Board of Education, Utica School District No. 1 v. Delle Cese

65 Misc. 2d 473, 318 N.Y.S.2d 46, 1971 N.Y. Misc. LEXIS 1848
CourtNew York Supreme Court
DecidedFebruary 11, 1971
StatusPublished
Cited by5 cases

This text of 65 Misc. 2d 473 (Board of Education, Utica School District No. 1 v. Delle Cese) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Education, Utica School District No. 1 v. Delle Cese, 65 Misc. 2d 473, 318 N.Y.S.2d 46, 1971 N.Y. Misc. LEXIS 1848 (N.Y. Super. Ct. 1971).

Opinion

J. Robert Lynch, J.

The defendant S ’Doia herein moves for summary judgment dismissing the complaint on the grounds raised by his affirmative defenses that: (1) any claim against him has been discharged by the plaintiff’s acceptance of his work and final payment to him; (2) arbitration is by contractual necessity a condition precedent to suit and that the time to demand arbitration has expired; (3) the plaintiff by receiving payment of its damages through insurance has waived its right to seek damages from him. S’Doia also moves for summary judgment dismissing the defendant Delle Cese’s cross claim against him on the ground that Delle Cese could only be actively negligent to the plaintiff and hence not entitled to indemnity.

The plaintiff moves to strike from S’Doia’s answer as insufficient in law paragraphs Sixth through Twenty-fifth, “ including the second, third and fourth affirmative defenses ”. Actually the paragraphs specified also include the first affirmative defense and the thrust of the plaintiff’s motion papers is to the first, second and third defenses and not to the fourth.

[475]*475After these motions were made and while decision was pending, the defendant S’Boia for reasons which will appear later moved to stay the action against him on the ground that the issue is referable to arbitration, despite the fact that arbitration cannot be held, the time for it having passed. All of the motions are herein considered.

On June 10, 1966 the defendant S’Boia contracted with the plaintiff to do the general construction work involved in the reconstruction of one of its buildings. The contract provided:

Section 31 Damages

11 Should either party to the Contract suffer damages because of any wrongful act or neglect of the other party or of anyone employed by Mm, claim shall be made in writing to the party liable within a reasonable time of the first observance of such damage and not later than the final payment, except as expressly stipulated otherwise in the case of faulty work or materials, and shall be adjusted by agreement or arbitration.”

Section 40 Arbitration

All disputes, claims or questions subject to arbitration under the Contract shall be submitted to arbitration in accordance with the provisions, then obtaining, of the Standard Form of Arbitration Procedure of the American Institute of ArcMtects, and the Agreement shall be specifically enforceable under the prevailing arbitration law, and judgment upon the award rendered may be entered in the court of the forum, state or federal, having jurisdiction. It is mutually agreed that the decision of the arbitrators shall be a condition precedent to any right of legal action that either party may have against the other.

11 The Contractor shall not cause a delay of the work during any arbitration proceedings, except by agreement with the Owner.

“ Notice of the demand for arbitration of a dispute shall be filed in writing with the other party to the Contract, and a copy filed with the Architect. The Demand for arbitration shall be made within a reasonable time after the dispute has arisen; in no case, however, shall the demand be made later than the time of final payment, except as otherwise expressly stipulated in the Contract.”

The defendant Belle Cese was the architect of the reconstruction project and the defendant Dale Engineering was the consulting engineer for structural steel work. During the course of the job a part of the east wall of the building collapsed on [476]*476November 28, 1966 and a part of the west wall on February-16, 1967. On July 18, 1967 a change order on S’Doia’s contract was issued which called for re-erection of the collapsed portions at a cost of $219,973. By letter of October 2, 1967, the plaintiff through its attorneys advised the defendants:

This matter has been thoroughly investigated and the result of said investigation clearly demonstrates that the damage and loss aforesaid, was occasioned by the negligence of each of you, either jointly or severally.

Please acknowledge receipt of this letter so that a possible disposition may be discussed without the necessity of litigation. If I do not hear from you within 30 days, I will assume that litigation will be necessary.”

The letter led to conferences among the parties’ representatives which continued to at least July 15, 1968, if not longer. In April, 1969 this action was commenced by the service of bare summonses to which S’Doia responded with a notice of appearance and a demand for a complaint. On June 19,1969 the entire construction job, change orders and all, was completed; the job was accepted; the final payment to S’Doia was made. On June 30, 1969, the plaintiff served the complaint on S’Doia. This was taken back to correct some dates and the corrected version was served on July 21, 1969. S’Doia answered, setting forth the defenses mentioned, on August 15, 1969.

S’Doia’s prayer for summary judgment on the ground that the claim against him has been discharged by acceptance of his work and final payment is denied. By its terms the contract excludes from release by final payment all claims arising out of “ failure to comply with drawings and specifications ”. Whether the claim asserted by the plaintiff’s letter of October 2, 1967 falls in this category or whether or not it was excluded for some other reason from the release of final payment, an issue nonetheless remains. It may ultimately be resolved as a question of law but at this juncture the moving papers, while treating this aspect of the motion rather cursorily, do suggest that there may well be considerable factual evidence on this point. Since this defense has been pleaded in paragraphs Sixth through Sixteenth of S’Doia’s answer, the plaintiff’s motion to strike these paragraphs is denied.

S’Doia’s motion for summary judgment on the ground that the plaintiff has waived its right to seek damages from him because it has accepted payment of those damages through insurance must be denied. S’Doia would have us hold that the usual insurer-loan receipt-plaintiff arrangement is unavailable here because the contract provides that the “ owner, contractor, [477]*477and all other subcontractors waive all rights, each against the others, for damages caused by fire or other perils covered by insurance ”. To interpret this to exempt a contractor from the results of his own negligence is forbidden as contrary to public policy (General Obligations Law, § 5-323). We recognize that Melodee Lane Co. v. American Dist. Tel. Co. (18 N Y 2d 57) cited by S’Doia permits, consistent with the statutory prohibition against exemption from liability, an optional limitation of liability, but that does not lie within our facts. The plaintiff’s motion to strike this defense, pleaded in the Twentieth and Twenty-first paragraphs of the answer, is granted.

We come now to the problem presented by the existence of the arbitration clauses in the contract and the compounding of that problem by the complaint not having been served until the time for arbitration had expired. First though we must agree with S’Doia that he was not required to seek arbitration before the complaint was served. It is traditional that “ a defendant may ordinarily let a sleeping dog lie until he is in danger of being bitten ” (Matter of Haupt v. Rose, 265 N. Y. 108, 111).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deneen v. City of New York
106 Misc. 2d 785 (Civil Court of the City of New York, 1980)
Heimlich v. Charlton Lithographing, Inc.
103 Misc. 2d 741 (New York Supreme Court, 1979)
Ralph Korte Construction Co. v. Springfield Mechanical Co.
369 N.E.2d 561 (Appellate Court of Illinois, 1977)
Hogeland v. Sibley
366 N.E.2d 263 (New York Court of Appeals, 1977)
St. Vincent's Medical Center v. Vincent E. Iorio, Inc.
78 Misc. 2d 968 (New York Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
65 Misc. 2d 473, 318 N.Y.S.2d 46, 1971 N.Y. Misc. LEXIS 1848, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-education-utica-school-district-no-1-v-delle-cese-nysupct-1971.