Blumenthal Kahn Electric Ltd. Partnership v. Bethlehem Steel Corp.

708 A.2d 1, 120 Md. App. 630, 1998 Md. App. LEXIS 83
CourtCourt of Special Appeals of Maryland
DecidedApril 6, 1998
Docket203, Sept. Term, 1997
StatusPublished
Cited by3 cases

This text of 708 A.2d 1 (Blumenthal Kahn Electric Ltd. Partnership v. Bethlehem Steel Corp.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blumenthal Kahn Electric Ltd. Partnership v. Bethlehem Steel Corp., 708 A.2d 1, 120 Md. App. 630, 1998 Md. App. LEXIS 83 (Md. Ct. App. 1998).

Opinion

BYRNES, Judge.

This appeal is from a judgment entered against appellant Blumenthal-Kahn Electrical Limited Partnership, in the Circuit Court for Baltimore County, on a contract claim by Bethlehem Steel Corporation. Blumenthal initiated suit, alleging that Bethlehem Steel had breached an electrical services contract between the companies by failing to pay Blu-menthal the final balance for services performed. Bethlehem counterclaimed, alleging that Blumenthal was itself in breach by virtue of its defective performance and subsequent refusal to correct its work.

*633 The case was tried by the circuit court, sitting without a jury. The court ruled against Blumenthal on its contract claim and in favor of Bethlehem Steel on its counterclaim. It awarded Bethlehem Steel damages in the sum of $189,345.00. On appeal, Blumenthal presents the following questions for review, which we have rephrased slightly:

I. Was the trial court’s factual finding that Blumenthal-Kahn breached its contract with Bethlehem Steel by improperly locating electrical stubouts in sections one through four of a twelve section tunnel project clearly erroneous?
II. Did the trial court err in interpreting the language of the contract between Blumenthal-Kahn and Bethlehem Steel so as not to require Bethlehem Steel to avoid additional losses caused by its failure to inspect or negligent inspection and, thus, mitigate its damages?

Our review of the record reveals that the trial court’s factual findings were not clearly erroneous and that there was no error in its interpretation of the contract language. Accordingly, we affirm the judgments entered below.

FACTS

In 1991, Blumenthal and Bethlehem Steel entered into an electrical services contract in connection with the construction of an underwater tunnel. The Massachusetts State Highway Department had approved the Boston Central Artery Tunnel project to extend the Massachusetts Turnpike from south Boston to an area near Logan Airport, through the Boston Harbor. A large number of contractors formed a joint venture for the project. Morrison, Knudsen, Interboten and White (“MKIW”), a “sponsoring partner” of the joint venture, contracted with Bethlehem Steel to fabricate twelve 300 foot tunnel sections at Bethlehem Steel’s Sparrows Point plant. Bethlehem Steel was to build the steel tubes constituting the tunnel sections; install within the tubes a gridwork of reinforcing steel (known as “rebar”), electrical fittings, and mechanical fittings; stabilize the tubes with a small amount of *634 concrete; and deliver them to Boston by barge. Once in Boston, the tubes would be submerged in the Boston Harbor, joined end to end, and encased in concrete, which would be poured around their interiors and exteriors over form plates.

Blumenthal subcontracted with Bethlehem Steel to install the electrical fittings, including junction boxes, conduit connections, and exit points, called “stubouts,” from the junction boxes to the interior tunnel walls. The electrical fittings were to be installed behind the rebar grid. Because the electrical fittings were to be embedded in concrete, the stubouts were needed, and allowed, for installation of lighting systems, traffic control systems, fire alarms, and other electrical workings inside the tunnel. Each tunnel section was to have 54 stub-outs. The terms of the contract required, and Massachusetts State regulations dictated, that the stubouts be located at uniform heights throughout the tunnel sections.

Bethlehem Steel agreed to pay Blumenthal $1,411,490.72 for the electrical work it was to perform under the tunnel project subcontract. Blumenthal was to invoice Bethlehem Steel monthly for work performed, with a ten percent retention payable upon completion and acceptance of all work.

In determining the correct stubout locations, Blumenthal referred to drawings that accompanied and were part of the contract. The drawings specified that the stubouts were to be situated two feet above the ceiling height of the tunnel. Blumenthal could not determine the precise stubout locations, however, as the drawings did not specify the tunnel ceiling height. Blumenthal asked Bethlehem Steel for that specification, and Bethlehem Steel in turn made inquiry of MKIW. MKIW informed Bethlehem Steel that the ceiling tunnel height was 9’8” above the horizontal axis. Bethlehem Steel then conveyed this specification to Blumenthal.

Bethlehem Steel constructed the tunnel sections two at a time, in reverse order, beginning with section twelve. Blu-menthal completed the electrical work in tunnel sections five through twelve, and, following inspection by employees of Bethlehem Steel at Sparrows Point, those sections were *635 shipped to Boston. After they were submerged in the Boston Harbor and encased in concrete, MKIW notified Bethlehem Steel that some of the stubouts were incorrectly located. Upon further investigation, MKIW determined that the 9’8” ceiling dimension originally given to Bethlehem Steel, and conveyed to Blumenthal-Kahn, was inaccurate. The proper ceiling dimension actually was 11’8” above the horizontal axis. By the time that this discovery was made, however, Blumen-thal had commenced work on tunnel sections one through four. Bethlehem Steel paid Blumenthal-Kahn an additional sum to revise its work in those tunnel sections, so as to conform to the amended ceiling height.

Upon completion of the electrical work for tunnel sections one through four, employees of Bethlehem Steel inspected each tunnel section. Tubes one and four were inspected on May 28, 1993; tubes two and three were inspected on July 30, 1993. The inspections did not reveal any irregularities. Bethlehem Steel transported the sections from Sparrows Point to Boston, by barge. In February, 1994, after those sections had been submerged in the Boston Harbor and encased in concrete, MKIW informed Bethlehem Steel that the stubouts in those sections were not located properly either. In particular, the stubouts were not uniformly located; rather, they appeared at different heights and different locations in the interior walls of the tunnels.

MKIW and the Massachusetts State Highway Department demanded that Bethlehem Steel correct the stubout locations. Bethlehem Steel notified Blumenthal of the problem and demanded that it take action to correct the defect. Blumen-thal refused to do so, and notified Bethlehem Steel that it was disclaiming liability for the improperly placed stubouts. Thereafter, Bethlehem Steel informed Blumenthal that it was reserving its right to take action against it, and proceeded to correct the stubout locations in sections one through four itself, at a cost of $277,147.00.

Blumenthal issued a final invoice to Bethlehem Steel for the contract retainage amount of $144,149.07. After Bethlehem *636 Steel refused to pay, asserting that Blumenthal had breached the contract, Blumenthal filed suit against Bethlehem Steel, in the Circuit Court for Baltimore County, seeking the retainage sum as damages. Bethlehem Steel counterclaimed for the costs it had incurred in relocating the electrical stubouts. 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Pittsburgh Water and Sewer Authority v. UCBR
Commonwealth Court of Pennsylvania, 2020
Cent. Ohio Med. Textiles v. PSC Metal, Inc.
2020 Ohio 591 (Ohio Court of Appeals, 2020)
Mais v. Allianz Life Insurance Co. of North America
34 F. Supp. 3d 754 (W.D. Michigan, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
708 A.2d 1, 120 Md. App. 630, 1998 Md. App. LEXIS 83, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blumenthal-kahn-electric-ltd-partnership-v-bethlehem-steel-corp-mdctspecapp-1998.