BNM Ventures, LLC v. Shannon Green

CourtCourt of Appeals of Texas
DecidedJune 16, 2023
Docket05-22-00474-CV
StatusPublished

This text of BNM Ventures, LLC v. Shannon Green (BNM Ventures, LLC v. Shannon Green) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BNM Ventures, LLC v. Shannon Green, (Tex. Ct. App. 2023).

Opinion

AFFIRMED in part; REVERSED and RENDERED in part; VACATED and REMANDED and Opinion Filed June 16, 2023

S In The Court of Appeals Fifth District of Texas at Dallas No. 05-22-00474-CV

BNM VENTURES, LLC, Appellant V. SHANNON GREEN, Appellee

On Appeal from the 95th District Court Dallas County, Texas Trial Court Cause No. DC-20-08630

MEMORANDUM OPINION Before Justices Reichek, Nowell, and Garcia Opinion by Justice Reichek In this appeal following a bench trial, BNM Ventures, LLC challenges the

trial court’s judgment in favor of Shannon Green on his claim for breach of a

settlement agreement. BNM brings two issues generally asserting the evidence does

not support the trial court’s finding of breach or its award of damages. Because we

conclude Green failed to adduce any evidence at trial to show the cost-of-completion

damages he sought to recover were reasonable, we reverse the trial court’s award of

those damages and render judgment that Green recover no remedial damages.

Because the remaining damages are unchallenged, they are affirmed. We remand the case to the trial court for a reassessment of attorney’s fees in light of this

disposition.

Background

BNM constructed a home and sold it to Green in April 2019. Several weeks

later, the area received substantial rainfall and the house flooded. Green hired

Lighthouse Engineering, L.L.C. to do a drainage inspection.

A report prepared by Lighthouse concluded there were several issues with the

water drainage on the property, including that the grading around the house did not

meet the minimum requirements of the International Residential Code (“IRC”).

Lighthouse drafted an engineering report recommending remediation measures and

attached a drawing outlining their recommendations.

On August 8, 2019, Green’s attorney sent Michael White, BNM’s managing

partner, a notice of construction defects pursuant to the Texas Residential

Construction Liability Act. Among the defects listed in the notice were that the

“driveway was improperly constructed and allows water to run toward the house,”

and the “final grade was improperly completed on the front and left sides of the

Property, which causes water to drain toward the house, rather than away from it.”

Following a mediation, Green and BNM entered into a settlement agreement in

which BNM agreed to,

Modify the driveway and grading per the Lighthouse Engineering, LLC report attached as Exhibit “B.” Post- completion inspection by an engineer will be performed at

–2– Shannon Green’s expense within 15 days from the date that BNM notifies Mr. Green that repairs are believed to be complete; if the post-completion inspection determines that the modifications made by BNM did not conform to the specifications set forth in Exhibit “B,” BNM will make further modifications until those specifications are met.

In May 2020, White informed Green that BNM’s work was ready for

inspection. The Lighthouse engineer who drafted the original report determined the

repairs did not conform to the report’s specifications. White disputed the engineer’s

conclusion, particularly with respect to the driveway, stating the report was “very

ambiguous.” According to White, the report did not require the driveway to be

broken out and replaced to the extent Lighthouse now claimed was necessary. White

ceased work on the exterior of the house and said he wanted the parties’ attorneys to

resolve the conflict.

On June 1, Green’s attorney sent an email to BNM’s attorney stating that

Green would be “hiring another contractor to finish the exterior work that [BNM]

refuses to complete.” Two days later, Green sent a text message to White stating he

was not sure if White was “waiting on a deal” to complete the repairs, but he was

hiring another company to complete the work. Lighthouse issued an inspection

report the same day stating the work done by BNM was deficient in several ways

including, (1) the grading around the perimeter did not meet the minimum required

by the IRC, and (2) the driveway was not broken out and “swaled” as recommended

in the repair plan.

–3– On June 29, Green received a bid from Armadillo Fences, Decks and

Remodels stating the cost to make the necessary modifications to his property would

be $8,600. Payment by credit card would add an additional service charge of

$301.15. The estimate stated it was also “HIGHLY recommended” to have sod laid

on the property. Ten days later, Armadillo Fences provided Green with an estimate

of $4,288.05 to install 2,199 square feet of sod. Green hired Armadillo Fences and

the record shows the company completed the drainage work and laid sod. Green

paid the estimated amounts, including the credit card fee.

BNM filed this suit seeking a declaratory judgment that the settlement

agreement did not require more construction than was required by “the plain

language and plain meaning” of the original Lighthouse engineering report. BNM

asked the court to specifically declare that BNM’s interpretation of the report’s

specifications for the driveway was correct. BNM stated there was a justiciable

controversy because Green indicated his intention to recover the additional costs of

having the repairs performed “pursuant to his own interpretation of the Lighthouse

report.” Green brought a counterclaim for breach of contract asserting that BNM

refused to make the changes necessary for its work to conform to the original

engineering report’s specifications. BNM moved for, and was granted, an order of

mediation. No settlement resulted.

A trial was conducted before the court without a jury. White testified he

believed the work performed by BNM was consistent with the engineering report

–4– prepared by Lighthouse. White further testified BNM did not refuse to finish the

drainage work, but had merely paused the work to allow the attorneys for both sides

to resolve the issue of what the Lighthouse report required. White conceded the

grading around the house did not meet the minimum slope required by the IRC, but

stated the code provides exceptions to that requirement. White did not ask

Lighthouse whether reliance on an exception would be permitted.

Michael Gandy, owner of Lighthouse, testified the engineering report clearly

required the driveway to be broken out and rebuilt to divert water away from the

house and meet code requirements. The work done by BNM, according to Gandy,

was insufficient to resolve the property’s drainage issues. Gandy stated he could

find no record of anyone from BNM contacting his office to get clarification or

resolve any ambiguities in the report. He further stated there was nothing about the

property that would cause it to fall under an exception to the IRC’s grading

requirement.

Green testified he hired Armadillo Fences only after BNM walked off the job.

He stated he was concerned the house was not safe while the work was left undone.

After he sent the text to White saying he was going to hire someone else, White

never responded that BNM was willing and able to make the modifications

Lighthouse said were needed for the work to meet the report’s specifications. Green

agreed that the settlement agreement did not require BNM to install sod.

–5– George Francey, a general contractor with Armadillo Fences, testified he

generated the estimate of $8,600 for the drainage work based on the original

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Young v. Qualls
223 S.W.3d 312 (Texas Supreme Court, 2007)
Del Lago Partners, Inc. v. Smith
307 S.W.3d 762 (Texas Supreme Court, 2010)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Dallas Railway & Terminal Company v. Gossett
294 S.W.2d 377 (Texas Supreme Court, 1956)
Dorsett v. Cross
106 S.W.3d 213 (Court of Appeals of Texas, 2003)
Perry Homes v. Alwattari
33 S.W.3d 376 (Court of Appeals of Texas, 2001)
St. Joseph Hospital v. Wolff
94 S.W.3d 513 (Texas Supreme Court, 2002)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Vickery v. Commission for Lawyer Discipline
5 S.W.3d 241 (Court of Appeals of Texas, 1999)
Browning-Ferris, Inc. v. Reyna
865 S.W.2d 925 (Texas Supreme Court, 1994)
Ebby Halliday Real Estate, Inc. v. Murnan
916 S.W.2d 585 (Court of Appeals of Texas, 1996)
LITTON LOAN SERVICING, LP v. Manning
366 S.W.3d 837 (Court of Appeals of Texas, 2012)
CCC Group, Inc. v. South Central Cement, Ltd.
450 S.W.3d 191 (Court of Appeals of Texas, 2014)
McGinty v. Hennen
372 S.W.3d 625 (Texas Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
BNM Ventures, LLC v. Shannon Green, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bnm-ventures-llc-v-shannon-green-texapp-2023.