Board of Commissioners v. Branaman

82 N.E. 65, 169 Ind. 80, 1907 Ind. LEXIS 33
Indiana Supreme Court·Decided October 10, 1907·No. No. 21,132·Published·Cited by 10 cases

Opinion

Jordan, J.

This action was instituted by appellee in the Jackson Circuit Court, against appellant, to recover upon a contract entered into by and between him and said board, whereby he contracted to construct five gravel roads in Owen township, in said county. A demurrer to the complaint for insufficiency of facts was overruled, and the venue was changed to the Lawrence Circuit Court, wherein, upon .the issues joined between the parties, there was a trial by the court and a finding in favor of the appellee, and, over appellant’s motion for a new trial, judgment was rendered against it for $3,937.35, to be paid out of the funds arising from the sale of the bonds issued under the statute. It ivas further adjudged that appellee recover of appellant his costs laid o.ut and expended. The assignment of errors calls in question the decision of the court in overruling the demurrer to -the complaint, as well as other rul- ■ ings in the case.

[82] 1. [81] The facts alleged in the complaint may be said to be substantially as follows: Upon a petition of fifty freeholders [82] of Owen township, Jackson county, the board of commissioners ordered, and there was held, an election by the voters of the township to determine whether the highways in question should" be improved by graveling and grading as prayed for in the petition. A majority voted in favor of the improvement, and the board of commissioners “thereupon duly ordered that said highways be improved. Plans, profiles, and specifications were adopted, and the contract, upon competitive bidding, was duly and legally let to appellee. Thereupon he entered into a written contract with the board of commissioners to construct the ro'ads, in accordance with the plans and specifications as adopted, at and for the sum of $15,690. Said proceedings were had under and in pursuance of an act of the legislature approved March 3, 1893 (Acts 1893, p. 196, §§6924-6934 Burns 1894), and the amendatory act thereto, approved March 7, 1895 (Acts 1895, p. 143). By the terms of the contract payments were to be made to appellee as the work progressed, on estimates made and certified by the superintendent. Twenty per cent of such estimate was to be withheld until final completion of the work. Appellee duly filed his bond as such contractor, which was approved. Appellant caused bonds to be issued and sold for an amount sufficient to pay the amounts due to appellee and received the money therefor, and now has, and at all times has had, money arising from the sale of such bonds amply sufficient to pay for such roads in full. Thereafter appellant levied a tax upon the property of said township for the payment of said bonds and the interest thereon. Appellee fully performed all the work required by his said contract in accordance with the estimates, plans, and profiles therefor, which were modified by said board of commissioners so as to require him to perform extra work, etc. Appellant duly received, accepted, and approved the construction of the following roads embraced in said contract. (Here the complaint specifies three of the five roads embraced in the con[83] tract.) Appellee completed the other two roads according to the plans and profiles as modified by appellant and by the superintendent in charge of such construction, and in accordance with his contract, and fully performed every condition and provision of his contract. Appellant from time to time made payments to appellee as the work progressed, upon estimates duly made and filed, and the amounts paid and the amounts remaining unpaid are fully specified and set out. Upon one of the roads appellee did additional work, under the order and direction of appellant, amounting to $501, and upon another he did additional work, in obedience to the order of appellant, under the plans and profiles aforesaid as modified, to the value of $503.54. Upon the completion of said work, and long before the commencement of this action, appellee filed his verified claim for said sums, and each of them, with the auditor of said county, more than ten days before the regular term of the board, which claim was accompanied by the certificate and report of the superintendent of each of said roads, duly verified by him, showing that said roads, and each of them, had been theretofore completed according to the plans, plats, profiles, and contract, but appellant, after a long and unreasonable delay, refused to pay him any part of said sum, although the same was long past due and wholly unpaid. The contract and itemized statement of the extra work are filed-with and made exhibits of the complaint, and judgment is demanded for $7,500, payable out of the fund derived from the sale of the bonds, and for all other and proper relief.

Free access — add to your briefcase to read the full text and ask questions with AI

Board of Commissioners v. Branaman, 82 N.E. 65, 169 Ind. 80, 1907 Ind. LEXIS 33 (Ind. 1907).

82 N.E. 65 (Board of Commissioners v. Branaman) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Canteen Athletic Club's Appeal
60 Pa. D. & C. 631 (Erie County Court of Quarter Sessions, 1947)
Sullivan v. Board of Commissioners
149 N.E. 94 (Indiana Court of Appeals, 1925)
Frankfort Construction Co. v. Sims
113 N.E. 298 (Indiana Supreme Court, 1916)
Board of Commissioners v. Chastain
111 N.E. 630 (Indiana Supreme Court, 1916)
Modlin v. Board of Commissioners
103 N.E. 506 (Indiana Court of Appeals, 1913)
City of Indianapolis v. American Construction Co.
96 N.E. 608 (Indiana Supreme Court, 1911)
Smith v. Board of Commissioners
90 N.E. 881 (Indiana Supreme Court, 1910)
Donaldson v. State ex rel. Board of Commissioners
90 N.E. 132 (Indiana Court of Appeals, 1909)
Templeton v. Board of Commissioners
89 N.E. 880 (Indiana Supreme Court, 1909)