BME & Sons, Inc. v. Cobow Pacific, LLC.

CourtSuperior Court of Guam
DecidedDecember 31, 2014
DocketCV0751-13
StatusUnknown

This text of BME & Sons, Inc. v. Cobow Pacific, LLC. (BME & Sons, Inc. v. Cobow Pacific, LLC.) is published on Counsel Stack Legal Research, covering Superior Court of Guam primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BME & Sons, Inc. v. Cobow Pacific, LLC., (superctguam 2014).

Opinion

6 IN THE SUPERIOR COURT OF GUAM 7

8 BME & SONS, INC., CIVIL CASE NO. CV0751-13 9 Plaintiff v. 10 FINDINGS OF FACT & COBOW PACIFIC, LLC., CONCLUSIONS OF LAW II

12 Defendant. 13

14 INTRODUCTION 15 This matter came before the Honorable Vernon P. Perez for a bench trial on July 25 & 16 28, 2014. Attorney Phillip Torres represented the Plaintiff. Defendant, prose, was represented 17 by Isagani Z. Dayao, Vice-President of Cobow Pacific, LLC. Having considered the evidence 18 presented, the Court hereby makes the following findings of fact and conclusions of law. 19 FINDINGS OF FACT 20 By a preponderance of the evidence, the Court makes the following findings of fact. 21 1. Plaintiff BME & Sons, Inc. ("Plaintiff' or "BME") and Defendant Co bow Pacific, LLC. 22 ("Defendant" or "Cobow"), are both licensed construction companies on Guam that 23 provide labor and engineering services. 24 2. In November of 2012, Defendant, through Vice President and General Manager Isagani 25 Z. Dayao Jr. ("Dayao" or "Jun"), sought assistance from Plaintiff, through its 26 Administrative Manager, Bernie Maranan ("Maranan"), to provide manpower for 27 Defendant's construction project at Christian Dior, DFS Guam ("Dior Project"). 28

BME, Inc. & Sons v. Cobow Pacific, LLC. Case No. CV0751-13 Findings of Fact & Conclusions of Law ORIGINAL Page 1 of8 3. Plaintiff agreed to assist Defendant and the terms of that agreement were memorialized 2 by an employee of Plaintiff's at Plaintiff's office. The agreement provided, in relevant 3 part: Dear Mr. Dayao, 4 [BME] would like to propose an initial estimated amount of USD Fifteen 5 thousand Only ($15,000.00) to provide construction Labor only for the completion of the above project. Any amount in excess of the contract 6 amount will be charged accordingly. $ 25.00 I hour- regular hour 7 $ 30.00 I hour- overtime hour 8 (Def's Ex. I, Jul. 22, 2014). (emphasis added). 9

10 4. The project referred to was that described on the agreement as "DIOR Interior Fit-out, II DFS Galleria." ld. 12 5. Plaintiff sent Defendant an initial list of employees who could be assigned to the project. 13 6. On November 7, 2012, Defendant requested the names of additional workers who could 14 be assigned to the project over the next week. Plaintiff provided Defendant with that 15 list. 16 7. After November 13, 2012, Defendant made additional requests for workers who could 17 be assigned to the Dior project and also to a second project at Bottega Veneta, located at 18 the Plaza Guam ("Bottega Project"). 19 8. On November 20, 2012, Maranan sent an email to Dayao informing him of the need for 20 BME to adjust the original rates. That email stated: 21 Jun, during our discussion you just need man power support for a week and the overtime is minimal that's why I agreed on the rate I gave you. 22 Please be informed that we are also paying overtime to our workers for time in half for 30 dollars is not enough for our overhead. 23

24 Jun, because of our relationship I agree for the above cost knowing that it will only takes 7 days from November 6 to 13[,] 2012. Jun be known that 25 I even sacrifice my own project to support you. Please considered adjustment cost for $30.00 skilled workers and paying time half on 26 overtime, this new charges will start on 11-14-2012. Please advise me if 27 you are in agreed to this rate. 28 (Def's Ex. B, Apr. 16, 2014).

BME, Inc. & Sons v. Cobow Pacific, LLC. Case No. CV0751-13 Findings of Fact & Conclusions of Law

Page 2 of8 2

3 9. That same day, Dayao replied to Maranan's email and stated in relevant part: "Sorry I 4 was busy in the middle of getting the subject project prepared for shop opening so I was 5 not able to speak with you. Anyway, I really appreciate your valuable support and 6 continued assistance." !d. 7 10. Plaintiff sent invoices for its services to Defendant. The invoices reflect the $25 and $30 8 rates charged for work performed between November 7 and 13, 2012. After November 9 13, 2012, the invoices reflect the higher rates of $3 0 and $41. 10 11. On December 14, 2012, Maranan sent another email to Dayao, which stated in relevant II part: 12 After !(sic) week you are requesting more man power for another project at DFS Gallery for Christian Dior 1, after knowing this request I 13 immediately send you e-mail that will have cost adjustment, please see below email. 14 As I mention to you I sacrifice my project just to support you. I have big 15 cost on my overhead plus I get additional wage bond to this project. My charges to you is not overkill as you mention during our telecom 16 conversation. As you requested to reduce overtime pay, the most we can do is $41.00 dollars per overtime pay. 17

18 (Def's. Ex. C, Apr. 16, 2014).

19 12. Defendant paid for most of what was owed on the invoices except for the unpaid amount 20 that Plaintiff's seek in this action ($9,085.80). (Digital Recording at 11:02:52, Jul 25, 21 2014). 22 13. In response to Plaintiff's numerous attempts to collect on the unpaid balance, Defendant 23 largely attributed its delay in payment to nonpayment from Christian Dior. 24 II 25 II 26

28 1 The evidence suggests that Maranan erroneously referenced the Dior Project instead of the Bottega Project.

BME, Inc. & Sons v. Cobow Pacific, LLC. Case No. CV0751-13 Findings of Fact & Conclusions of Law

Page 3 of8 CONCLUSIONS OF LAW 2 14. To create an enforceable contract, there must be an offer, acceptance, and consideration. 3 See Mobil Oil v. Tendido, 2004 Guam 7 ~ 34; see also 18 GCA § 85102 (2014)("It is 4 essential to the existence of a contract that there should be: 1) Parties capable of 5 contracting; 2) Their consent; 3) A lawful object; and 4) A sufficient cause or 6 consideration."). 7 15. In this case, the parties each signed a letter on November 6, 2012, the subject of which 8 was described as a "Cost Proposal to provide construction labor." (Def.'s Ex. I, Nov. 6, 9 2012). Contained in the letter was Plaintiffs offer to provide Defendant with 10 construction labor for an initial amount of $15,000.00 and specific rates to be applied for 11 excess work. The signatures of both parties demonstrate Plaintiffs offer, Defendant's 12 acceptance, and the consideration to be provided. Accordingly, the letter serves as an 13 enforceable contract between the two parties. 14 16. Guam contract law provides that "[t]he language of a contract is to govern its 15 interpretation, if the language is clear and explicit, and does not involve an absurdity." 16 18 GCA § 87104 (2014). Further, "[w]hen a contract is reduced to writing, the intention 17 of the parties is to be ascertained from the writing alone, if possible subject, however, to 18 the other provisions ofthis chapter." 18 GCA § 87105 (2014). 19 17. In addressing what evidence is to be considered in contract interpretation, the Supreme 20 Court of Guam confirmed that this jurisdiction adheres to the "traditional approach." 21 Wasson v. Berg, 2007 Guam 16 ~ 16; see also Guam United Warehouse Corp.v. Dewitt 22 Transp. Servs.,2003 Guam 20 ~ 24 ("[W]e 'look to the ... four corners to determine the 23 parties' intentions, which are controlling.' ... 'Ifthe language within the four corners of 24 the contract is unambiguous, then a court does not resort to extrinsic evidence of the 25 contracts meaning, and a court determines the parties intentions from the plain meaning 26 of the contractual language as a matter of law."') (internal citations omitted). 27 18. In this case, the parties first dispute whether the agreed upon rates was for one week or 28 for the completion of Defendant's project. Plaintiff argues for the former and Defendant

BME, Inc. & Sons v. Cobow Pacific, LLC. Case No. CV0751-13 Findings of Fact & Conclusions of Law

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Diamond Woodworks, Inc. v. Argonaut Insurance
135 Cal. Rptr. 2d 736 (California Court of Appeal, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
BME & Sons, Inc. v. Cobow Pacific, LLC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bme-sons-inc-v-cobow-pacific-llc-superctguam-2014.