Bogardus v. Phœnix Manufacturing Co.

134 Ill. App. 456, 1907 Ill. App. LEXIS 413
Appellate Court of Illinois·Decided June 1, 1907·Published·Cited by 1 cases

Opinion

Mb. Presiding Justice Ramsay

delivered the opinion of the court.

The Phoenix Manufacturing Company instituted suit against Charles Bogardus in the Circuit Court of Ford county, to recover upon a guaranty in writing, executed by said Bogardus, by the terms of which it is claimed he obligated himself to' pay notes made by one Neils C. Neilson to said Phoenix Manufacturing Co., upon default therein by Neilson. Demurrer was interposed by Bogardus to an amended declaration, which was overruled. Bogardus elected to abide by his demurrer, whereupon the trial court rendered judgment against him in the sum of $2,245.05, from which he has prosecuted ah appeal.

The written guaranty upon which appellant’s liability is asserted is set forth in full in Bogardus v. Phoenix Manufacturing Co., 120 Ill. App. 46, and, therefore, need not be here repeated. The declaration then under consideration was held to be defective, the judgment reversed and the cause remanded. The question now presented is whether or not the amended declaration, herein involved, states such a cause of action that the judgment upon it should be sustained.

In such amended declaration it is alleged, in substance, that appellee, on the tenth day of October, 1901, proposed in writing, through its salesman, A. E. White, to furnish to one Neils C. Neilson, of Pellston, Michigan, certain saw mill machinery, a part to be delivered f. o. b. at Indianapolis, Indiana, a part f. o. b. Eau Claire, Wisconsin, and the remainder, f. o. b. Chicago, Illinois, all to be shipped oh or before November 1, 1901, to said Charles Bogardus, appellant, Pellston, Michigan, for the stun of $2,620, payable in New York, Chicago or Milwaukee exchange, free of expense to appellee, one-third to be due in twelve months, one-third in eighteen months and the balance in twenty-four months from date of shipment, to be witnessed by the notes of said Neilson in equal amounts bearing six per cent, interest; that this proposition was accepted by said Neilson on the eleventh day of October, 1901; that in consideration that appellee would approve said proposition and furnish such machinery as proposed by said salesman and would accept the notes of Neilson therefor, the said appellant executed and delivered to appellee the written guarantee hereinbefore referred to, agreeing that if said Neilson should fail to make the payments provided for in said notes, he, appellant, would be responsible therefor to appellee ; that in consideration of such guaranty so made by appellant, appellee on the 12th day of October, 1901, approved of the sale and entered into the performance of the contract; that on or before November 1, 1901, appellee furnished f. o. b. cars at Indianapolis and Chicago, part of the mill machinery so specified, and shipped the same to appellant at Pellston,- Michigan; that on the 13th day of November,. 1901, appellee furnished and delivered f. o. b. cars at Ban Claire, Wisconsin, the remainder of such mill machinery, shipped and consigned to said appellant at Pellston; that the carrier at Ban Claire refused to convey such machinery unless the freight thereon was prepaid, and appellee, thereupon prepaid said freight charges to Pellston; that appellant, with knowledge that said articles to be so shipped from Ban Claire had not been shipped on or before November 1, 1901, on the ninth day of November, 1901, instructed and directed, in writing, shipment thereof to be made; that upon the arrival of the articles so shipped from Bau Claire, at Pellston, the appellant accepted said articles from the carrier and paid the freight thereon that had been so prepaid by appellee.

The amended declaration further charged that all the articles so furnished were constructed of good material and were made in workmanlike manner as required, and were shipped in good order; that on the thirteenth day of November, 1901, said Neilson executed and delivered to appellee his three promissory notes, each for $873.33, payable to appellee at the First State Bank of Petoskey, Michigan, at six per cent, interest, due, respectively, in twelve, eighteen and twenty-four months after their date, which said notes were submitted by said salesman, A. E. White, to appellant, who directed the signing and delivery thereof by Neilson to appellee; that Neilson defaulted in the payment of said notes, wherefore it was claimed that appellant was liable upon his guaranty td appellee, etc.

The declaration under consideration when the former cause was before this court, reported in 120 Ill. App., supra, was held to be insufficient upon the ground that the contract provided that the machinery should be shipped on or before November 1, 1901, and that the notes to be given by Neilson should be payable in twelve, eighteen and twenty-four months from date of shipment; that the note upon which appellant’s liability as guarantor was alleged, was dated November 13, 1901, thirteen days later than the one in which he had agreed to be responsible and that there was no allegation' of fact in the declaration connecting the guaranty of appellant with the note sued upon. The question now made is whether or not by the amended declaration that objection has been overcome and appellant so far connected with the completion of the transaction that he is liable- upon his written guaranty.

The amended declaration, in our judgment, states a good cause of action against appellant. In it, it is averred that on the ninth day of November, 1901, nine days after the machinery was to be shipped under the terms of the contract, appellant directed in writing that such shipment from Eau Claire should be made; that upon the arrival of such machinery at Pellston, appellant accepted the same from the common carrier and paid to appellee the freight which it had prepaid on the shipment from Eau Claire. Notwithstanding these averments, appellant contends that the variance of thirteen days in point of date and maturity is sufficient to discharge him and bases that contention on the ground that the liability of a guarantor cannot be extended by implication. This doctrine, however, can have no application here, since appellant’s conduct in connection with the acts which constitute the variance were such as to estop him from taking advantage of such variance. If appellant had done nothing, himself, .after November 1, 1901, either to further or complete the transaction, his position would be tenable, but as he directed, in writing, the shipment of a part of the machinery several days after the time first fixed for its delivery, accepted the machinery upon its arrival at Pellston, and repaid to appellee the freight prepaid upon a part thereof, he must be held estopped from denying the regularity of the delivery and to have waived his right to insist upon the specific time of performance. Eyster v. Parrott, 83 Ill. 517; Moline Malleable Iron Co. v. McDonald, 38 Ill. App. 589; Brown v. Abbott, 110 Ill. 162.

Free access — add to your briefcase to read the full text and ask questions with AI

Bogardus v. Phœnix Manufacturing Co., 134 Ill. App. 456, 1907 Ill. App. LEXIS 413 (Ill. Ct. App. 1907).

134 Ill. App. 456 (Bogardus v. Phœnix Manufacturing Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Berg Metals Corp. v. Wilson
339 P.2d 869 (California Court of Appeal, 1959)