Board of Educ., Monongalia County, W. Va. v. Mellon-Stuart Co.

885 F.2d 864, 1989 U.S. App. LEXIS 13519, 1989 WL 106813
CourtCourt of Appeals for the Fourth Circuit
DecidedSeptember 8, 1989
Docket88-1768
StatusUnpublished

This text of 885 F.2d 864 (Board of Educ., Monongalia County, W. Va. v. Mellon-Stuart Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Educ., Monongalia County, W. Va. v. Mellon-Stuart Co., 885 F.2d 864, 1989 U.S. App. LEXIS 13519, 1989 WL 106813 (4th Cir. 1989).

Opinion

885 F.2d 864
Unpublished Disposition

NOTICE: Fourth Circuit I.O.P. 36.6 states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Fourth Circuit.
BOARD OF EDUCATION, MONONGALIA COUNTY, WEST VIRGINIA, a West
Virginia Public Body Corporate, Plaintiff-Appellant,
v.
MELLON-STUART COMPANY, a Pennsylvania corporation,
Construction Cost Consultants, Inc., a
Pennsylvania corporation, Defendants-Appellees.

No. 88-1768.

United States Court of Appeals, Fourth Circuit.

Argued May 11, 1989.
Decided Sept. 8, 1989.

Paul Lambert Selby, Jr. (Mike Magro, Jr., Magro & Magro on brief) for appellant.

Carolyn M. Branthoover (Donald E. Seymour, James A. Buddie, Kirkpatrick & Lockhart, Jacques R.A. Williams, Hamstead, Hamstead & Williams on brief) for appellees.

Before PHILLIPS AND MURNAGHAN, Circuit Judges, and FRANK A. KAUFMAN, Senior United States District Judge for the District of Maryland, sitting by designation.

PER CURIAM:

Appellant Board of Education of Monongalia County ("the Board") filed a seven-count complaint on January 5, 1987, in the Circuit Court of Monongalia County, West Virginia, against appellees Mellon-Stuart Company ("Mellon-Stuart") and Construction Cost Consultants ("CCC"), alleging four causes of action: breach of contract, unjust enrichment, fraud in the inducement and misrepresentation. Appellees removed the case to the United States District Court for the Northern District of West Virginia on February 9, 1987.1 The district court granted, immediately prior to trial, defendants' motion for summary judgment with regard to the counts for fraud and misrepresentation.2

On July 8, 1988, the breach of contract and unjust enrichment claims were tried to the court. The district court concluded that no breach of contract had been committed by either Mellon-Stuart or CCC,3 and that, in any event, the Board had not proven any damages. The district court entered judgment for defendants. The Board then timely noted this appeal.

Facts

Between the years 1976-1981, the Board undertook an extensive construction program consisting of five separate school projects. Those projects included: (1) construction of South Area Junior High School; (2) construction of the Vocational Technical Center; (3) construction of the University High School Gymnasium; (4) construction of North Morgantown Elementary School; and (5) construction of an addition to Clay-Battelle High School. The Board hired an architectural firm for the first project. That firm advised the Board to utilize "construction management" to administer the school projects because "construction management" is said to eliminate the need for a general contractor and to lower the total cost of a project. The Board accepted that recommendation of the architects, conducted interviews with various firms, and ultimately entered into construction management contracts with CCC for each of the five projects.

Construction management involves a construction manager working with the owner and architect in planning a budget for each project. The construction manager provides cost advice and scheduling advice in order to reduce the time frame of the entire project; and reviews, and expresses views concerning, drawings presented to him by the architect. The architect and the construction manager jointly supervise the bidding process and recommend to the owner the contractor to which each contract should be awarded. After the architect completes final drawings concerning a project, the construction manager computes a guaranteed maximum price ("GMP") for the owner--that is, a guaranteed cap on the total cost of the project. Thus, in the instant case, when the total cost of a project exceeded the GMP, CCC was required to bear that excess cost or "overage." On the other hand, each contract provided that if the total project cost was less than the GMP, the Board and CCC would split the savings on a 90%-10% basis, with 90% going to the Board and 10% to the CCC. During the work period of each project, CCC was responsible for reviewing applications for payments made by the general trades contractors to the Board before any payments were made.

In return for its services, CCC was to be paid 6% of the total cost of each project, plus the 10% savings, if any, discussed supra. In addition, the Board agreed to reimburse CCC for certain reimbursable costs.

During 1972-1978, CCC was a wholly-owned subsidiary of Mellon-Stuart Company.4 While members of the Board may not have been aware of the exact relationship of the companies, and in particular may not have known that many employees were employed by both Mellon-Stuart and CCC, and that all employees were compensated from the same payroll, members of the Board knew that the companies were affiliated. Indeed, the relationship of CCC and Mellon-Stuart was discussed during certain Board meetings, including the meeting during which CCC made its presentation to the Board in support of CCC's quest to be hired as construction manager. From the outset, CCC informed the Board of its relationship with Mellon-Stuart, and also specifically requested the Board to permit Mellon-Stuart to bid for general trades contracts on projects administered by CCC. Mellon-Stuart did bid on, and was awarded as the low bidder, each one of the five general trades contracts for the school projects.

Under applicable law in West Virginia during the relevant time period, any construction work in excess of $5,000 was required to be put out for competitive bidding.5 Consequently, each of the five School Board projects was advertised for public bidding. CCC, as construction manager, was present when the Board opened the bids and then reviewed them in order to make a recommendation to the Board for acceptance.

After Mellon-Stuart had been awarded the general trades contracts, CCC discussed with the Board the billing of CCC's reimbursable costs through the Mellon-Stuart general trades contracts. The Board agreed to that method of billing. The billing procedure provided that construction management fees would be taxed at the lower 1.2% West Virginia Business and Occupancy tax for services, rather than the State's 2.2% Business and Occupancy tax applicable to a construction manager's reimbursable costs. Consequently, inclusion of CCC's cost reimbursables with the Mellon-Stuart billings for fees resulted in a tax savings for the Board. That method of billing had been used by Mellon-Stuart and CCC with regard to school projects in West Virginia in areas other than Monongalia County.6

After acceptance of a bid, the usual practice was that CCC would prepare a form AIA contract in which the total cost of the contract, labelled the "contract sum," would equal the bid amount. However, in the case of the Mellon-Stuart contracts, each AIA contract was not prepared until several months after Mellon-Stuart had begun the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John W. Lodge Distributing Co. v. Texaco, Inc.
245 S.E.2d 157 (West Virginia Supreme Court, 1978)
W. L. Thaxton Construction Co. v. O.K. Construction Co.
295 S.E.2d 822 (West Virginia Supreme Court, 1982)
Pennsylvania Lightning Rod Co. v. Board of Education
20 W. Va. 360 (West Virginia Supreme Court, 1882)
First National Bank of Gallipolis v. Marietta Manufacturing Co.
153 S.E.2d 172 (West Virginia Supreme Court, 1967)
Kentucky Fried Chicken of Morgantown, Inc. v. Sellaro
214 S.E.2d 823 (West Virginia Supreme Court, 1975)
Shrader v. White
761 F.2d 975 (Fourth Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
885 F.2d 864, 1989 U.S. App. LEXIS 13519, 1989 WL 106813, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-educ-monongalia-county-w-va-v-mellon-stuart-co-ca4-1989.