Bolt v. Nelson

241 N.W. 896, 257 Mich. 610, 1932 Mich. LEXIS 882
CourtMichigan Supreme Court
DecidedApril 4, 1932
DocketDocket No. 144, Calendar No. 35,870.
StatusPublished
Cited by1 cases

This text of 241 N.W. 896 (Bolt v. Nelson) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bolt v. Nelson, 241 N.W. 896, 257 Mich. 610, 1932 Mich. LEXIS 882 (Mich. 1932).

Opinions

McDonald, J.

This is an appeal to review a judgment entered in the circuit court of Muskegon county in favor of the plaintiffs in the sum of $21,769.21.

The defendant had a contract with the State highway commissioner for the construction of a portion of -the Holton road, so called. He . sublet a part of the work to the plaintiffs by contract in writing. This controversy arises in part over -the construction of certain provisions of the contract, and in part over charges made by the plaintiffs for extra work occasioned, they claim, by the failure of the defendant to construct a bridge .over Cedar creek *612 in time to enable them to complete their fills according to contract. The claims of the parties in respect to these matters will be more fully stated as we come to discuss the disputed charges.

Item 12 of the plaintiffs ’ bill of particulars is disputed. It makes the following charges:

“12 — ’Trenching for pavement.... 6,091.9 cu. yds. Removing earth from pavement ...................5,537.4 ” ”
Trenching for stone and clay shoulders ...............7,23,0.8 ” ”
“Total ............18,860.1 cu. yds.
“@ 38y2íS per cu. yd.......$7,263.13”

Whether this item contains proper charges depends upon the construction of the following provisions of the contract:

“In respect to item 1, aforesaid, the subcontractors agree that said item shall include trenching for concrete slab; clearing off pavement; shouldering and ditching; removing all grubs, stumps and stones not included in foregoing item number 6; trimming job for acceptance; and placing and removing detour road on section A and removing all dirt, except that which is taken care of by other items and units.”

Item 1, to which this provision refers, is for the work of earth excavation for which plaintiffs were to be paid 38yy per cubic yard. The defendant contends that the quoted provision of the contract was intended to show the understanding of the parties as to what work was to be included in excavation; that trenching for concrete slabs, etc., was considered to be a part of the excavation, and payment therefor was to be included in the price paid to the plaintiffs for the excavation and was not to .be *613 charged for separately. If this is a correct construction of the contract, the plaintiffs are not entitled to payment of the amount charged in item 12. But the plaintiffs contend for a different construction. They say that the quoted provision merely classifies the work of trenching for concrete slabs, etc., as excavation for the purpose of fixing the price at which it should be done, and that, therefore, the charges in item 12, which were based on the contract price for excavation, were proper and were rightly allowed by the trial court.

“In respect to item number 1, aforesaid, the subcontractors agree that said item shall include .trenching for concrete slabs, etc.”

As item number 1 was for excavation, the language to be construed has the same meaning as though it read:

“In respect to excavation the subcontractors agree that excavation shall include trenching for concrete slabs, etc.”

To give the language the meaning contended for by the plaintiffs, it would be necessary to have it read as follows:

“In respect to excavation, the subcontractors agree that the contract price for trenching for concrete slabs, etc., shall be the same as that for excavation.”

We cannot believe it was the intention of the parties to take such a roundabout way of fixing the price of trenching for slabs, etc. In the subcontract, all of the' work which the plaintiffs were to perform except the work in question is specified in 13 items at fixed prices. If it were intended that this work should be paid for, the usual and natural thing to *614 do would be to put it in the schedule of prices. It cannot be found there or elsewhere in the contract unless by inference, as plaintiffs claim, it was intended to be paid for as excavation at 38% per cubic yard. Such an inference is unreasonable, because the work is of a kind that is not susceptible to measurement as excavation. The items themselves make this clear. For instance, one of the items is “placing and removing detour road on section A. ” It would be impossible to compute by the cubic yard the cost of “placing and removing detour road.” Another item, the cost of which cannot be computed by the cubic yard as for excavation is “removing all grubs, stumps, and stones not included in foregoing item number 6.” Item number 6 is scheduled as “clearing and grubbing” and the price was fixed at $75 per acre in the schedule of prices. In fixing the price according to acreage, the parties recognized the fact' that it could not be computed by the cubic yard. Notwithstanding this, the plaintiffs are claiming that the reason for putting some of the work for “cleaning and grubbing” in item number 1 was for the purpose of fixing the price at 38%(¿ a cubic yard, the same as excavation. In other words, according to their contention, the same work they were to get $75 an acre for in item number 6 they were to get 38% a cubic yard for under item number 1. The parties could not have so intended. It is more reasonable to suppose that when they agreed on item number 6, they had in mind that there might be some stumps and grubs in the way of thé excavation which could not be charged,for-by the acre, and these they regarded.as incidents of excavation, compensation for which-should be included in the contract price paid for excavation. They were in fact incident to the excavation and a necessary part of that work. Davies v. East Saginaw, 66 Mich. 37.

*615 This class of work seems to be so considered in contracts made by the highway commissioner for the construction of roads. In defendant’s contract with the State, such work was considered incident to excavation,. and he was allowed no compensation for it except as it was included in the contract price for excavation. It is not reasonable to believe that in subletting to the plaintiffs he would agree to pay them $7,263.13 for work which he was under contract to do without compensation. In the specifications for this work, after describing how “clearing” is to be done by the contractor, it is said, division 2, section 4:

“Basis of payment — If the contract contains a separate estimate and unit price for ‘clearing,’ the contract unit price per acre shall be payment in full for all work specified in this section. Otherwise, the contract price for earth excavation shall be considered as including payment for the item of clearing. ’ ’

A like provision is made as a basis for payment of grubbing, trimming for acceptance, etc. The plaintiffs made their subcontract to do the work in accordance with these specifications. They knew there were some parts of the work which the highway commissioner considered as incident to excavation and for which contractors received no compensation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bolt v. Nelson
248 N.W. 581 (Michigan Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
241 N.W. 896, 257 Mich. 610, 1932 Mich. LEXIS 882, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bolt-v-nelson-mich-1932.