Boise Tower Associates, LLC v. Hogland

215 P.3d 494, 147 Idaho 774, 2009 Ida. LEXIS 141
CourtIdaho Supreme Court
DecidedAugust 24, 2009
Docket34333
StatusPublished
Cited by38 cases

This text of 215 P.3d 494 (Boise Tower Associates, LLC v. Hogland) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boise Tower Associates, LLC v. Hogland, 215 P.3d 494, 147 Idaho 774, 2009 Ida. LEXIS 141 (Idaho 2009).

Opinion

W. JONES, Justice.

NATURE OF CASE

This appeal arises out of a failed condominium tower project that Boise Tower Associates (BTA) intended to build in downtown Boise, Idaho. BTA filed a lawsuit against Timothy Hogland (Hogland) and the City of Boise, alleging constitutional violations and other causes of action stemming from the *777 mistaken miscalculation of BTA’s building permit expiration date. The district court granted summary judgment in favor of Hog-land and the City of Boise. BTA brought this appeal. We affirm in part and remand for further proceedings.

FACTS AND PROCEDURAL BACKGROUND

The facts of this case are largely undisputed by the parties. On November 27, 1998, BTA submitted an application to the Boise Planning and Development Services Department (PDS) for a building permit to construct the Boise Tower Project (the Project). Hogland, Director of PDS, approved BTA’s application and issued the permit on May 3, 2000.

Under the applicable building regulations found in the 1994 Uniform Building Code (UBC), the permit would expire if work authorized by such permit was suspended or abandoned for a period of 180 days. For two years minimal work was performed on the Project. The last date that work was performed was on May 15, 2002, when concrete was poured for the foundation. Accordingly, BTA’s permit was set to expire on November 11, 2002, which would have been 180 days after the last day work was performed on the Project. However, PDS’s records incorrectly indicated that May 3, 2002 was the last date that BTA had performed work on the Project. According to PDS, the permit was therefore set to expire on November 3, 2002.

On November 7, 2002, Hogland received a letter from M.A. Mortenson, BTA’s construction contractor, notifying PDS that work would commence that day. Under the mistaken notion that the permit expired on November 3, 2002, an inspector for the City of Boise issued a stop-work order to BTA and notified it that the site was to remain as-is until Hogland could meet with BTA and agree on a course of action.

On November 13, 2002, Hogland met with representatives from BTA and Mortensen to discuss a course of action. Rick Peterson (Peterson), the managing member of BTA, tried to convince Hogland that the permit had not yet expired, but Peterson did not provide Hogland with any supporting evidence that BTA had worked on the Project on May 15, 2002. At that meeting, Hogland told BTA that to move forward and continue work under the permit BTA would have to enter into a written stipulation agreement. One condition of the stipulation agreement required BTA to provide a letter from a lending institution indicating a commitment of full financing within 60 days from the date of the agreement or the permit would be deemed expired.

BTA alleges that Hogland told Peterson if BTA did not sign the stipulation agreement that day, Hogland would tell the Boise City Council at their meeting that night that BTA’s permit had expired. Peterson protested, arguing that his attorney advised him not to sign the stipulation agreement. However, BTA believed that if Hogland publicly announced that the permit was expired, it would jeopardize financing and lead to the demise of the Project. On November 15, 2002, Hogland received a letter from BTA stating that Peterson had signed the stipulation agreement. Thereafter, Peterson and his attorney suggested revisions to the agreement. The agreement was revised and signed again by Peterson and Hogland on November 19, 2002.

BTA did not satisfy the stipulation agreement condition requiring it to provide a commitment letter within the agreed-upon 60 day time period. Hogland agreed to grant an extension to BTA. On January 22, 2003, the parties entered into an addendum to the stipulation agreement, which extended the time by which BTA was required to provide a commitment letter to February 4, 2003. BTA failed to provide a commitment letter to Hogland by that date.

On February 11, 2003, Hogland notified BTA that its permit had expired because BTA failed to meet its obligations under the stipulation agreement and addendum. BTA requested a hearing on the matter and Hog-land allegedly denied the request.

On February 19, 2003, BTA sent a letter to Hogland and the City of Boise, requesting an appeal to the Board of Appeals pursuant to Boise Municipal Code § 4-02-05 and UBC § 105.1. The letter stated that in the event *778 the Board of Appeals did not have jurisdiction to hear the matter, the letter was to be considered notice that BTA was appealing to the City Council. The record reflects that the Board of Appeals did not hear the matter, although it is unclear why that procedure was not followed. Rather, a hearing on the matter was conducted before the City Council on April 1, 2003. At that hearing, BTA was represented by counsel and was allowed to present testimony and offer evidence. After the City Council heard BTA’s evidence, it found that Hogland mistakenly calculated BTA’s permit expiration date. The City Council reinstated BTA’s permit on April 9, 2003.

BTA filed a complaint against Hogland and the City of Boise on November 2, 2004, claiming that negative publicity from the miscalculation of the expiration date of the building permit led to cancellation of a number of pre-sale condominium purchase agreements and caused the withdrawal of financing commitments, ultimately leading to the Project’s failure. BTA brought various causes of action, including in relevant part: (1) intentional interference with contract and intentional interference with prospective economic gain, (2) vicarious liability of the City of Boise for Hogland’s tortious actions, (3) violation of 42 U.S.C. § 1983 by Hogland and the City of Boise, (4) a regulatory taking without just compensation by the City of Boise in violation of the Fifth and Fourteenth Amendments to the United States Constitution and Article 1, Sections 13 and 14 of the Idaho Constitution, and (5) violation of BTA’s procedural due process rights under the Fifth and Fourteenth Amendments to the United States Constitution and Article 1, Section 13 of the Idaho Constitution.

Hogland and the City of Boise filed an answer, raising various affirmative defenses, including that “some or all [state law] claims are either barred or limited by the Idaho Tort Claims Act.” The record is unclear whether BTA complied with the notice provisions of the Idaho Tort Claims Act.

During the course of preparing for litigation, Hogland stated in an affidavit that he was “concerned about the safety of the BTA construction site because it was an open pit in the middle of downtown Boise.” He stated that he issued the stop-work order because he believed BTA’s permit had expired and his actions “were intended to address what [he] believed to be the significant risk to the public and adjacent buildings of the site, given the width and depth of the excavated pit and exposed reinforcing bar, foundation, and concrete columns.”

The parties filed cross-motions for summary judgment. The district court granted summary judgment on BTA’s § 1983 claim in favor of the City of Boise, finding that it was immune from suit, and Hogland, finding that he was entitled to qualified immunity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Van Orden v. Van Orden
515 P.3d 233 (Idaho Supreme Court, 2022)
State v. Ahmed
492 P.3d 1110 (Idaho Supreme Court, 2021)
Ayala v. Meyers Farms
Idaho Supreme Court, 2019
Ayala v. Robert J. Meyers Farms, Inc.
445 P.3d 164 (Idaho Supreme Court, 2019)
T3 Enters., Inc. v. Safeguard Bus. Sys., Inc.
435 P.3d 518 (Idaho Supreme Court, 2019)
Smith v. Smith (In Re Estate of Smith)
432 P.3d 6 (Idaho Supreme Court, 2018)
Smith v. Smith
Idaho Supreme Court, 2018
Nielson v. Talbot
Idaho Supreme Court, 2018
William R. Fischer v. James F. Croston
413 P.3d 731 (Idaho Supreme Court, 2018)
Forbush v. Sagecrest Multi Family Property Owners' Ass'n
396 P.3d 1199 (Idaho Supreme Court, 2017)
Melinda Deiter v. Donald Coons
394 P.3d 87 (Idaho Supreme Court, 2017)
Gugino v. Rowley (In re Floyd)
540 B.R. 747 (D. Idaho, 2015)
Mack Phillips v. Montgomery County, Tennessee
442 S.W.3d 233 (Tennessee Supreme Court, 2014)
State v. Dennis Ray Smith, Jr.
Idaho Court of Appeals, 2012
Victor Klingonsmith v. State
Idaho Court of Appeals, 2012
Idaho Development, LLC v. Teton View Golf Estates, LLC
272 P.3d 373 (Idaho Supreme Court, 2011)
TWO JINN, INC. v. District Court
249 P.3d 840 (Idaho Supreme Court, 2011)
Sirius LC v. Erickson Ex Rel. Erickson
244 P.3d 224 (Idaho Supreme Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
215 P.3d 494, 147 Idaho 774, 2009 Ida. LEXIS 141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boise-tower-associates-llc-v-hogland-idaho-2009.