Board of Trade, Inc. v. State, Department of Labor, Wage & Hour Administration

83 P.3d 1072, 2004 Alas. LEXIS 10, 2004 WL 103306
CourtAlaska Supreme Court
DecidedJanuary 23, 2004
DocketNo. S-10533
StatusPublished

This text of 83 P.3d 1072 (Board of Trade, Inc. v. State, Department of Labor, Wage & Hour Administration) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Trade, Inc. v. State, Department of Labor, Wage & Hour Administration, 83 P.3d 1072, 2004 Alas. LEXIS 10, 2004 WL 103306 (Ala. 2004).

Opinion

OPINION

FABE, Chief Justice.

I. INTRODUCTION

On remand from our decision in Board of Trade, Inc. v. State, Department of Labor <fe Workforce Development, Wage & Hour Administration1 (BOT I), the hearing officer determined that an employer must pay prevailing wages under the Little Davis-Bacon Act to workers employed at a quarry located thirteen miles from the site of an airport construction project. The hearing officer concluded that the Cape Nome Quarry activity should be considered “on-site” because it could not have been carried out at an alternative site closer to the airport construction project. Necessary to the hearing officer’s determination was his finding that five closer quarry sites could not produce adequate material. The employer challenges the hearing officer’s conclusion. Because the hearing officer incorrectly interpreted our guidance on remand and because the factual record demonstrates that the quarry activity could have been carried out at sites closer to the construction project, we reverse and order that judgment be entered in favor of the employer.

II. FACTS AND PROCEEDINGS

A. Factual History

The Alaska Department of Transportation and Public Facilities (DOTPF) invited bids from contractors to resurface the EasVWest runway of Nome’s airport. The invitation informed bidders that the project required four layers of material: two inches of asphalt concrete at the top; nine to twelve inches of base course under the asphalt concrete; thirty-two inches of subbase materials; and two types of borrow material at the bottom.

While the invitation did not dictate the source of the contractors’ material, it did state that DOTPF was “unaware of any other material sources in closer proximity meeting project requirements” than those at the Cape Nome Quarx-y, thirteen miles from the airport. DOTPF further represented that [1074]*1074the Cape Nome Quarry was “off-site” for purposes of the Little Davis-Bacon Act.

In July 1991 DOTPF notified Knik Construction Company that it was the lowest bidder on the prime contract for the runway renovation project.2 At the same time, Board of Trade, Inc. (BOT), a Nome gravel supplier, entered into a contract with Sound Quarry, Inc., the owner of the Cape Nome Quarry, for the removal of material from the quarry to supply the job.3 Prior to 1991, Sound Quarry had entered into royalty agreements with other contractors for the extraction of material from the Cape Nome Quarry. From 1993 to 1996, after the completion of the runway project, BOT entered into additional royalty agreements with Sound Quarry for the extraction of material from the Cape Nome Quarry.

In August 1991 DOTPF formally awarded Knik the runway renovation contract.4 Knik and BOT then entered into a formal agreement for the supply of aggregate materials.5 BOT supplied Knik with aggregate materials for the top two layers of the runway: the asphalt concrete and base course layers. For 1991 and 1992, the overwhelming majority of rock that BOT extracted from the Cape Nome Quarry went to supply the runway project.

For each of the top two layers, DOTPF required that the rock have a sufficiently high degradation mark and low abrasion result. The degradation mark indicates the hardness of the rock and its durability when struck. A higher degradation test result indicates harder rock. DOTPF required that the first two layers have a degradation value of fifty. The abrasion test measures how durable the rock is when exposed to water. A lower test result indicates more durable rock. DOTPF required an abrasion test re-suit of forty for the asphalt concrete layer and of forty-five for the base course layer.

B. Procedural History

The Little Davis-Bacon Act requires “that where a public construction contract involves the employment of mechanics, laborers, or field surveyors, they are to be paid the prevailing wage.”6 Public construction is defined as work performed “on-site.”7 In August 1992 the Department of Labor (Department) informed BOT that under regulations interpreting the Little Davis-Bacon Act, the Cape Nome Quarry was considered “on-site” for the public construction project and that employees at the quarry were entitled to compensation at the prevailing wage rate.8 The Department filed a prevailing wage complaint against BOT because the Department concluded that virtually all of BOT’s activities at the quarry were dedicated to the performance of the Nome airport contract, making the activities “on-site” under 8 Alaska Administrative Code (AAC) 30.910(a).9 That provision defines “on-site” as including areas that are “adjacent” or “nearby.”10 BOT appealed, claiming that the regulation was invalid and, alternatively, that the Department’s interpretation of the regulation was wrong.11

We upheld the regulation’s validity, noting that the Little Davis-Bacon Act expanded the scope of its model, the federal Davis-Bacon Act, to include workers who are not “directly upon the site of the work.”12 But we ruled that the regulation’s expanded definition of “on-site” was still geographically based and rejected the Department’s argument “that the determination of whether a public project is ‘on-site’ depends more on the relationship between the contract and’the construction project than the geographic [1075]*1075proximity of the activity to the construction site.” 13

Consequently, we remanded. We recognized that “whether a public construction project is ‘on-site’ will necessarily be fact specific and decided on a case-by-case basis” 14 and that “the agency should consider the normal meaning of the statutory term ‘on-site’ and the regulatory terms ‘adjacent’ and ‘nearby.’ ”15 We added that “the agency may consider whether the activity could have been carried out at an alternative site closer to the construction”16 and clarified that whether “the site of an activity is ‘nearby’ and ‘proximate’ to the construction depends on the setting, the physical lay of the land, and whether the area is developed or undeveloped.” 17

On remand, the hearing officer held that the Cape Nome Quarry was “on-site” because no closer quarry could consistently produce material that met the project’s specifications. The Department adopted the hearing officer’s findings of fact and conclusions of law, and the superior court affirmed its decision. BOT again appeals and raises two primary arguments: (1) that the hearing-officer misread this court’s first ruling by requiring any sites closer than the Cape Nome Quarry to “consistently” produce material that matches the project specifications; and (2) that substantial evidence does not support the agency’s factual determination that there are no closer sites that can consistently produce the material.

III. STANDARD OF REVIEW

We do not defer to a superior court acting as an intermediate court of appeal.18

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Handley v. State, Department of Revenue
838 P.2d 1231 (Alaska Supreme Court, 1992)
Storrs v. State Medical Board
664 P.2d 547 (Alaska Supreme Court, 1983)
Board of Trade, Inc. v. State
968 P.2d 86 (Alaska Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
83 P.3d 1072, 2004 Alas. LEXIS 10, 2004 WL 103306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-trade-inc-v-state-department-of-labor-wage-hour-alaska-2004.