Boh Bros. Const. v. DOTD

698 So. 2d 675, 1997 WL 435027
CourtLouisiana Court of Appeal
DecidedJuly 14, 1997
Docket97 CA 0168
StatusPublished
Cited by16 cases

This text of 698 So. 2d 675 (Boh Bros. Const. v. DOTD) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boh Bros. Const. v. DOTD, 698 So. 2d 675, 1997 WL 435027 (La. Ct. App. 1997).

Opinion

698 So.2d 675 (1997)

BOH BROS. CONSTRUCTION CO., L.L.C.
v.
DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT, Frank Denton and Roddy Dillon.

No. 97 CA 0168.

Court of Appeal of Louisiana, First Circuit.

July 14, 1997.

W.P. Wray, Jr., Baton Rouge, for Plaintiff-Appellant Boh Bros. Construction.

*676 Lawrence A. Durant, Baton Rouge, for Defendant-Appellee Dept. of Transportation and Development, et al.

H. Bruce Shreves and Denise C. Puente, New Orleans, for Intervenor-Appellee Barriere Construction Co., Inc.

Before LOTTINGER, C.J., and SHORTESS, FOIL, FOGG and CHIASSON,[*] JJ.

FOIL, Judge.

This appeal challenges a trial court's determination that the Louisiana Department of Transportation and Development did not violate the Public Bid Law in awarding three contracts to the lowest numerical bidder. After a thorough review of the record, we affirm.

BACKGROUND

On July 31, 1996, the State of Louisiana, Department of Transportation and Development (DOTD) advertised for bids on numerous public works contracts involving major highway overlay projects. The three contracts at dispute in this litigation are State Project Nos. XXX-XX-XXXX, XXX-XX-XXXX and XXX-XX-XXXX. The bid advertisement stated that bids must be submitted on the proposal forms provided by DOTD, must be prepared in accordance with Section 102 of the 1992 Louisiana Standard Specifications for Roads and Bridges and must include all information required by the proposal. It stated further that the bid shall include a proposal guaranty in an amount not less than specified in the advertisement.

On August 28, 1996, DOTD received bids on all three of the projects from Boh Brothers Construction Co., L.L.C. and Barriere Construction Company. Barriere's bids of $2,349,234.20 on SP-0099, $2,705,937.96 on SP-0038 and $138,039.05 on SP-0012 were the lowest bids submitted to DOTD. Boh Bros. bid $2,462,701.38 on SP-0099; $3,047,987.96 on SP-0038 and $145,661.44 on SP-0012.

All three of Barriere's bids were initially stamped "irregular" by DOTD. On SP-0099, two irregularities were cited in the proposal check list: (1) the bond was not for the amount specified in the proposal and (2) the Equal Employment Opportunity Certification Statement (EEO Statement) was incorrectly filled out. The advertisement for bids originally called for a $107,000.00 proposal guaranty, but by virtue of an addendum which increased the estimated cost on the project, this amount was changed to $108,000.00. Barriere's bid on this project contained a $107,000.00 proposal guaranty. The other two bids were stamped irregular for not having a correctly filled out EEO Statement; the proposal guaranty in these two bids matched the bond amount specified in the advertisements.

In a low bid analysis, Robert Pierce, Chairman of the DOTD Bid Review Committee, recommended that the contracts be awarded to Boh Bros. The recommendation was endorsed by Chief Engineer Roddy Dillon, and later approved by Secretary Frank Denton.

Barriere challenged DOTD's irregularity determination, charging that it simply made a mistake in filling out the EEO Statement, and pointed out that as part of the same bid letting, it submitted a bid on another state project which contained a correctly filled out EEO Statement. Barriere stressed that since 1984, it completed at least 12 federal aid projects for DOTD and filed the requisite EEO Statements therein. Therefore, Barriere urged, since DOTD had the properly filled out certifications on file, the error in filling out the forms on the three projects should have no bearing on the validity of its bids.

Thereafter, DOTD determined that its initial ruling that Barriere's bids were irregular was made in error, and it recognized Barriere as the lowest responsible bidder on the three contracts. DOTD found that the error in filling out the EEO Statement did not go to the substance of the bid, and concluded that the fact that Barriere's bid on SP-0099 contained a $1,000.00 less bid bond than required was not a substantive deviation from the bid because the bid advertisement initially *677 contained a proposal guaranty of $107,000.00, the precise amount of Barriere's proposal guaranty on the SP-0099 bid.

On October 7, 1996, Boh Bros. filed this lawsuit, seeking injunctive relief in the trial court to prevent DOTD from awarding the contracts to Barriere. It also sought a mandamus ordering DOTD to award the contracts to it as the lowest responsible bidder.

The trial court denied the request for a preliminary injunction, finding that the irregularities in the EEO Statement were errors of form which DOTD could legally waive. The court also ruled that the $1,000.00 discrepancy in the bid bond on SP-0099 was insubstantial and this deficiency could be waived by DOTD. Noting that the deficiencies in Barriere's bids were insignificant coupled with the fact that Boh Bros.' bid was over half a million dollars higher than Barriere's, the court believed that DOTD did not act arbitrarily or otherwise favorably in accepting Barriere's bid as the lowest responsive bid despite its insignificant irregularities.

Boh Bros. appealed, challenging as a matter of law the power of DOTD to waive insignificant irregularities in bids on public works projects.

MOTION TO DISMISS THE APPEAL AS MOOT

During the course of this appeal, DOTD filed a motion to dismiss Boh Bros.' appeal, offering proof that all three disputed projects have been substantially completed. DOTD contends that the injunctive relief prayed for by Boh Bros. is no longer available as a remedy due to the completion of the projects. It also points out that Boh Bros. did not specifically ask for damages in its petition, and because the only relief sought is no longer available, this court should dismiss the appeal as moot.

It is true that Boh Bros. did not request damages in its petition. It did, however, request a declaration that DOTD violated the Public Bid Law and sought the relief available to it at that time: to enjoin DOTD from entering into the contract with Barriere. In public bid cases, our courts have recognized the dilemma created when an unsuccessful bidder files a timely application for injunctive relief which is denied by the trial court, and during the appeal delays, the project is substantially completed, resulting in the unavailability of injunctive relief. See Airline Construction Company, Inc. v. Ascension Parish School Board, 568 So.2d 1029 (La.1990).

In Stafford Construction Company, Inc. v. Terrebonne Parish School Board, 612 So.2d 847 (La.App. 1st Cir.1992), writ denied, 614 So.2d 82 (La.1993), this court held that an aggrieved bidder on a public works project who has timely filed a suit for injunctive relief may recover damages against a public entity. Thus, even though Boh Bros. may not be entitled to injunctive relief at this time due to the substantial completion of the project, because it timely sought injunctive relief, its remedy would convert to a cause of action for damages against the public entity. Therefore, the underlying legal issue in this case, that is, whether DOTD violated the Public Bid Law in awarding the contract to Barriere, is not mooted by the unavailability of injunctive relief. Accordingly, DOTD's motion to dismiss the appeal is denied.

POWER OF DOTD TO WAIVE IRREGULARITIES IN BIDS

We now turn to the merits of the challenged action, namely, whether the trial court erred in finding that DOTD did not violate the Public Bid Law in determining that Barriere was the lowest responsible bidder on the three contracts in dispute. Boh Bros.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

An Erny Girl, L.L.C. v. BCNO 4 L.L.C.
216 So. 3d 833 (Louisiana Court of Appeal, 2017)
Wiseman Construction Co. v. Maynard C. Smith Construction Co.
779 S.E.2d 893 (West Virginia Supreme Court, 2015)
Benitez v. TRULY NOLAN OF AMERICA
7 So. 3d 656 (District Court of Appeal of Florida, 2009)
HAMP'S CONST. v. City of New Orleans
924 So. 2d 104 (Supreme Court of Louisiana, 2006)
Broadmoor, LLC v. ERNEST N. MORIAL EXHIBITION
867 So. 2d 651 (Supreme Court of Louisiana, 2004)
Broadmoor v. Ernest N. Morial Authority
865 So. 2d 136 (Louisiana Court of Appeal, 2003)
Opinion Number
Louisiana Attorney General Reports, 2003
Mickey O'Connor General Contractor, Inc. v. City of Westwego
804 So. 2d 128 (Louisiana Court of Appeal, 2001)
Wallace C. Drennan, Inc. v. Sewerage & Water Bd.
798 So. 2d 1167 (Louisiana Court of Appeal, 2001)
Barriere Const. v. Terrebonne Consol. Gvt.
754 So. 2d 1123 (Louisiana Court of Appeal, 2000)
State MacH. Sales v. Gravity Drainage 5
742 So. 2d 26 (Louisiana Court of Appeal, 1999)
MERRITT McDONALD v. PARISH OF EAST BATON
742 So. 2d 564 (Louisiana Court of Appeal, 1999)
D'Arbonne Construction Co. v. Union Parish Police Jury
736 So. 2d 981 (Louisiana Court of Appeal, 1999)
Hebert Bros. Engineers v. Department of Transportation & Development
744 So. 2d 40 (Louisiana Court of Appeal, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
698 So. 2d 675, 1997 WL 435027, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boh-bros-const-v-dotd-lactapp-1997.