Board of Works v. I.A.E., Inc.

956 N.E.2d 86, 2011 Ind. App. LEXIS 1727, 2011 WL 4104910
CourtIndiana Court of Appeals
DecidedSeptember 15, 2011
Docket45A03-1007-CP-369
StatusPublished
Cited by6 cases

This text of 956 N.E.2d 86 (Board of Works v. I.A.E., Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Works v. I.A.E., Inc., 956 N.E.2d 86, 2011 Ind. App. LEXIS 1727, 2011 WL 4104910 (Ind. Ct. App. 2011).

Opinion

OPINION

DARDEN, Judge.

STATEMENT OF THE CASE

The Board of Works of the City of Lake Station, Indiana, and the City of Lake Station (collectively, “Lake Station”) appeal the jury’s verdict and the trial court’s rulings in favor of I.A.E. Consulting Engineers, Inc. (“I.A.E.”).

*89 We affirm but remand for further proceedings.

ISSUES

1. Whether the jury’s verdict is supported by sufficient evidence.
2. Whether the trial court abused its discretion in refusing to give Lake Station’s Proposed Final Instruction No. 5 regarding a party who is first guilty of a material breach of contract.
3. Whether the trial court abused its discretion in giving the Court’s Final Instruction No. 24 regarding prejudgment interest.

FACTS

On June 19, 1990, I.A.E., designated “Consultant,” and Lake Station, designated “Owner,” entered into a written contract whereby I.A.E. was to provide engineering services, including “a location study; a design study; and [a] Combined Location-Design Study Report,” for Lake Station in a project to provide improved roads and a bridge. (Lake Station’s App. 59). The studies and report were to be developed in accordance with appropriate regulations and requirements as approved by the Federal Highway Administration (“FHWA”) and geometric design standards and safety criteria as adopted by the American Association of State and Highway Transportation Officials and approved by the Indiana Department of Transportation (“INDOT”).

The Lake Station Board of Works’ minutes from 1990 indicate that the contract was the product of ongoing discussions between Lake Station and I.A.E. and that the Board of Works unanimously approved the contract on June 19, 1990. The total amount to be paid to I.A.E. for its work on the three phases of the project — design of the 15th Avenue extension, the Grand Boulevard extension, and the bridge — was $450,999. In relevant part, the contract stated:

SECTION IV — COMPENSATION

A. The CONSULTANT shall receive as payment for the work performed under this Agreement as indicated herein unless a modification of this Agreement is mutually approved by the OWNER and CONSULTANT in writing, as follow:
1. 15th Avenue from Lake Street to Old Hobart Road, and Old Hobart Road from 15th Avenue to State Road 51 — LUMP SUM FEE OF $159,288.84.
2. Grand Boulevard from 15th Avenue to Central Avenue except for the Bridge Structure over 180-94— LUMP SUM FEE OF $130,430.25.
3. The Bridge Structure over ISO-94 — LUMP SUM FEE OF $161,280.00.
B. The CONSULTANT shall submit monthly invoices after the project has been approved for funding by the Indiana Department of Transportation, Federal Highway Administration, Regional Planning Commission, or any other funding agency. The OWNER agrees to pay all submitted invoices within forty-five (45) days from the date of each invoice.

Ik. Abandonment and Termination

The OWNER reserves the right to terminate or suspend this Agreement upon written notice.

A. If the OWNER shall abandon the services herein mentioned, the CONSULTANT shall deliver to the OWNER all data, reports, drawings, specification and estimates completed or partially completed and these shall become the property of the owner. The earned value of the work performed shall be based upon an estimate of the *90 portions of the total services as have been rendered by the CONSULTANT to the date of the abandonment and which estimate shall be as made by the OWNER in the exercise of its honest and reasonable judgment. The payments as made to the CONSULTANT shall be paid as the final payment in full settlement for his services hereunder.

(Lake Station’s App. 48, 53).

On May 1, 1990, prior to the signing of the contract, Carl Miller, who was mayor at the time, told the Board of Works that I.A.E. could be hired, “but that they could not do any work until funding was in order.” (Lake Station’s App. 40). Subsequently, on October 26, 1990, INDOT approved a resolution granting $431,000 to Lake Station to begin actual construction of the project. 1 On February 27, 1991, Mayor Miller issued to I.A.E. a “proceed order” directing I.A.E. to begin the preparation of plans and specifications pursuant to the contract, adding that “payment will be made by [Lake Station] ... upon availability of funds.” (Lake Station’s App. 64). I.A.E. began work on engineering designs needed to obtain state approval for the project, spending approximately $250,000 on salaries alone.

The project proceeded in various parts. The first part was a feasibility study, which included soil borings. As of May 24, 1995, Lake Station had made partial payment to I.A.E. for services rendered in the amount of $37,000 for the completion of the soil borings. Lake Station, through a May 24, 1995 letter written by Dewey R. Lemley, who was mayor at the time, acknowledged that it had an outstanding balance due to I.A.E. in the amount of $413,000. The letter stated that “[a]l-though I.A.E. has substantially completed the plans and specifications, [Lake Station] is unable to pay the balance of the $413,000 for engineering services until [Lake Station] receives funding.” (Lake Station’s App. 104). Throughout Miller’s and Lemley’s terms as mayor, Lake Station continued to seek federal funding of the project. The record is devoid of any evidence that Miller or Lemley told I.A.E. that it would have to obtain financing to continue the project so that it could be paid. Under INDOT procedures, I.A.E. could not obtain final approval of the design plan until funding was secured by Lake Station.

Shirley Wadding became mayor in 1996, and shortly thereafter, orally informed I.A.E. president, Rama Talluri (“Rama”), that Lake Station would proceed only if I.A.E. found the money to finish the project. No additional funds were ever appropriated for the project, and on June 15, 1999, Mayor Wadding stated, “No more Project Rama. I’m happy it is over.” (Tr. 588). On June 18, 1999, Rama, perceiving Lake Station’s abandonment of the project, wrote Mayor Wadding, seeking payment of the $413,000 that former Mayor Lemley had acknowledged was owed, plus 10 percent interest.

On May 26, 2000, I.A.E. filed suit against Lake Station seeking payment under the contract for the work it had already completed for the project. Lake Station filed a motion for summary judgment, arguing that the receipt of funding was a condition precedent that had not been fulfilled. I.A.E. responded by filing a cross-motion for partial summary judgment, alleging that Lake Station had abandoned the project, triggering the contract’s *91 abandonment and termination provision. On August 11, 2003, the trial court granted Lake Station’s motion for summary judgment, finding that payment was contingent on funding, and therefore the agreement between the parties had never become a binding contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
956 N.E.2d 86, 2011 Ind. App. LEXIS 1727, 2011 WL 4104910, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-works-v-iae-inc-indctapp-2011.