Bolton Corp. v. T. A. Loving Co.

334 S.E.2d 495, 77 N.C. App. 90, 1985 N.C. App. LEXIS 4026
CourtCourt of Appeals of North Carolina
DecidedOctober 1, 1985
DocketNo. 8410SC1215
StatusPublished

This text of 334 S.E.2d 495 (Bolton Corp. v. T. A. Loving Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bolton Corp. v. T. A. Loving Co., 334 S.E.2d 495, 77 N.C. App. 90, 1985 N.C. App. LEXIS 4026 (N.C. Ct. App. 1985).

Opinion

COZORT, Judge.

Plaintiffs principal assignment of error concerns the trial court’s granting summary judgment for defendant. At the center of the controversy is a document entitled “Release in Full” which signifies a settlement agreement between defendant and plaintiffs insurance company. Plaintiff contends the trial court erred in granting summary judgment because it never ratified the document, or that at most, only ratified part of the agreement, and nevertheless by the terms of the document retained its right to sue. For the reasons stated below, we affirm.

Plaintiff and defendant were prime contractors in the construction of the Walter R. Davis Library at the University of North Carolina at Chapel Hill.

In September 1979, the State entered into contracts with plaintiff and defendant for the construction of the library. Defendant was the general contractor for the project and was responsible for furnishing labor and materials and performing certain work on this project. In addition to furnishing labor and materials, defendant was designated “Project Expediter,” and as such, was responsible for coordinating all schedules and ongoing projects in the course of construction. Plaintiff was responsible for installation of the library’s heating, ventilation, and air conditioning system.

Both plaintiffs and defendant’s contract with the State contained identical provisions specifying that work would be performed within 930 consecutive calendar days. The construction project, however, experienced numerous delays and was not completed until well after the 930-day time period.

On 14 April 1983, a water line at the unfinished library was ruptured by plaintiff’s construction crew. In the following months, defendant filed claims with plaintiff’s insurance carrier, Aetna Casualty and Surety Co., for delays and damages to property.

[92]*92On 16 November 1983, plaintiff filed its lawsuit against the defendant seeking damages it allegedly suffered by reason of defendant’s delay in completing its work on the library and the resulting interference with plaintiffs work on the library. In its complaint plaintiff alleged that defendant was responsible for maintaining certain progress on its own work and scheduling and coordinating the work of the other prime contractors; that defendant failed to timely complete its work as required by the September 1979 contract; and that plaintiff was delayed in performing its contract with the State and suffered $350,000 in damages, by reason of defendant’s failure to maintain progress and failure to coordinate progress on the job. Plaintiff contended that defendant was liable to it both by reason of breach of contract and under a theory of negligence.

On 23 January 1984, defendant filed its answer denying the bulk of plaintiff’s allegations, moved to dismiss plaintiff’s complaint under Rule 12(b)(6), and counterclaimed alleging that it had been damaged by reason of the broken water line for which plaintiff was responsible and also that plaintiff was liable to defendant for failure to pay its pro rata share of the power bills.

On 21 February 1984, upon receipt of $136,445.29 from plaintiff’s insurer in the ruptured water pipe claim it had filed with the insurer, defendant executed a “Release in Full” in which defendant

releasefd] and forever discharge[d] the said Bolton Corporation and their representatives, Aetna Casualty & Surety Co. and all other persons, firms or corporations from all claims, demands, damages, actions, or causes of action, on account of damage to property, The Central Library, Chapel Hill, N. C. which occurred on or about the 14th day of April, 1983, by reason of water pipe breaking and of and for all claims or demands whatsoever in law or in equity, which it and its successors can, shall or may have by reason of any matter, cause or thing whatsoever prior to the date hereof.
* * * *
It is Understood and Agreed that this is a full and final release of all claims of every nature and kind whatsoever, [93]*93and releases claims that are known and unknown, suspected and unsuspected.

Only defendant and accompanying witnesses signed the document.

The next day, 22 February 1984, plaintiff filed its reply to defendant’s counterclaim asserting in its concluding paragraph that “any recovery sought is barred by the doctrine of accord and satisfaction, settlement and release.”

On 3 August 1984, defendant moved for summary judgment pursuant to Rule 56, N.C. Rules Civ. Proc. Both parties submitted briefs, memoranda, and supporting exhibits. Defendant contended that plaintiffs plea of settlement and release was a binding ratification of the settlement between plaintiffs insurer, Aetna Casualty, and defendant, which barred plaintiffs original claim. The trial court granted defendant’s motion for summary judgment in an order filed 13 September 1984.

On the issue of ratification of settlement, our Supreme Court has stated:

It seems to be well-nigh the universal holding in this country that where an insurance carrier makes a settlement in good faith, such settlement is binding on the insured as between him and the insurer, but that such settlement is not binding as between the insured and a third party where the settlement was made without the knowledge or consent of the insured or over his protest, unless the insured in the meantime has ratified such settlement.

Lampley v. Bell, 250 N.C. 713, 714, 110 S.E. 2d 316, 317 (1959). In Patterson v. Lynch, 266 N.C. 489, 493, 146 S.E. 2d 390, 393 (1966), the Supreme Court noted that “ ‘[o]ne of the most unequivocal methods of showing a ratification of an agent’s unauthorized act is by bringing an action or basing a defense on the unauthorized act with full knowledge of the material facts.’ [Citation omitted.]”

Here it is undisputed that at the time plaintiffs insurer settled with the defendant, plaintiff had not consented to the settlement but that at the time plaintiff filed its reply to defendant’s counterclaim plaintiff had full knowledge of the material facts of the settlement and “Release in Full.” Therefore, the question we [94]*94must decide is whether plaintiff has ratified the compromise settlement by pleading the settlement and release in its reply as a bar to defendant’s counterclaim, and, if so, whether the ratification of the settlement bars plaintiffs claim for damages presented in this lawsuit. At least in the context of motor vehicle negligence cases, this question has repeatedly been answered in the affirmative. See, e.g., Keith v. Glenn, 262 N.C. 284, 136 S.E. 2d 665 (1964); Johnson v. Austin, 29 N.C. App. 415, 224 S.E. 2d 293, cert. denied, 290 N.C. 308, 225 S.E. 2d 829 (1976); White v. Perry, 7 N.C. App. 36, 171 S.E. 2d 56 (1969).

In Keith v. Glenn, supra, the court phrased the issue as follows: “May plaintiff maintain his action against defendant and at the same time rely on the release given by defendant to defeat the counterclaim?” It ruled that “[u]nless we are to depart from logic and overrule prior decisions of this Court, the answer must be ‘No.’ ” 262 N.C. at 286, 136 S.E. 2d at 667.

A consummated agreement to compromise and settle disputed claims is conclusive and binding on the parties to the agreement and those who knowingly accept its benefits. Bradford v. Kelly, 260 N.C. 382, 132 S.E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Houghton v. Harris
89 S.E.2d 860 (Supreme Court of North Carolina, 1955)
Bradford v. Kelly
132 S.E.2d 886 (Supreme Court of North Carolina, 1963)
McKinney v. Morrow
196 S.E.2d 585 (Court of Appeals of North Carolina, 1973)
White v. Perry
171 S.E.2d 56 (Court of Appeals of North Carolina, 1969)
Johnson v. Austin
224 S.E.2d 293 (Court of Appeals of North Carolina, 1976)
Lampley v. Bell
110 S.E.2d 316 (Supreme Court of North Carolina, 1959)
Cannon v. Parker
106 S.E.2d 229 (Supreme Court of North Carolina, 1958)
Keith v. Glenn
136 S.E.2d 665 (Supreme Court of North Carolina, 1964)
Patterson v. Merrill Lynch, Pierce, Fenner & Smith, Inc.
146 S.E.2d 390 (Supreme Court of North Carolina, 1966)
Snyder v. Kenan Oil Co.
68 S.E.2d 805 (Supreme Court of North Carolina, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
334 S.E.2d 495, 77 N.C. App. 90, 1985 N.C. App. LEXIS 4026, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bolton-corp-v-t-a-loving-co-ncctapp-1985.