Boas v. Thatcher Car & Construction Co.

28 N.Y.S. 659, 8 Misc. 443
CourtThe Superior Court of the City of New York and Buffalo
DecidedMay 7, 1894
StatusPublished
Cited by1 cases

This text of 28 N.Y.S. 659 (Boas v. Thatcher Car & Construction Co.) is published on Counsel Stack Legal Research, covering The Superior Court of the City of New York and Buffalo primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boas v. Thatcher Car & Construction Co., 28 N.Y.S. 659, 8 Misc. 443 (superctny 1894).

Opinion

SEDGWICK, C. J.

The action was upon the written contract of the parties. It was made May 5, 1893. The plaintiff agreed to make and deliver to the defendant certain goods, “and to complete them within three weeks’ time.” The defendant agreed to pay for them a stipulated price, and there is no dispute here as to the amount. On the trial the learned judge dismissed the complaint under plaintiff’s exception, and ordered the exceptions taken by plaintiff to be heard in first instance at the general term. The counsel for the parties here argue that the complaint was dismissed solely upon the ground that it appeared that the goods were not delivered within three weeks, and that it does not appear that the defendant had waived the provision as to the time of delivery. The time named in the contract—that is, May 26th—elapsed without delivery. On June 9th the defendant wrote by its officer, “I am much surprised to hear that your people have not got any of the address books ready yet,” and, “By giving this your personal attention, and doing your utmost to push the books to completion, you will very much oblige,” etc. This modifying the contract, of course, as to the time of performance, waived the obligation of the plaintiff as to the time first stipulated. The jury might have found that the plaintiff agreed to the modification as to time. The modified contract was obligatory upon the parties from that time. As to whether the plaintiff complied with the new contract by doing his utmost, if it were necessary to show that, would be a question for the jury. The jury might have found, if the testimony left it in doubt, that on June 10th the defendant told the plaintiff orally to stop work on those memorandum books until they received further orders. The plaintiff refused to accede to the proposition. If these positions are correct, the plaintiff, as might have been found by the jury, offered for delivery to the defendant the goods in a condition provided by the contract, and was entitled to receive the price by the contract. I am of opinion that at the least the plaintiff had a right to go to the jury upon the issues of fact. Plaintiff’s exceptions are sustained, and a new trial is ordered, with costs to abide the event.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hirsch v. Annin
28 Misc. 228 (Appellate Terms of the Supreme Court of New York, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
28 N.Y.S. 659, 8 Misc. 443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boas-v-thatcher-car-construction-co-superctny-1894.