Board of Improvement Water & Light Improvement Districts v. Galbraith

185 S.W. 474, 133 Ark. 302, 1916 Ark. LEXIS 296
CourtSupreme Court of Arkansas
DecidedMarch 20, 1916
StatusPublished
Cited by1 cases

This text of 185 S.W. 474 (Board of Improvement Water & Light Improvement Districts v. Galbraith) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Improvement Water & Light Improvement Districts v. Galbraith, 185 S.W. 474, 133 Ark. 302, 1916 Ark. LEXIS 296 (Ark. 1916).

Opinion

WOOD, J.,

(after stating the facts). I. Among other provisions in the contract is the following:

‘ ‘ The board shall have the final decision in all matters of dispute involving the character, quality and the amount of work and the-compensation to be paid therefor in eases not directly provided for in this contract or the plans and specifications, or any other question arising under this contract. ’ ’

Appellants contend that under this provision the decision of the board and the engineer as to the amount that should be deducted from the original contract price was final.

The improvement districts in entering upon the. contracts with the appellee could do so only through their' board of commissioners. No authority is found in the above provision of the contract for constituting the board a final arbiter to settle all matters of dispute that might arise between the improvement districts and the appellee. There was no attempt upon the part of either party to the contract to have the matters in dispute submitted to the board as an arbiter. Such a provision in the contract, if made, was uninforceable, as evidenced by this lawsuit. Hence Hatfield Special School District v. Knight, 112 Ark. 83, and Boston Store v. Schleuter, 88 Ark. 213, cited by appellee to the effect that where a dispute arose between the parties to the contract as to the performance of the same in certain particulars that the decision of the architect should be binding, has no application here, for there is no such provision in this contract.

The above provision, however, must be considered as reflecting the intention of the parties in making the contract, and in determining the questions now at issue between them we must weigh the evidence in the light of the above provision. But such provision can not be invoked by the appellants as a settlement of this lawsuit in favor of their contention.

There are provisions in the contract requiring all work to be inspected by the engineer, Albert O. Moore, and giving him the right to reject all work that was not in compliance with the contract, and requiring the contractor to furnish all material and labor, and to execute the work in accordance with the plans and specifications prepared by the consulting engineer, and making these plans and specifications a part of the contract. When all of these provisions are considered together it is manifest that the board, in rejecting the itemized account presented by the appellee did so because it conceived that the items charged for were not in accord with the provisions of the contract as shown by the final estimate made by Moore, the consulting engineer. The testimony shows that the appellee and Moore went over this estimate, and that there was a considerable difference between them.

' The court found that the appellants were entitled to a credit for the sum of $2,340.23, for the value of the work and material which the board omitted, under the terms of the contract; whereas the appellants contend that the court should have allowed them on this account the sum of $3,838.24. The contention of appellants is in accord .with the clear preponderance of the evidence.

The testimony of Moore, the consulting engineer, shows that the total value of the deductions that should be made for work and materials that were omitted, under the terms of the contract, amounted to $3,838.24, and that the total value of the work, labor and materials furnished for the increased work was $1,836.32, which made a net reduction of $2,001.92, to which appellants were entitled. The testimony shows that appellee had been paid $16,-792.15. Appellants were entitled to have the amount of this net reduction and these admitted payments taken from the contract price of $19,161, which would leave a balance due appellee of $366.93, instead of the sum of $1,710.52, as found by the chancellor.

There was also, according to the testimony, “some old material left over which the board agreed to take, worth about $200, for which appellee should be paid. The chancellor found that the appellants had expended the sum of $159 in repairing certain defects wherein appellee had'failed to comply with his contract, and for which appellants should have credit. See Hatfield v. Knight, supra. So far as this record discloses these items are correct, and this would leave the sum of $107.93 due appellee on the contract, which sum should bear interest at the rate of 6 per cent, per annum from October 6, 1913, the date upon which appellants refused to make the settlement with appellee for the amount claimed to be due him under his contract.

The testimony of Moore, the consulting engineer, shows that he allowed appellee the contract price for the items. The testimony of appellee himself shows that he arrived at the amount claimed to be due on the unit basis. On this point he was asked, “How did this difference arise between the total of the aggregate sum here and the lump aggregate sum of the contract?” and answered, “It was by the difference in the allowances that was made, as on the basis of $100 for that smoke stack. This difference comes in a unit basis. The difference would be what it would be on a unit basis and what it would be under the original contract.”

Appellee’s testimony tended to show that there was an oral understanding at the time the changes were made which warranted him in charging for the increased work on the unit basis. The consulting engineer and each member of the board testified that there was no change made in the written contract. Besides the contract itself provides that any important changes should be agreed upon in writing by the parties prior to performing the work or furnishing the material, and that no extra charge should be made unless such provision was complied with. It also provides that such changes should be on the basis of the contract.

The court therefore erred in adopting the basis of account established by the testimony of the contractor instead of the basis as established by the testimony of the engineer, and the written contract.

II. The court found that the appellee had not complied with the contract in the manner in which he dug the ditches and laid and calked the pipes, but that the appellants were, estopped by their acts and conduct from recovering any sum on the cross-complaint on account of such breach of the contract.

The finding of the court that the contractor had not complied with his contract in the matter of digging ditches and calking the pipes is sustained by a preponderance of the evidence. The appellants set up in their cross-complaint that to do this work so as to make it conform to the requirements of the contract would cost the sum of $2,035.05. The chancellor refused to allow the appellants to recover against the appellee for this sum, on the ground that they were estopped by their conduct.

The statute, Kirby’s Digest, section 5719, provides that all contractors “shall be required to give bond for the faithful performance of such contracts as may be awarded them, with good and sufficient securities, in double the amount of the contract work, and the board shall not remit or excuse the penalty or forfeiture of said bond or the breaches thereof. ’ ’

.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
185 S.W. 474, 133 Ark. 302, 1916 Ark. LEXIS 296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-improvement-water-light-improvement-districts-v-galbraith-ark-1916.