Board of Zoning Appeals v. Blue Ridge Stone Corp.

166 S.E.2d 237, 209 Va. 594
CourtSupreme Court of Virginia
DecidedMarch 10, 1969
DocketRecord 6843 , 6844
StatusPublished
Cited by2 cases

This text of 166 S.E.2d 237 (Board of Zoning Appeals v. Blue Ridge Stone Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Zoning Appeals v. Blue Ridge Stone Corp., 166 S.E.2d 237, 209 Va. 594 (Va. 1969).

Opinion

*595 Buchanan, J.,

delivered the opinion of the court.

These are appeals from a decree of the Circuit Court of Roanoke County which held that the zoning ordinance of the county did not prohibit Blue Ridge Stone Corporation, herein called Blue Ridge, from continuing quarrying operations on one of three tracts of land under its contract with Adams Construction Company.

Adams Construction Company, a partnership, referred to herein as Adams, is engaged in road building which requires large quantities of stone. Adams does not ordinarily operate stone quarries but concerns itself with searching for available stone deposits. Sometime prior to the construction of Interstate 81 in the Roanoke area, Adams, in June 1959, purchased a stone-bearing tract of 130 acres, referred to as the Thomas tract. In drilling on this tract Adams found that the rock deposit continued into two adjoining tracts, referred to as the Todd tract and the France tract. In December 1959, Adams purchased the stone in place on six acres of the Todd tract, which adjoined the Thomas tract; and in April 1960, Adams purchased the stone in place on about four acres of the France tract, which ad j oined the Todd tract.

By agreement dated June 23, 1960, Adams conveyed to Blue Ridge its interest in the Todd and France tracts and the exclusive right to quarry stone from the Thomas tract if the stone on the other two tracts was exhausted before the interstate highway was completed (extended to ten years by a supplemental agreement dated September 1, 1962), together with the right to install on the Thomas tract all machinery, crushing plant and structures convenient for processing and storing stone from the Todd, France and. Thomas tracts.

Shortly after the execution of the above agreement, Adams constructed on the Thomas tract an asphalt plant for the treatment of stone furnished by Blue Ridge and used by Adams in its road-building work, and it has been continuously operated to the time of the decree appealed from in this case.

It developed in the fall of 1963 that the stone supplied by Blue Ridge from the Todd and France tracts was not sufficient to meet the needs of Adams in its road-building contract. Adams then requested and received from Blue Ridge permission to quarry stone from the Thomas tract to meet Adams’ needs. Adams accordingly employed Ararat Stone Company to quarry and stockpile from *596 the Thomas tract the required stone. Ararat quarried stone from the Thomas tract until about May 15, 1964, and then vacated the premises.

In the spring of 1965, Blue Ridge had finished its quarrying from the Todd and France tracts and in June of that year it was preparing to move its equipment to the Thomas tract. Before that was accomplished, however, the administrator of the zoning ordinance of Roanoke county notified Blue Ridge, by letter of August 30, 1965, that since the quarry on the Thomas tract had not been operated for more than a year, it could not under the provisions of the zoning ordinance be reopened.

Blue Ridge thereupon ceased , its operations and filed its appeal to the Board of Zoning Appeals. It stated therein, among other things, that the stone deposit and other rights which it acquired under the agreement of June 23, 1960, with Adams, i.e., on the Thomas, Todd and France tracts, constituted one area and that this area had been continuously used without interruption for the purpose for which it was zoned, and that its intention was to quarry the same as one area, exhausting first, as it was required to do, the stone on the Todd and France tracts. A hearing was had on November 22, 1965, before the Board of Zoning Appeals, consisting then of four members, one member being absent. Evidence was introduced and at its conclusion the board was evenly divided, two voting to permit Blue Ridge to continue operating and two voting that it not be allowed to do so.

Thereafter, on petition of Blue Ridge, the court below ordered the issuance of a writ of certiorari, according to the provisions of Code § 15.1-497, to which return was made and the court entered a decree referring the cause to one of its commissioners, who was directed to report whether Blue Ridge had the right to continue on the Thomas tract or had lost its right under paragraph 9-2-6 of the county zoning ordinance. The commissioner was directed to take evidence, consider the pleadings and exhibits and also the evidence before the Board of Zoning Appeals.

The commissioner filed his report on October 11, 1966. He said that the facts were not in dispute, and stated them to be about as set out above, with the following in addition:

The Roanoke County Zoning Ordinance was adopted April 18, 1960, and the Thomas, Todd and France tracts were zonéd “Industrial District M-2”. The three tracts are shown on a map in the *597 record as they adjoin each other. Section 9-1-12 of the ordinance * provides that “stone works, quarries, crushing plants, asphalt plants, and mining operations” are permitted uses in Industrial District M-2, and § 9-2-6 of the ordinance further provides:

“In any Industrial M-2 area where the operation of quarries, stone works, crushing plants, asphalt plants, and mining operations has been undertaken and discontinued for a period exceeding one year, said operations shall not be resumed, nor shall said areas be used for any of the other permitted uses in Industrial District M-2.”

At the time of the adoption of the ordinance there were no stone quarries, crusher plants, mining operations or asphalt plants in operation on the Thomas, Todd or France tracts. Quarrying and asphalt plant operations were contemplated, however.

Shortly after the agreement of June 1960, between Adams and Blue Ridge, Adams located its asphalt plant on the Thomas tract so as to operate efficiently with stone taken from the Thomas, Todd and France tracts. Blue Ridge’s evidence is that it considered the Thomas, Todd and France tracts as one area, and it intended to quarry the Todd and France tracts first and then move over to the Thomas tract.

The commissioner then refers to the permission granted by Blue Ridge to Adams in the agreement of September 1, 1962, to quarry stone on the Thomas tract to supplement Blue Ridge’s production on the other two tracts and to the fact that Ararat quarried, processed and stockpiled a large quantity of stone for Adams which it has continued to use in its road construction and asphalt surfacing business, and that a part of the stockpile is still on the Thomas tract.

The commissioner then states that the sole issue is whether Blue Ridge has lost its rights by the discontinuing of quarrying on the Thomas tract for more than one year, as to which Blue Ridge contends: (1) that paragraph 9-2-6 of the zoning ordinance is not applicable; and (2) that this paragraph is arbitrary and unreasonable and lacks certainty and definiteness.

The commissioner agreed with the second contention and found *598 that paragraph of the ordinance to be indefinite and uncertain and therefore invalid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chesterfield, Etc. v. Board of Zoning, Etc.
209 S.E.2d 925 (Supreme Court of Virginia, 1974)
Chesterfield Civic Ass'n v. Board of Zoning Appeals
209 S.E.2d 925 (Supreme Court of Virginia, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
166 S.E.2d 237, 209 Va. 594, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-zoning-appeals-v-blue-ridge-stone-corp-va-1969.