Boger Contracting Corp. v. Board of Commissioners

396 N.E.2d 1054, 60 Ohio App. 2d 195, 14 Ohio Op. 3d 176, 1978 Ohio App. LEXIS 7628
CourtOhio Court of Appeals
DecidedAugust 24, 1978
DocketCA-4920
StatusPublished
Cited by7 cases

This text of 396 N.E.2d 1054 (Boger Contracting Corp. v. Board of Commissioners) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boger Contracting Corp. v. Board of Commissioners, 396 N.E.2d 1054, 60 Ohio App. 2d 195, 14 Ohio Op. 3d 176, 1978 Ohio App. LEXIS 7628 (Ohio Ct. App. 1978).

Opinion

Dowd, J.

This appeal presents the issue of what procedure must be followed to comply with the requirements for competitive bidding for the construction of a county sanitary sewer project where the board of commissioners modifies the plans and specifications for the project after the required statutory notice has been published and such a modification was prior to the opening of the bid proposals.

The undisputed 2 facts which present the issue follow.

*196 On March 15,1977, the Stark County Board of Commissioners (hereafter referred to as Commissioners) approved plans and specifications for Sanitary Sewer Project 405. The plans and specifications, as approved, did not indicate the time in which the work was to be completed. To the contrary, the original plans and specifications and the bid proposal form clearly indicate that the bidder was to specify the number of days he would take to complete the work of the project and that he would be bound by such bid and required to pay liquidated damages in the sum of $500 for each day of delay in completion beyond the number of days stated in his proposal.

On November 19,1977, and November 26,1977, and pursuant to R. C. 307.86 and R. C. 307.87, the Commissioners advertised for competitive bids on Sewer Project 405 in the Canton Repository, a newspaper of general circulation in Stark County. The advertisement was silent with respect to a completion date or time in which to complete the contract. The published notice declared:

“ * * * Plans, specifications and proposal forms may be obtained at, ordered from, the office of the Stark County Engineer, County Office Building, Canton, Ohio, 44702. A non-refundable cash deposit of Forty Dollars ($40.00) will be required in advance for each set of plans and specifications taken from the above office.***”

On November 27, 1977, the Commissioners adopted a resolution providing for an addendum to the plans and specifications. The addendum called for a completion time of 180 days.

On December 7, 1977, Dale Hoagland of the plaintiff Boger Contracting Corporation (hereafter referred to as Boger) picked up the booklet of plans and specifications including the bid proposal forms at the office of the Stark County Sanitary Engineer.

On December 20, 1977, Boger submitted a bid for Sewer Project 405. Three other contractors submitted bids and they were opened on December 20,1977, at 10 a.m. Boger’s bid to do the work for $589,578.30 was the low bid. Boger’s bid also declared that the completion time would be 360 days.

J. K. Boger, president of Boger, wrote the following two letters to the Board of Commissioners on December 20,1977, *197 and December 21, 1977. The texts of the two letters follow:

“December 20, 1977
“Stark County Commissioners
Virgil Musser
Robert Schirack
Norman Sponseller
County Office Building
Canton, Ohio 44702
Ref: Stark County
Project 405 Bids.
“We were advised by a County Commissioner late this afternoon that an addendum limiting construction time to 180 days had been mailed to prospective bidders on Project 405.
“We were the low bidder on Project 405, but did not receive the preported (sic) addendum. This letter is to inform you we are prepared to accept this project with the 180 day limit or as called in the addendum.
“Very truly yours,
Isi John K. Boger
J. K. Boger
President.”
“December 21, 1977
“Stark County Commissioners
Virgil Musser
Robert Schirack
Norman Sponseller
County Office Building
Canton, Ohio 44702
“Ref: Project 405
and Letter of 12-20-77
“We have now been advised that the preported [sic] addendum limiting the contract time on Project 405 to 180 days was included with specification picked up for bidding after December 1, 1977. This addendum was not in the specifica *198 tion we received and submitted. We are still prepared to complete the project with the 180 day limit at the same contract price.
“Very truly yoUrs,
Is/ John K, Boger
J. E. Boger
President.”

On February 16, 1978, the Commissioners adopted a resolution awarding the contract for the construction of Sewer Project 405 to the Crano Construction Company for its bid price of $599,509.70. In the resolution declaring the bid of Crano Construction Company to be the lowest and best bid, the Commissioners declared that the bid of Boger contained a completion date beyond that required in the addendum to the specifications and thus was not in compliance with the specifications for Project 405 and could not be considered for the award.

On February 24, 1978, Boger filed an action in the Common Pleas Court of Stark County against the Commissioners, Crano Construction Company, and others. The case proceeded to trial on Boger’s amended complaint with a prayer for relief including a judicial declaration that the bidding be declared null and void and any contracts awarded pursuant thereto be declared null and void and that the project be resubmitted for advertising and bidding. It is with respect to this portion of Boger’s prayer for relief in its amended complaint that the plaintiff now prosecutes its appeal.

The principal claim of Boger on appeal is that the judgment of the Common Pleas Court of Stark County, to the effect that the Commissioners complied with the competitive bidding requirements in awarding the construction contract for Project 405 to Crano Construction Company, is contrary to law.

The overriding purpose of the legislature in compelling mandatory competitive bidding by public bodies for major construction projects such as the project at hand is to protect the taxpayer and the users of the system against excessive costs and corrupt practices.

*199 By the provisions of R. C. 307.90 and R. C. 6117.27, county commissioners are granted the right to award contracts for sewer construction projects to the lowest and best bidder in recognition of the fact that the lowest dollar bid might not in every instance be the best bid. State, ex rel. Roger J. Au & Son, Inc. v. Studebaker

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
396 N.E.2d 1054, 60 Ohio App. 2d 195, 14 Ohio Op. 3d 176, 1978 Ohio App. LEXIS 7628, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boger-contracting-corp-v-board-of-commissioners-ohioctapp-1978.