Bob Thompson Homes, Inc. v. Peters, Rick & Anne Peters

CourtCourt of Appeals of Texas
DecidedApril 28, 1999
Docket05-97-00674-CV
StatusPublished

This text of Bob Thompson Homes, Inc. v. Peters, Rick & Anne Peters (Bob Thompson Homes, Inc. v. Peters, Rick & Anne Peters) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bob Thompson Homes, Inc. v. Peters, Rick & Anne Peters, (Tex. Ct. App. 1999).

Opinion

f AFFIRMED; Opinion filed April 28,1999

In The

Court of Appeals Jfiftfj IHstrttt nf tttexas at Uallas

No. 05-97-00674-CV

BOB THOMPSON HOMES, INC., Appellant V.

RICK PETERS AND ANNE PETERS, Appellees

On Appeal from the 199th District Court Collin County, Texas Trial Court Cause No. 199-139-97

OPINION

Before Justices Lagarde, Moseley, and Bridges Opinion By Justice Lagarde

Bob Thompson Homes, Inc. (Thompson) appeals an interlocutory order denying its motion

to compel arbitration. In one point oferror, itasserts that the trial court erred in denying arbitration because its contract with appellees Rick and Anne Peters (collectively Peters) requires arbitration of any dispute arising out of the contract. We affirm the trial court's order.

On March 3, 1994, Thompson and Peters signed acontract, under which Thompson would construct a single-family residence for Peters. The contract designated Caperton/Johnson as the architect. The contract was a form contract, provided by Thompson. The form contained the following provision: All claims or disputes between the Contractor [Thompson] and the Owner [Peters] arising out of or relating to the Contract Documents, or the breach thereof, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect unless the parties mutually agree otherwise and subjectto an initial presentation of the claim or dispute to the Architect as required under Paragraph 15.5. Notice of the demand for arbitration shall be filed in writing with the other party to this Agreement and with the American Arbitration Association and shall be made within a reasonable time after the dispute has arisen. The award rendered by the arbitrator or arbitrators shall be final andjudgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof. . . . The agreement herein among the parties to the Agreement and any other written agreement to arbitrate referred to herein shall be specifically enforceable under applicable law in any court having jurisdiction thereof.

Before Peters signed the form contract, however, Thompson crossed this provision out and Rick

Peters initialed the strike-out to indicate his assent. In an affidavit later filed with the court,

Thompson explained that the deletions "represent changes that [Thompson] has made to this

standard form and incorporated in essentially all contracts with its customers through the date of the

Peters contract. These standard changes were made by [Thompson] in the initial draft submitted

to Peters and represent [Thompson's] changes."1

As construction progressed, Peters became dissatisfied with Thompson's performance.

Peters complained of major plumbing leaks, faulty electrical wiring, improper and defective

installation of fixtures, appliances, and carpeting, and the like. When Thompson did not remedy

the defects to Peters's satisfaction, Peters stopped making the contracted installment payments.

Thompson sued Peters for payment. Peters counterclaimed for various claims in contract and in tort.

Neitherpartyarguedin itsbriefthat the contractat issuecontainedany ambiguity. Afteroralargument.Thompson submitteda letterbrief arguingthat if there is any ambiguity,it must be resolvedin favor of arbitration because of the publicpolicyfavoringarbitration. It analogizesthe argumentto the principlethat, when the languageof an insurance policy is ambiguous, the construction that affords coverage will be adopted. We donotagreewithThompson'sconclusion. Where an ambiguity existsin a contract, the contractlanguage willbe construed strictly againstthe party who drafted it. since the drafter is responsible for the language used. Gonzalez v.XfissionAm, Ins. Co., 795 S.W.2d 734,737 (Tex. 1990). Because insurersare almostinvariably, if not always,the draftersof their policies,the specificrule about insurancepoliciesissimplya corollaryof the more generalrule. Inthiscase,Thompsondraftedthe formcontract,andThompson,not Peters,struckout the generalarbitration clause. Thereis no reason we should not apply the general contract principle and construe the effect of striking out the general arbitration clause against Thompson.

-2- Thompson moved the trial court to compel arbitration; Peters objected to arbitration. Despite the deletion of the arbitration clause, Thompson contended that other provisions, taken together, meant that, in the event ofadispute between the parties, the architect, Caperton/Johnson, would serve as arbitrator. It relied principally on three provisions:

In case of a dispute between Owner and Contractor as to whether any part of an application for payment should be paid, Architect shall make the final decision on the amount that should be paid.

The Architect will interpret and decide matters concerning performance under and requirements of the Contract Documents on written request of either the Owner or Contractor. The Architect will make initial decisions on all claims, disputes orother matters in question between the Owner and Contractor. The Architect's decisions in matters relating to aesthetic effect will be final if consistent with the intent expressed in the Contract Documents.

The Architect will have authority to reject Work which does not conform to the Contract Documents.

Because the architect was given this authority, Thompson concludes that the contract contemplated Caperton/Johnson as arbitrator.

Peters responds that the striking ofthe formal arbitration clause means that he did not agree

to the arbitration process. At most, he argues, the contract gave Caperton/Johnson the authority to

decide the amount that should be paid ifthe parties disagreed whether any amount ofan application

for payment should bepaid. Inquestions ofperformance under the contract, Caperton/Johnson had

the authority to make "initial decisions on all claims, disputes orother matters in question"; Peters,

stressing the word "initial," contends that Caperton/Johnson was explicitly given authority to make

final decisions only in matters relating to aesthetic effect. While Caperton/Johnson had the authority to reject work that did not conform to the contract between the parties, Peters asserts that nothing in the contract gave Caperton/Johnson the exclusive right to do so. Peters also argued thatCaperton/Johnson would notbe animpartial arbitrator, because it and

Thompson enjoyed a long professional relationship andThompson often used Caperton/Johnson as

its architect. In response, Thompson cites authority for the proposition that an engineer, working

on a project, may be delegated the authority to actas an arbitrator. City ofSan Antonio v. McKenzie

Constr. Co., 150 S.W.2d 989, 995-96 (Tex. 1941). Butin thatcase thesupreme court emphasized

the critical language: the engineer"shall determine all questions in relation to said work, and the

construction thereof. He shall in all cases decide every question which may arise relative to the

execution of this contract on the part of said Contractor." City ofSan Antonio, 150 S.W.2d at 996.

We do not dispute that parties to a contract can designate another party to the same contract as an

arbitrator, if they chooseto do so. Caperton/Johnson is not disqualified from being an arbitrator in

the Peters' home building contract simply because it is the architect on the project. The real issue

Free access — add to your briefcase to read the full text and ask questions with AI

Related

De Gonzalez v. Mission American Insurance Co.
795 S.W.2d 734 (Texas Supreme Court, 1990)
City of Pinehurst v. Spooner Addition Water Co.
432 S.W.2d 515 (Texas Supreme Court, 1968)
Solis v. Evins
951 S.W.2d 44 (Court of Appeals of Texas, 1997)
Freis v. Canales
877 S.W.2d 283 (Texas Supreme Court, 1994)
Hasty Inc. v. Inwood Buckhorn Joint Venture
908 S.W.2d 494 (Court of Appeals of Texas, 1995)
Cantella & Co., Inc. v. Goodwin
924 S.W.2d 943 (Texas Supreme Court, 1996)
Belmont Constructors, Inc. v. Lyondell Petrochemical Co.
896 S.W.2d 352 (Court of Appeals of Texas, 1995)
City of San Antonio v. McKenzie Construction Co.
150 S.W.2d 989 (Texas Supreme Court, 1941)
Shead v. State
746 S.W.2d 19 (Court of Appeals of Texas, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Bob Thompson Homes, Inc. v. Peters, Rick & Anne Peters, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bob-thompson-homes-inc-v-peters-rick-anne-peters-texapp-1999.