Board of Supervisors v. Department of Environmental Resources

669 A.2d 418, 1995 Pa. Commw. LEXIS 613
CourtCommonwealth Court of Pennsylvania
DecidedNovember 13, 1995
StatusPublished
Cited by2 cases

This text of 669 A.2d 418 (Board of Supervisors v. Department of Environmental Resources) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Supervisors v. Department of Environmental Resources, 669 A.2d 418, 1995 Pa. Commw. LEXIS 613 (Pa. Ct. App. 1995).

Opinions

RODGERS, Senior Judge.

The Board of Supervisors of Middle Pax-ton Township (Township) petitions for review of a decision of the Environmental Hearing Board (Board), which dismissed the Township’s appeal from the Department of Environmental Resources’ (Department) disapproval of an update to the Township’s official plan, submitted pursuant to the Pennsylvania Sewage Facilities Act (Act).1

The Board’s relevant findings of fact are summarized as follows. The Township’s first official plan, approved by the Department in 1975, included provisions for the eventual installation of sewers in certain developed areas of the Township and for the conveyance of sewage to a treatment plant in the adjacent Borough of Dauphin (Dauphin). By 1985 this portion of the official plan had not been implemented. On November 20, 1985, the Department notified the Township that Dauphin was upgrading its sewage treatment plant, advised the Township to negotiate for capacity in the upgraded plant, and directed the Township to update its official plan within 120 days. On April 80, 1986, the Department and the Township entered into a Consent Order and Agreement providing, inter alia, for the updating and implementation of the official plan and for continuing limitations on the issuance of sewage system permits in the meantime.

In October of 1986, the Township submitted to the Department an official plan update; the 1986 update recognized malfunctions of existing on-site sewage systems and proposed the installation of sewers within the next ten years to connect two residential developments, Delwood Acres and Stony Creek Manor, to Dauphin’s treatment plan. After discussions with the Department, the Township submitted a second official plan update. The Department determined that both updates were unacceptable because they did not address, to the Department’s satisfaction, the need for sewers in the developed areas of the Township.

The Township then retained a technical consultant to perform water sampling and other studies to determine whether sewers were, in fact, needed in these areas. The Township also directed its sewage enforcement officers to study subsurface sewage disposal repairs in two residential developments to determine the effectiveness of the repairs. Using the results of these studies, the Township submitted to the Department a third official plan update on August 26, 1988. This plan update reflected the Township’s position that a sewer system would not be needed within the next ten years and that the Township’s sewage disposal needs could be met adequately by on-site systems.

After reviewing the Township’s third official plan update and after performing its own soil and water investigations, the Department, by letter dated December 8, 1988, scheduled a meeting with the Township for December 21, 1988. The letter included the following statements:

Please note that information available to the Department indicates that there is a serious health hazard present. Citizens should be advised to avoid contact with groundwater seeps and water in ditches and small streams close to developed areas especially Stoney [sic] Creek Manor. Owners of wells in developed areas should consider bacterial treatment of drinking water until the township resolves problems with ongoing groundwater contamination.

(Exhibit C-18G.)

At the meeting on December 21, 1988, the Department made it clear to the Township [420]*420that the third update would not be approved, and the Township requested to review the Department’s sampling data. On December 30, 1988, the Department sent a letter to the Township stating as follows:

As a result of the meeting held on December 21, 1988, Middle Paxton Township has requested that all information gathered by the Department be turned over to the Township. Therefore, the Department of Environmental Resources is requiring a sixty (60) day extension to the review time for the above referenced Official Act 537 Plan, as per Chapter 71, Section 71.16 [25 Pa.Code § 71.16].

(Exhibit C-18H.)

On January 9, 1989, the Township sent a letter to the Department stating that the Township did not wish to reconsider the plan update. The letter also expressed the Township’s belief that the Department’s claim to an extension of the review period was untimely. On February 24, 1989, the Department formally disapproved the third official plan update, concluding that the plan failed to address the existing and long term sewage disposal needs of the Township.

The Township appealed to the Board, arguing, inter alia, that the Department’s disapproval was untimely, having been issued well after the 120-day period set forth at 25 Pa.Code § 71.16, and that the plan update must, therefore, be deemed approved.

As it existed on February 24, 1989, the date of the Department’s disapproval, 25 Pa. Code §§ 71.16(c) and (d) read as follows:2

(c) Within 120 days after submission of the official plan or revision, the Department shall either approve or disapprove the plan or revision.
(d) Upon the Department’s failure to approve an official plan within 120 days of its submission, the official plan shall be deemed to have been approved, unless the Department informs the municipality that an extension of time is necessary to complete the review.

The Board acknowledged that, under the provisions set forth at 25 Pa.Code § 71.16, the Department was required to approve or disapprove the third plan update, or to inform the Township that an extension of time was necessary, no later than December 27, 1988.3 The Board also recognized that the Department’s letter of December 30, 1988, informing the Township that an extension was required, was sent three days after the review period expired. However, the Board concluded that the Department’s disapproval was timely, reasoning that:

The stated reason for the extension, as set forth in the December 30, 1988 letter, was the Township’s request at the December 21, 1988 meeting to review all of DER’s soil and water sampling data. DER had made it clear to the Township at that meeting and in the December 8,1988 letter ... that it had completed its review of the third Update and would not approve it. On the date of the meeting, there was still adequate time remaining in the 120-day review period to issue a formal disapproval. When the Township asked to review the data, however, it was obvious that the period had to be extended. The Township’s request, therefore, effectively waived the 120-day limit.

(Board’s decision, p. 27.)

On appeal to this Court,4 the Township again argues that the language of 25 Pa.Code § 71.16 is mandatory and explicitly provides for deemed approval when the Department fails to approve or disapprove a plan within 120 days.

[421]*421In order for the result of deemed approval to occur from the Department’s failure to act within a statutorily prescribed time period, there must be explicit language in the statute providing for deemed approval. Department of Environmental Resources v. Washington County, 157 Pa.Cmwlth. 1, 629 A.2d 172 (1998), appeal dismissed as improvidently granted, 536 Pa. 431, 639 A.2d 1171 (1994).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pequea Township v. Herr
716 A.2d 678 (Commonwealth Court of Pennsylvania, 1998)
Evangelical Lutheran Good Samaritan Society, Inc. v. Albert Oil Co.
969 S.W.2d 691 (Kentucky Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
669 A.2d 418, 1995 Pa. Commw. LEXIS 613, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-supervisors-v-department-of-environmental-resources-pacommwct-1995.