Board of Drainage Commissioners v. H. J. Peterson & Co.

244 S.W. 322, 196 Ky. 130, 1922 Ky. LEXIS 474
CourtCourt of Appeals of Kentucky
DecidedOctober 20, 1922
StatusPublished
Cited by2 cases

This text of 244 S.W. 322 (Board of Drainage Commissioners v. H. J. Peterson & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Drainage Commissioners v. H. J. Peterson & Co., 244 S.W. 322, 196 Ky. 130, 1922 Ky. LEXIS 474 (Ky. Ct. App. 1922).

Opinion

Opinion of the Court by

Judge Clarke

Reversing.

A drainage district having been establisbed, and tbe construction of a ditch known as ‘ ‘Otter Creek Public Ditch” having been ordered pursuant to tbe drainage act of 1912, section 2380, Kentucky Statutes, the appellants, the- drainage commissioners of the county, in accordance with subsection 26 of the act, entered into a written contract on February 3, 1919, with appellees Peterson Company as principal, and the 'Southern Surety Company as its surety, for the construction of the ditch, estimated to cost $27,108.70.

The contract provides that the work should be completed in the year 1919, in accordance with the plans and specifications. The work not having been completed [131]*131within that time, and the contractor having done no work thereon after .about December 1, 1919, appellants rele't the contract to J. H. Church on April 3, 1920, and on September 9, 1920, instituted this action for damages against the original contractor and its surety.

After the issues had been formed, proof was taken by deposition, a jury waived and the case submitted to the court by agreement, resulting in a judgment dismissing the petition, from which plaintiffs have appealed.

As a basis for the judgment the court stated separately, in writing, its findings of fact and law, as follows:

“The court finds, that from the evidence that plaintiff had given no notice that it intended to declare the contract forfeited or cancelled; that the time was not of the essence of such contract, that the plaintiff without the knowledge or consent of the surety and in contravention of its rights, overpaid the H. J. Peterson Company in the sum of $1,900.00. The court finds as matter of law that the plaintiff had no right or authority to declare said contract forfeited or cancelled without notice to each defendant; that time was not of the essence of the contract, and that by overpaying the H. J. Peterson Company, as found above, the Southern Surety Company was released from all liability as surety in said contract.”

The appellants contend that the court erred in each of its findings of both law and fact, while the appellees insist that the court found correctly in each instance, and in addition, that the judgment should be affirmed in any event, because of a total failure of plaintiffs to prove, even approximately, the amount of damages, if any, sustained by the district.

We are unable to find any evidence whatever in the record to sustain the court’s finding that plaintiffs overpaid the contractor $1,900.00 or any other sum, and we may therefore eliminate from consideration the court’s conclusion of law that because of such overpayment the surety was released. The only evidence cited by counsel for appellees to sustain this finding of fact consists of statements by witnesses for plaintiffs that the contractor had not completed more than about one-fourth of his contract according to plans and specifications, and that he had been paid, as the contract provides, 80% of the monthly estimates of the engineer for work performed by him .

[132]*132The argument that this proof shows an overpayment to the contractor is based upon the erroneous assumption that the Avitnesses meant that of the work performed by the contractor only about one-fourth of it was done according to the plans and specifications, and that in paying him 80% of the value thereof he was paid the 80%. for all of his work, wherea's he should have been paid only 80% of one-fourth of what he had done, since only one-fourth of it was done according to plans and specifications. The Avitnesses, however, were careful to explain, and no one contradicts, that all of the work performed by the contractor, and for which he was paid 80% of the contract price, was required to be done by the contract, but the places where the work was done were not completed according to plans and specification's, except as to about 25% thereof.

What happened was, that the contractor, at several places, cut the ditch not so wide or so deep as he was required to do, but all of the excavations made by him and for which he was paid were required by the contract, hence he neither did nor was paid for any Avork except in strict accordance with the contract, although by not completing the excavations at many places to the required width and depth he did not, as the witnesses stated, complete more than about one-fourth of the work according to plans and specifications.

It is very clear, hoAvever, that only having been paid for 80% of the work actually done by him, and all of this work being required under the plans and specifications, there was no overpayment, as the contract provided for payment of 80% of the engineer’s monthly estimates of work done by him in compliance with the plans and specifications.

Neither is there any merit in the contention of appellees that the judgment should be affirmed Avithout reference to the court’s findings of law and fact, because of an absence of proof of damage to the district, and we. shall also dispose of this question before taking up the more troublesome one as to whether or not both defendants were released from their obligations under the contract by reason of a failure upon the part of the plaintiffs to give notice of a purpose to rescind the contract before reletting the work to another.

The contract as amended provided that the contractor was to receive 1114 cents per cubic yard for soft dirt ex[133]*133cavations, and 2% times that amount or 35% cents per cubic yard for hardpan or hard dirt excavations. In proof of damages, the plaintiff; .showed that'they were required to pay Church for doing the work originally let to the Peterson Company, a flat rate of 22 cents per cubic' yard for both soft and hard dirt excavations, estimated at.107,085 cubic yards, but found by actual measurement to be 108,383 cubic yards; that this price was.reasonable and the best that could be obtained.

Obviously, under the Peterson contract the cost would - depend upon the relative amounts of soft and hard dirt excavated, and to ascertain which contract was. more expensive to the district it would be necessary to know the quantity of each kind of earth left unremoved by the contractor. It is insisted for appellees that this information was in the keeping of the plaintiffs and they made no effort to furnish it. It is true that plaintiffs did not prove this essential fact, but defendants brought out upon the cross-examination of Mr. Poole, the engineer in charge of the work, that Peterson’s contract was estimated to contain 3,005 cubic yards of hard earth and that he removed 2,336 cubic yards of same, and it takes only a simple calculation to show that according to the engineer’s estimates there were but 669 cubic yards of hard dirt left unremoved by the Peterson Company, and for which it was to receive 35% cents per cubic yard. It was therefore established by the proof that only 669 ■cubic yards of hard dirt were left unremoved by the Peterson Company; and that plaintiffs gained 13% cents per cubic yard on this 669 cubic yards of hard dirt under the flat rate of 22 cents per cubic yard with the new contractor, but lost 7% cents per cubic yard upon 107,714 cubic yards of soft dirt, which shows a net loss to the district of $8,236.68 on excavation work.

Then again the proof shows a loss of $5.20 an acre on clearing 24.62 acres of right-of-way, or $180.02 on this item.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Center Drainage District No. 1 v. Capitol Indemnity Corp.
147 N.W.2d 245 (Wisconsin Supreme Court, 1967)
Barrett v. Commonwealth
259 S.W. 25 (Court of Appeals of Kentucky, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
244 S.W. 322, 196 Ky. 130, 1922 Ky. LEXIS 474, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-drainage-commissioners-v-h-j-peterson-co-kyctapp-1922.