, thereby requiring additional shoring to avoid the danger of collapse. We are not persuaded by appellant’s argument that structural damage may be recognized only if collapse or removal ensues, and not if replacement is averted by a shoring process. We therefore think the trial court properly determined that the defective cement caused injury under respondent’s insurance policy, even though financial loss was minimized by and limited to installation of shoring and related expenses.

Ibid., at 1337-1338.

In the case sub judice, the defect was not in the materials employed by the insured but in the insured’s workmanship or lack thereof. D&R did not utilize or install defective steel or other products in its rebar work, but simply failed to complete the same in conformity with the contract. The remedial measures undertaken by Bond were to correct D&R’s work or rather to complete it, reinforcing corbels were added to provide that degree of structural soundness to the wall which had been the responsibility of D&R as subcontractor. It has been stated that a “claim limited to remedying faulty workmanship or materials does not constitute ‘injury to or destruction of tangible property. ’ ’ ’ Vernon Williams & [282]*282Son v. Continental Ins. Co., 591 S.W.2d 760, 763 (Tenn. 1979). The rationale for this rule is derived from the purposes of CGL coverage and from the distribution of risks to be borne by the contractor and by the insurance company:

The insured-contractor can take pains to control the quality of the goods and services supplied. At the same time, he undertakes the risk that he may fail in this endeavor and thereby incur contractual liability whether express or implied. The consequences of not performing well is part of every business venture; the replacement or repair of faulty goods and works is a business expense, to be borne by the insure-contractor in order to satisfy customers. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parent v. Blue Cross & Blue Shield of Massachusetts, Inc.
1993 Mass. App. Div. 67 (Mass. Dist. Ct., App. Div., 1993)
Martin v. Harry E. Dillon, Inc.
1991 Mass. App. Div. 184 (Mass. Dist. Ct., App. Div., 1991)
Landers v. Sherwin-Williams Co.
1989 Mass. App. Div. 58 (Mass. Dist. Ct., App. Div., 1989)

Cite This Page — Counsel Stack

Bluebook (online)
1983 Mass. App. Div. 280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bond-bros-v-robinson-massdistctapp-1983.