Bolton v. Adirondack Park Agency

128 Misc. 2d 59, 488 N.Y.S.2d 969, 1985 N.Y. Misc. LEXIS 2878
CourtNew York Supreme Court
DecidedApril 20, 1985
StatusPublished
Cited by3 cases

This text of 128 Misc. 2d 59 (Bolton v. Adirondack Park Agency) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bolton v. Adirondack Park Agency, 128 Misc. 2d 59, 488 N.Y.S.2d 969, 1985 N.Y. Misc. LEXIS 2878 (N.Y. Super. Ct. 1985).

Opinion

OPINION OF THE COURT

Thomas E. Mercure, J.

In the within proceeding pursuant to CPLR article 78, petitioners seek to annul a September 1,1983 determination of the respondent Adirondack Park Agency (hereafter referred to as the APA or the agency) granting the respondent project sponsors, Barry Silverstein and Twin Ponds Associates (hereafter referred to in the aggregate as the sponsor) a permit to create a 49-lot subdivision on a 406 ± acre parcel of land situate on the east side of New York State Route 30 in the Town of Duane, Franklin County, New York.

In support of the petition, petitioners contend: (1) that the subject application involved more than 50 lots and that, accordingly, the director of operations of the APA lacked authority to review the application and grant the permit; (2) that the said director of operations lacked authority to deny petitioners’ request for a public hearing on the application, and the determination of the APA not to conduct a public hearing was based on inadequate consideration of necessary criteria; (3) that the APA failed to obtain legally mandated information in connection with the application and failed to make required findings and conclusions; and (4) that the provisions of the APA Act (Executive Law art 27) and regulations enacted thereunder which require that a public hearing be held if a subdivision permit is denied, but not if the permit is granted, constitute a violation of due process and equal protection.

[61]*61THE FACTUAL BACKGROUND

The sponsor owns two contiguous tracts of land in the Town of Duane; a parcel of 2,800 ± acres lies to the west of Route 30, and the above-mentioned parcel of approximately 406 acres lies to the east thereof. In February of 1982, the sponsor’s authorized representative, Spencer Thew, a licensed professional engineer, submitted preliminary materials to the APA in connection with the subject project. The materials consisted of a “Geotechnical Site Analysis” report, dated December 7, 1981; an application for conceptual review; and a preliminary lot layout for 93 residential lots to be located on the 406 ± acre lot. According to the APA, these materials did not constitute a formal application for a subdivision permit, but rather, preliminary material for agency review, so as to permit it to advise the sponsor informally of the feasibility of the plans. In fact, the preliminary nature of the submission was specifically discussed between Thew and an agency review specialist, Gary Duprey, on March 1, 1982, and confirmed in a March 2,1982 letter from Duprey to Thew. Such preliminary submissions and informal discussions are specifically encouraged by 9 NYCRR 572.3 and 574.2.

Between February 19, 1982 and March 22, 1983, a great deal of preliminary consideration, inspection, communication and recommendation took place. Studies were made and discussion was had with respect to the impact of the project on deer wintering areas, soil conditions, groundwater table, percolation rates, road locations, deep hole test pits, site topography and vegetation, and utility lines, and their impact on the project and site location. On March 22,1983, Thew submitted an application to subdivide the 406 ± acre parcel into 98 residential lots, to be accomplished in two phases: phase I was a proposed 49-lot residential subdivision on the northern half of the parcel and phase II was a 49-lot residential subdivision on the southern half. The application also indicated that a third phase, involving subdivision of the lands to the west of Route 30 into an additional 278 residential lots, was contemplated. However, no drawings were submitted with respect to the latter subdivision. During ongoing discussions between the agency staff and Thew, prior and subsequent to March 22, 1983, it was recommended that any development proposed on the 406 ± acre site be undertaken on the northern portion thereof, as it had the most environmentally compatible development potential.

On April 12, 1983, the agency issued a “Notice of Incomplete Permit Application” wherein it sought additional information [62]*62regarding the project application, especially whether the sponsor’s “project” consisted only of phase I or whether phases II and III were to be considered as well. On May 13, 1983, Thew submitted the requested information; with respect to the inquiry about the scope of the project, Thew stated that final approval for phase I was being sought at that time and that phases II and III were proposed for future development. Phase II development plans were to be submitted for approval upon successful completion of phase I and phase III development plans were to be submitted for approval upon successful completion of phase II. Based upon this response, the agency made a determination that the “project” subject to review was only phase I.

On June 3, 1983, the agency issued a “Notice of Application Completion”, pursuant to 9 NYCRR 572.8, with respect to the 49-lot subdivision. Notice of the project application was sent to all ascertainable adjoining landowners and to the Environmental Notice Bulletin for publication. In addition, a “Notice of Project Application Pending” was published on June 17,1983, in the Malone Evening Telegram. Comments were invited to be submitted by July 1,1983, in order to allow the agency sufficient time to evaluate them. The notices resulted in comments and inquiries from a total of four sources, two of which were the petitioners. Of the two remaining sources, one wanted nothing more than the sponsor’s address. Thereafter, the director of operations made a determination not to conduct a public hearing on the project application. The agency notified petitioner Bolton of this determination by letter of August 2, 1983.

The agency staff had reviewed proposed permit conditions it would recommend to the director of operations for inclusion in any order approving the project with both Thew and petitioner Bolton’s representatives. Based upon their input, the staff made final recommendations for conditions to the director of operations. On September 1, 1983, the director of operations issued permit No. 83-71 to the sponsor for what the APA contends was a 49-lot subdivision, consisting of 48 residential lots and the remaining contiguous lands of the sponsor, counted as one additional lot.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dudley Road Ass'n v. Adirondack Park Agency
214 A.D.2d 274 (Appellate Division of the Supreme Court of New York, 1995)
Green Island Associates v. Adirondack Park Agency
178 A.D.2d 860 (Appellate Division of the Supreme Court of New York, 1991)
Friends of Woodstock, Inc. v. Town of Woodstock Planning Board
152 A.D.2d 876 (Appellate Division of the Supreme Court of New York, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
128 Misc. 2d 59, 488 N.Y.S.2d 969, 1985 N.Y. Misc. LEXIS 2878, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bolton-v-adirondack-park-agency-nysupct-1985.