Bobbitt v. Hoffman, 200 S.W.2d 303, 304 Ky. 196, 1947 Ky. LEXIS 614 (Ky. 1947).

Opinion

Opinion op the Court by

Judge Latimer

Affirming.

This action was instituted as a class suit in the Kenton Circuit Court. Plaintiffs sued, as representatives of *197 the Locomotive Firemen of the Cincinnati Division of the L. & N. Railroad, for the purpose of voiding a judgment of the Estill Circuit Court, and abrogating an injunction of that court.

The Estill County action had its origin in a dispute between trainmen of the Cincinnati Division and the Eastern Kentucky Division of the L. & N. as to which division members would man trains over the trackage between Patio and Ravenna, Kentucky, which is situated within the Eastern Kentucky Division and on the border between the two divisions.

In the Estill litigation the only parties were the L. & N. Locomotive Engineers and their Bargaining Agent. The Locomotive Firemen were not parties to that suit.

It appears that in order to resolve the difficulty, an agreement was entered into in 1919 to the effect that Engineers and Firemen of the Cincinnati Division could operate trains from any point of origin on the Cincinnati Division over the disputed trackage, and any trains originating on that trackage to any point in the Cincinnati Division without accounting or adjustment with the Engineers of the Eastern Kentucky Division. Eastern Kentucky Engineers were given a like privilege with respect to manning and operating trains from points in the Eastern Kentucky Division over the trackage, and from the trackage to any points in the Eastern Kentucky Division. With respect to traffic having its origin and ■destination within the disputed trackage, the regularly assigned service was to be divided equally between Engineers of the respective divisions. This agreement is evidenced by a. letter written to Mr. B. M. Starks, General Manager, L. & N. Railroad, and signed by the General Chairman of each of the Brotherhoods of Locomotive Engineers, Locomotive Firemen and Enginemen, Order of Railway Conductors and Brotherhood of Railway Trainmen, requesting the above arrangements, and a reply by Starks to the General Chairman of each of the above Brotherhoods agreeing to comply with the request, but stating that in order to provide satisfactory operating conditions, the territory in question was being transferred to the Eastern Kentucky Division.

It appears that in 1927 a general contract governing 'intordivisional runs, and the manning of trains thereon, *198 was entered into between the Railroad Company and all its Engineers. Under this 1927 contract the operation of trains on this Patio-Ravenna run fell to the Eastern Kentucky Division Engineers, since it had been placed wholly in their division. The Cincinnati Division Engineers continued operating this run as they had done pursuant to the 1919 agreement.

The Eastern Kentucky Division Engineers sought to have their General Chairman obtain a ruling from the Railroad Company rearranging their assignments so as to give them the benefits of the 1927 contract. The Bargaining Agent declined to grant them this relief, insisting that they were not entitled to a readjustment under the contract of 1927, but were entitled to assignments pursuant to the previous contract made in 1919. The Brotherhood law provides that the decision of the General Chairman shall stand as “law” until “repealed” on an appeal submitted to a referendum vote of all members of all divisions of the L. & N. system. The laws of the Brotherhood further provide that the decision of the referendum shall be final.

After their General Chairman had thus decided against them, the Eastern Kentucky Engineers, pursuant to the ‘ ‘ Constitution and Statutes of the Brotherhood of Locomotive Engineers” appealed from his decision to. a referendum vote by the Engineers of the entire L. & N. system. As result of this referendum vote, the decision of the General Chairman was overruled and Eastern Kentucky Engineers were held to be entitled to assignments under that section of the 1927 contract respecting interdivisional runs.

The General Chairman, then, by letter bearing date December 31, 1941, wrote to the Railroad Company asking it to put into effect the interdivisional runs ‘ ‘ section of the Engineers contract according to its terms.” Thereupon, Mr. Johnston, the Grand Chief Engineer of the Brotherhood undertook to repudiate his previous authorization of the referendum,, and to nullify the decision which the working Engineers on the entire system had made by the referendum vote. Then the General Chairman, on January 14, 1942, by letter, withdrew his request as per his letter of December 31, 1941. Thereupon, the Brotherhood of Eastern Kentucky Engineers *199 brought their suit through G-. F. Hoffman, as their class representative in the Estill Circuit Court against J. N. Hatcher, General Chairman, and J. A. Hennessey, an Engineer employed on the Cincinnati Division as the representative of his colleagues. They alleged that by the expressed terms of the Brotherhood laws, the referendum above was final and conclusive as to their rights. They asked the court for a declaration of rights and for a mandatory injunction requiring their Bargaining Agent, Hatcher, to use all diligence and faith in obtaining from the Railroad an application of the Engineers’ contract to the interdivisional runs. The defendant, J. A. Hennessey, for himself, and all other Locomotive Engineers employed on the Cincinnati Division, through their attorney, immediately filed in the Estill Circuit Court a petition for the removal of the case to the Federal Court of the Eastern District of Kentucky. Upon hearing by that court the case was remanded to the State court. Following this the defendant filed numerous pleadings and participated in a trial for three days in the Estill Circuit Court, which resulted in a final judgment wherein the court declared: That under the constitutional laws of the Brotherhood the referendum decision was final; that the Engineers were entitled to assignments on “interdivisional runs” in accordance with the 1927 contract; that the attempt of the Grand Chief to nullify such decision was arbitrary and capricious; and that it was the duty of Hatcher as General Chairman and Bargaining Agent for the L. & N. system, diligently to seek to obtain approval of the L. & N. Railroad for assignment of Eastern Kentucky Engineers to int'erdivisional runs as requested in the letter written on December 31, 1941, above referred to.

The Cincinnati Division Engineers undertook an appeal to the Court of Appeals. Having not been perfected in time as provided by the statute, the appeal was dismissed and the judgment became final.

The instant action, for the purpose of abrogating this judgment, was brought by C. L. Bobbitt, Jr. and H. L. Foster, who sued for all other persons similarly employed as Locomotive Firemen by the L. & N. Railroad Company on its Cincinnati Division. Hoffman, who was plaintiff in the Estill case; Hatcher, the Bargaining Agent; Hennessey, defendant in the Estill action; Harry *200 J. Roadcut, H. R. Hutchins, and all Locomotive Engineers similarly employed by the L. & N. Railroad on its Cincinnati Division; and J. N.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kirby v. Scroggins
246 S.W.2d 453 (Court of Appeals of Kentucky, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
200 S.W.2d 303, 304 Ky. 196, 1947 Ky. LEXIS 614, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bobbitt-v-hoffman-kyctapphigh-1947.