Bogner Constr. Co. v. Field Assoc., 08 Ca 11 (1-13-2009)

2009 Ohio 116
CourtOhio Court of Appeals
DecidedJanuary 13, 2009
DocketNo. 08 CA 11.
StatusPublished
Cited by6 cases

This text of 2009 Ohio 116 (Bogner Constr. Co. v. Field Assoc., 08 Ca 11 (1-13-2009)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bogner Constr. Co. v. Field Assoc., 08 Ca 11 (1-13-2009), 2009 Ohio 116 (Ohio Ct. App. 2009).

Opinion

OPINION *Page 2
{¶ 1} Plaintiffs-Appellants Bogner Construction Company and Westfield Insurance Company appeal the February 28, 2008, decision of the Knox County Court of Common Pleas granting summary judgment in favor of Defendant-Appellee United States Fidelity Guaranty Company.

STATEMENT OF THE FACTS AND CASE
{¶ 2} The relevant facts are as follows:

{¶ 3} On September 6, 1994, Bogner Construction Company ("Bogner") entered into a written construction contract (the "Contract") with the School District for the City of Mount Vernon (the "School Board") to serve as the general contractor for the construction of the Mount Vernon Middle School (the "Middle School"). Bogner was required to furnish all the material, supplies, tools, equipment, and labor necessary for the completion of the Middle School.

{¶ 4} As set forth in the Contract, Bogner agreed to construct, among other things, a standing seam metal roof system, together with all required flashing, insulation and other related items (the "Roof Project"). The Roof Project included the gymnasium roof ("Gym Roof) and the roof for the main portion of the building ("Main Roof").

{¶ 5} As the general contractor, Bogner subcontracted the Roof Project to Defendant Field Associates, Inc. ("Field"), through a contract dated October 28, 1994.

{¶ 6} Field worked on the Project Roof in 1995, completing most of the Gym Roof and portions of the Main Roof in 1995. The roof was completed in June, 1996. Allegedly, leaks persisted ever since the completion of the Roof Project. *Page 3

{¶ 7} On or about November 1, 2004, the School Board filed an Arbitration Demand against Bogner and Bogner's bonding company, Ohio Farmers Insurance Company ("Ohio Farmers"), in the arbitration captionedMount Vernon City School District v. Bogner Construction Company, etal ., American Arbitration Association, Case No. 53 110Y0072504 (the "Arbitration"). In the Arbitration, the School Board asserted breach of contract claims against Bogner based on the deficiencies and defects in the construction of the Roof Project and against Ohio Farmers based on the performance bond. Specifically, the School Board asserted claims for breach of contract arising from Bogner's failure to construct and deliver a roof that conformed to the specifications in the construction projects. In its arbitration claims, the School Board alleged, among other things, that the roof leaked in 1995, causing property damage to occur not only to the Project Roof, but also to tangible property other than the roof itself-property which was purchased by the School Board, including ceiling tiles, plastic laminate casework, and other fixtures and furnishings.

{¶ 8} Upon learning of the arbitration claim, on or about November 1, 2004, Bogner notified its insurance carriers, Westfield Insurance Company ("Westfield") and United States Fidelity Guaranty Company ("USFG") demanding that its insurers provide indemnification and defense against the School Board's claims. The comprehensive general liability ("CGL") policy issued by USFG to Bogner provided coverage from January 1, 1995 to January 1, 1996, while Westfield's coverage period ran from January 1, 1996 to January 1, 1997.

{¶ 9} By letter dated September 6, 2005, St. Paul Travelers, on behalf of USFG, notified Bogner in writing that it was denying coverage on the School Board's *Page 4 claims. Specifically, USFG stated that it was denying coverage because, among other things, Bogner had sought coverage for property damage that occurred outside the coverage period, and that the USFG Policy excluded coverage for property damage to property on which Bogner was performing operations.

{¶ 10} On or about November 7, 2005, the School Board, Bogner, and Westfield entered into a settlement agreement, thereby settling the claims in the Arbitration. Under the terms of the settlement agreement, the School Board agreed to release Bogner from all claims in exchange for the payment of $1,016,604.82. Based upon the settlement, Westfield has subrogated to certain of Bogner's rights.

{¶ 11} In the instant case, Bogner and Westfield have asserted claims against USFG for breach of contract. Bogner has asserted an additional claim of bad faith based upon USFG's refusal to indemnify and defend Bogner against the claims in the Arbitration.

{¶ 12} During the course of the litigation, an agreed order was entered by the trial court severing the claims against Field and Ohio Farmers from the claims against USFG for trial purposes.

{¶ 13} On June 12, 2007, USFG filed a motion for leave to file its summary judgment motion instanter.

{¶ 14} On June 15, 2007, the trial court granted USFG's motion for leave to file its Motion for Summary Judgment.

{¶ 15} On July 31, 2007, a jury trial commenced on the claims against Field and Ohio Farmers. Those claims were settled on the second day of the jury trial. Because *Page 5 the claims against USFG were severed for trial purposes, USFG did not participate in the trial.

{¶ 16} On August 30, 2007, after receiving an extension of time to file a response so that Plaintiffs-Appellants could depose USFG's claims adjuster, Plaintiffs-Appellants filed their Response to USFG's Motion for Summary Judgment. USFG filed a Reply in Support of its Motion for Summary Judgment, and Plaintiffs-Appellants filed a Surreply.

{¶ 17} By Judgment Entry filed February 28, 2008, the trial court granted United States Fidelity Guaranty Company's motion for summary judgment.

{¶ 18} Appellants now appeal, assigning the following error for review:

ASSIGNMENT OF ERROR
{¶ 19} "I. THE TRIAL COURT ERRED IN GRANTING DEFENDANT UNITED STATES FIDELITY GUARANTY COMPANY'S MOTION FOR SUMMARY JUDGMENT."

"Summary Judgment Standard"
{¶ 20} Summary judgment proceedings present the appellate court with the unique opportunity of reviewing the evidence in the same manner as the trial court. Smiddy v. The Wedding Party, Inc. (1987),30 Ohio St.3d 35, 36. Civ. R. 56(C) provides, in pertinent part:

{¶ 21} "Summary judgment shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, written admissions, affidavits, transcripts of evidence in the pending case, and written stipulations of fact, if any, timely filed in the action, show that there is no genuine issue as to any material fact and that the moving *Page 6 party is entitled to judgment as a matter of law. * * * A summary judgment shall not be rendered unless it appears from such evidence or stipulation and only therefrom, that reasonable minds can come to but one conclusion and that conclusion is adverse to the party against whom the motion for summary judgment is made, such party being entitled to have the evidence or stipulation construed most strongly in his favor."

{¶ 22}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westfield Insurance v. Custom Agri Systems, Inc.
2012 Ohio 4712 (Ohio Supreme Court, 2012)
Myers v. United Ohio Ins. Co.
2012 Ohio 340 (Ohio Court of Appeals, 2012)
Cincinnati Ins. Co. v. Dorsey Reconditioning, Inc.
2011 Ohio 1499 (Ohio Court of Appeals, 2011)
JTO, Inc. v. State Automobile Mutual Insurance
956 N.E.2d 328 (Ohio Court of Appeals, 2011)
Auto Owners Mutual Ins. Co. v. Kendrick, 08-Coa-028 (5-4-2009)
2009 Ohio 2169 (Ohio Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2009 Ohio 116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bogner-constr-co-v-field-assoc-08-ca-11-1-13-2009-ohioctapp-2009.