Bollinger Shipyards Lockport, LLC v. Certain Underwriters at Lloyd's

98 F. App'x 311
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 7, 2004
DocketM 03-30697
StatusUnpublished

This text of 98 F. App'x 311 (Bollinger Shipyards Lockport, LLC v. Certain Underwriters at Lloyd's) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bollinger Shipyards Lockport, LLC v. Certain Underwriters at Lloyd's, 98 F. App'x 311 (5th Cir. 2004).

Opinion

JERRY E. SMITH, Circuit Judge. *

Bollinger Shipyards Lockport, L.L.C. (“Bollinger”), a party in the district court but not a combatant in this appeal, was contracted by the Army to build cargo barges. Bollinger sub-contracted Am-Clyde Engineered Products, Inc. (“Am-Clyde”), to fabricate and install a cargo crane on one of those barges, the D/B SPRINGFIELD.

Pursuant to the subcontract, AmClyde named Bollinger as an Assured under its Builder’s All Risk Policy, with appropriate remuneration to be paid to the insurer, Certain Underwriters at Lloyd’s, London and/or Institute Companies (“Lloyd’s”). Coverage also was extended under a Commercial General Liability (“CGL”) policy issued by Lloyd’s.

Bollinger handed over the SPRINGFIELD to AmClyde, which duly installed the crane on the barge at its facility in Slidell, Louisiana. Possession of the barge then was returned to Bollinger, which contracted for tugboats to transport it to Newport News, Virginia, for delivery to the Army.

The crane and its associated operator’s house snapped off the barge during transit and fell overboard. The accident apparently did not result in damage to the barge, apart from the $1.2 million loss of *313 the crane itself. Boston Old Colony Insurance Company (“Boston Old Colony”), with which Bollinger had contracted specifically to insure the trip, was left responsible for payment to Bollinger to the extent of $900,000.

Bollinger and Boston Old Colony sued Lloyd’s, alleging that the Builder’s All-Risk Policy and CGL policy required that Lloyd’s cover the loss. On Lloyd’s’ motion for summary judgment, the district court found that the losses fell outside the coverage of the Builder’s All Risk Policy and the CGL policy. The district court accordingly dismissed all claims of Bollinger and Boston Old Colony against Lloyd’s. Only Boston Old Colony appeals.

I.

We review the district court’s legal conclusions, including its interpretation of contracts, de novo. Taita Chem. Co. v. Westlake Styrene Corp., 246 F.3d 377, 385 (5th Cir.2001); Nolan v. Golden Rule Ins. Co., 171 F.3d 990, 992 (5th Cir.1999). In reviewing a summary judgment, we view any reasonably disputable facts in the light most favorable to the non-moving party, in this case Boston Old Colony.

The insurance policies are governed by Louisiana law, under which we utilize the general rules of contract interpretation, requiring determination of the common intent of the parties. See Thermo Terratech v. GDC Enviro-Solutions, Inc., 265 F.3d 329, 334 (5th Cir.2001). The intent of the parties as reflected in the words of the policy determines the proper extent of its coverage. Id.

The first question is whether the Builder’s All-Risk Policy extended coverage to the loss of the crane. That policy is a one-size-fits-all document, intended to apply to the numerous projects AmClyde might pursue. AmClyde could pay Lloyd’s to have additional projects covered by the policy, with its clients named as “additional assureds.” Its provisions, then, were not specially crafted to reflect the tasks associated with the installation of the crane on the SPRINGFIELD, but instead were of a more general nature.

Among the Builder’s All-Risk Policy’s provisions was the following:

Insurance hereunder in respect to each part, item, or portion of the subject matter(s) of this insurance shall attach from the time of beginning at the risk of an Assured where that insurance becomes the responsibility of the named Assured and continued thereafter until completion of the entire project under the contract(s) or agreement(s), and acceptance by client and/or customer and/or as per contract(s), or agreements).

(Emphasis added.) In other words, the coverage ended when the “entire project” was completed.

Lloyd’s argues that the entire project was completed with the return of the SPRINGFIELD to Bollinger and before the loss of the crane during the delivery trip. Boston Old Colony contends that “entire project” should be read to refer not to AmClyde’s whole contract work for Bollinger, but rather to the work to be done under the entire prime contract. Under Boston Old Colony’s view, coverage under the Builder’s All-Risk Policy would have ceased only when the Army accepted the SPRINGFIELD and only after the loss of the crane.

The district court, reasoning that the Builder’s All-Risk Policy should be read in the factual context of the subcontract that required its application, concluded that the “entire project” language referred only to the work done under the AmClyde subcontract. The court noted especially that the subcontract provided that risk of loss was *314 intended to shift from AmClyde to Bollinger on return of the barge to the latter. The subcontract stated:

SUPPLIER [AmClyde] shall provide Builder’s All Risk Insurance for 100% replacement cost for all PURCHASER [Bollinger] supplied equipment while said equipment is in the possession of SUPPLIER [AmClyde]. Risk of loss shall pass on delivery of this LSB-18 Crane to PURCHASER [Bollinger].

The parties thus contemplated that the insurance yet to be provided by Am-Clyde would lapse after the SPRINGFIELD was returned to Bollinger. It is in light of these circumstances that the district court interpreted the contract’s “entire project” language to mean only the work performed under the subcontract.

Boston objects to the district court’s reference to the subcontract in interpreting the Builder’s All Risk Policy. As Boston Old Colony correctly notes, the language of the subcontract cannot overwhelm or defeat the plain language of the insurance contract. See Saavedra v. Murphy Oil USA Inc., 930 F.2d 1104, 1110 (5th Cir. 1991). But the district court did not act improperly by looking to the circumstances surrounding the inclusion of Bollinger as an additional assured under the Builder’s All Risk Policy. Indeed, it is impossible to interpret the policy in any fashion without looking to surrounding circumstances, for its terms are almost wholly generic.

Further, the existence and nature of the subcontract are among the most important circumstances relevant to the interpretation of the policy. It was no error for the district court to look to the subcontract in concluding that the likely meaning of “entire project” under the policy was limited to the completion of work under the subcontract. The court’s reference to other circumstances surrounding the policy, such as its price and the typical extent of builder’s all risk policies as a species, was likewise appropriate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
98 F. App'x 311, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bollinger-shipyards-lockport-llc-v-certain-underwriters-at-lloyds-ca5-2004.