Board of Commissioners v. Quaker Construction Co.
This text of 441 A.2d 801 (Board of Commissioners v. Quaker Construction Co.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Opinion by
The Board of Commissioners of Abington Township (Board) seeks review of a judgment in mandamus filed by the Court of Common Pleas of Montgomery County ordering the Board to grant approval to the subdivision plan of the appellees1.
The appellees sought approval from the Board to subdivide 63 acres in Abington Township for the construction of single-family residences. A tentative sketch2 of the subdivision plan was submitted to the Department of Public Works of Abington Township, which recommended to the Board in a meeting on April 10, 1979 that the application be refused. The Board adopted that recommendation and took no further action on the proposed subdivision. On July 3, 1979, the appellees filed an action in mandamus seeking to compel the Board to approve the tentative [10]*10sketch, contending that the Board did not comply with the notification requirements of Section 508 of the Pennsylvania Municipalities Planning Code (MPC),3 Act of July 31, 1968, P.L. 805, as amended, 53 P.S. §10508 and that the subdivision plan should therefore be deemed to have been approved. The court of com[11]*11mon pleas granted a peremptory judgment ordering that the Board approve the tentative sketch of the subdivision plan, and the Board’s petition to open that judgment was dismissed. The Board’s appeal of those two orders was denied by the court below and this appeal followed.
The Board first maintains that the notification requirements of Section 508 of the MPC do not apply here because the tentative sketch submitted by the appellee was not mandatory under the Abington Township Subdivision of Land Ordinance and this case is therefore not governed by this Court’s decision in Mid-County Manor Inc. v. Haverford Township Board of Commissioners, 22 Pa. Commonwealth Ct. 149, 348 A.2d 472 (1975), but is controlled by our holding in Raccoon Mountain, Inc. v. Perry County Planning Commission, 50 Pa. Commonwealth Ct. 613, 413 A.2d 1170 (1980).4
In Mid-County Manor we noted that, while the MPC envisions only a two-step process for the approval of a subdivision plan, the submission of a preliminary and a final plan, a township may require more than two steps. Id. at 156-57, 348 A.2d at 476, note 2. We concluded, however, that even if the governing body of a municipality does prescribe additional procedures, it must nevertheless comply with the notice provisions contained in Section 508 of the MPC. We concluded that the sketch and site plans filed by Mid-County as the first of three steps required in seeking plan approval should have been acted upon by the Township within 90 days and that its failure to act constituted an approval of the plans. In Raccoon Mountain Inc., however, we found that the initial stage of - the County’s three-step application process [12]*12was optional, not mandatory, that Mid-County Manor was therefore distinguishable and that Section 508 did not apply in that case.
We believe that this case is controlled by Mid-County Manor. Article IV of the Abington Township Subdivision of Land Ordinance governs Plan Processing Procedures and Section 146-7 of Article IV requires that “[t]he procedures set forth in this Article shall be strictly followed by all subdividers.” Section 146-8 of Article IV provides that “[a] tentative sketch shall be submitted to the Township Engineer for informal discussion and suggestions as to general layout and preparation of the preliminary plan.” We believe that these sections of the ordinance clearly establish that submission of a tentative sketch by a subdivider is a mandatory step in the process of obtaining subdivision approval. We are, of course, aware of Section 146-32 which provides: “In order to save unnecessary work, it is recommended that before preparing preliminary plans, a tentative sketch showing proposed streets and lots be submitted for review. It may be in pencil and need not be drawn to scale.” This section, however, is contained in Article VI of the ordinance which covers Plan Requirements, and we believe that this language concerns only the content of the tentative sketch and not the necessity for submitting one. We must conclude, therefore, that Mid-County Manor requires that the notice requirements of Section 508 of the MPC be applied in this case.
The Board also argues that it expressly rejected the tentative sketch because of numerous inadequacies in the plan and that such rejection should be effective, despite any technical violations of Section 508. Section 508 requires that a governing body’s decision must be in writing and communicated to the applicant within 90 days of the governing body’s regular meeting and that the decision must also be mailed or personally
[13]*13communicated to the applicant within 15 days. Section 508(1) of the MPC, 53 P.S. §10508(1). There is no question that no such written decision was rendered and that no mailing or personal communication was made to the appellees here. In addition, Section 508(2) of the MPC, 53 P.S. §10508(2), provides that the governing body’s decision must also explicitly set forth, not only the defects in the subdivision plan, but also the sections of the municipality’s ordinances which the plan violates. The Board, by failing to render a written decision, also failed to specify to the appéllees which sections of the Township’s ordinance were inconsistent with the tentative sketch. Under Section 508(3) of the MPC, 53 P.S. §10508(3), failure to comply with all of the aforementioned technical requirements results in a deemed approval of the subdivision plan. The requirements of Section 508, although technical, are nonetheless mandatory and the Board cannot avoid its duty to comply with Section 508 merely by assertirig that it had valid reasons for rejecting the appellees’ tentative sketch. See V. C. Finisdore, Inc. v. Lower Merion Township, 27 Pa. Commonwealth Ct. 598, 367 A.2d 412 (1976). Because the Board did not comply with Section 508 in attempting to reject the appellees’ tentative sketch, we must hold that said sketch was approved. See e.g., Bobiak v. Richland Township Planning Commission, 50 Pa. Commonwealth Ct. 77, 412 A.2d 202 (1980); Finisdore.
We will therefore affirm the order of the court below.
Order
And Now, this 24th day of February, 1982, the order of the Court of Common Pleas of Montgomery County in the above-captioned matter is affirmed.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
441 A.2d 801, 65 Pa. Commw. 8, 1982 Pa. Commw. LEXIS 1076, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-commissioners-v-quaker-construction-co-pacommwct-1982.